| IN THE SUPREME COURT OF VICTORIA |
AT MELBOURNE
COMMON LAW DIVISION
JUDICIAL REVIEW AND APPEALS LIST
No. 8722 of 2009
| PAUL CARDONA and LAUREN BROWNSCOMBE | Appellants |
| v | |
| ROD BROWN and WENDY BROWN | Respondents |
---
JUDGE: | Pagone J | |
WHERE HELD: | Melbourne | |
DATE OF HEARING: | 9 August 2010 | |
DATE OF JUDGMENT: | 23 August 2010 | |
CASE MAY BE CITED AS: | Cardona & Anor v Brown & Anor | |
MEDIUM NEUTRAL CITATION: | [2010] VSC 368 | |
---
JUDICIAL REVIEW - Decision of VCAT – Building Contract – Domestic Building Contracts Act 1995 (Vic) – Entitlement to claim for construction stages dependent on separate definitions – Proper construction of “lock up stage” – Repudiation and suspension of contract.
---
APPEARANCES: | Counsel | Solicitors |
| For the Appellants | Mr J Digby QC and Mr B Miller | Simon Parsons & Co Lawyers |
| For the Respondents | Mr R Edmunds | Littleton Hackford & D’Alessandro Solicitors |
HIS HONOUR:
The plaintiffs (“the owners”) seek to set aside orders made by VCAT in favour of the defendants (“the builders”). On 7 August 2009 VCAT, constituted by Deputy President Macnamara, ordered that the owners pay the builders $125,431.17 together with costs.
The dispute between the parties arises from the performance of a building contract between them for the builders to construct a brick veneer dwelling on the owners’ land for the sum of $245,245.00. A building permit was issued by a private building surveyor, Mr Roger Kidd, and the builders commenced the works around 22 September 2006. The strip footings were poured, stumps were installed, base brick work was completed and the base stage progress payments were paid on 16 November 2006. On 4 December 2006 the builders requested payment of the frame stage progress payment pursuant to the contract. That claim of $36,786.75 was paid and, at around this time, the owners appeared to be happy with the work which had been completed although disagreement has since arisen about whether the frame stage progress payment claim could have been made. At some point there arose a significant dispute between the parties about the roof trusses which formed part of the work during the frame stage. That dispute was the trigger of subsequent disagreement between the owners and the builders but the state of the trusses is not directly relevant to the issues which I must decide which, rather, depend upon whether there was an error of law in the VCAT decision to enliven the Court’s jurisdiction under s 148 of the Victorian Civil and Administrative Tribunal Act 1998 (Vic).
On 14 February 2007 the owners received a progress claim for the lock-up stage payment of $85,835.75 which they refused to pay. On 6 March 2007 the builders suspended works in reliance upon clause 35 of the contract and the non payment of the lock-up stage progress payment. On 26 April 2007 the owners’ solicitors informed the solicitors for the builders that the claim for the lock-up stage payment could not have been made and, amongst other things, required the builders to return to the site to…
Continue reading Cardona v Brown
Sign in free to access the full text
- AGLC
- Cardona v Brown [2010] VSC 368
- Case
- [2010] VSC 368
- Decision Date
CaseChat Overview and Summary
The court was required to determine the proper interpretation of the "lock up stage" as defined by the Act, and how this definition impacted the appellant's entitlement to claim for construction stages. The court also had to consider whether the respondent's actions constituted a repudiation of the contract and whether the appellant's suspension of work was justified. These issues were critical in resolving the dispute over the enforcement of the building contract and the respective rights and obligations of the parties.
The court found that the definition of the "lock up stage" as per the Act did not align with the common understanding of the term. It held that the respondent's actions did not amount to a repudiation of the contract, and the appellant's suspension of work was not justified. The court concluded that the respondent was entitled to continue with the construction works as per the contract terms. The appeal was dismissed, and the decision of VCAT was upheld.
The final orders of the court were that the appeal was dismissed, and the decision of VCAT was confirmed. The respondent was entitled to proceed with the construction works, and the appellant's claims for additional costs related to the construction stages were not upheld.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.