SUPREME COURT OF THE AUSTRALIAN CAPITAL TERRITORY
Case Title: | Mohamed & Anor v Adrija Pty Ltd |
Citation: | [2017] ACTSC 158 |
Hearing Date: | 8 May 2017 |
DecisionDate: | 21 June 2017 |
Before: | Ashford AJ |
Decision: | 1. The appeal be upheld. 2. The judgment and orders of the Magistrates Court of 1 June 2016 be set aside. 3. The matter be remitted to the Magistrates Court for rehearing and determination in respect of the breach notices and of the “fixings complete” issue. 4. The Respondent pay the Appellants' costs of the appeal, unless there is any further submission. 5. Her Honour recommends that the parties attempt mediation. |
Catchwords: | APPEAL – CIVIL LAW – Appeal from the Magistrates Court – appeal against decision finding termination of contract lawful – appeal against damages arising from termination of contract – Magistrate erred in finding breach notice valid – substantive issues still requiring determination at first instance – matter in part remitted to the Magistrates Court CONTRACT – BUILDING CONTRACT – Termination of contract – whether failure to make payment at certain stage of contract entitles termination of the contract – validity of breach notice – Magistrate erred in not making any determination as the validity of the subsequent breach notices |
Cases Cited: | |
Parties: | Abdiwahaab Barkhdale Mohamed (First Appellant) Sagal Ahmed (Second Appellant) Adrija Pty Ltd (ACN 119 998 720) (Respondent) |
Representation: | Counsel Mr N Philpott (First and Second Appellants) Mr D Hand (Respondent) |
| Solicitors Starnet Legal (First and Second Appellants) Vertex Legal Group (Respondent) | |
File Number: | SCA 47 of 2016 |
Decision under appeal: | Court/Tribunal: ACT Magistrates Court Before: Magistrate Morrison Date of Decision: 1 June 2016 Case Title: Adrija Pty Ltd v Abdiwahaab Barkhadle Mohamed & Sagal Ahmed Court File Number: CS 504 of 2013 |
ASHFORD AJ:
Background to the appeal
By Notice of Appeal filed on 29 June 2016, the appellants appealed the decision of the ACT Magistrates Court made on 1 June 2016 and seek the decision be set aside and the proceedings remitted to the Magistrates Court for hearing and determination.
The three grounds of appeal as set out in the notice are:
(a)The learned Magistrate erred in finding that the respondent (‘the Builder’) was entitled to terminate the building contract with the appellants (‘the Owners’) on the basis that the Owners had failed to make payment on the “Fixings Complete” stage invoice.
Particulars:
(i)the building contract provided that the Builder was entitled to serve a progress payment for the “fixings complete” stage after the completion of the “fixings complete” stage as defined within the building contract;
(ii)the Builder served a progress payment claim upon the Owners in the sum of $54,750. The learned Magistrate found the works performed by the Builder under the building contract contained defects to the value of $25,130, being 46 per cent of the value of the “fixings complete” stage claim;
(iii)the Builder was therefore not…
Continue reading Mohamed v Adrija Pty Ltd
Sign in free to access the full text
- AGLC
- Mohamed v Adrija Pty Ltd [2017] ACTSC 158
- Case
- [2017] ACTSC 158
- Decision Date
CaseChat Overview and Summary
The court found that the Magistrate had erred in not determining the validity of the breach notices, which were critical to the decision. The court held that the Magistrate had overlooked the requirement to assess the validity of the breach notices before deciding on the termination and damages. As a result, the court concluded that the substantive issues regarding the validity of the breach notices and the “fixings complete” issue still required determination at first instance. The court set aside the Magistrates Court's judgment and orders and remitted the matter to the Magistrates Court for rehearing and determination of these issues. The appeal was upheld, and the matter was remitted for further proceedings.
The court ordered that the judgment and orders of the Magistrates Court be set aside, and the matter be remitted to the Magistrates Court for rehearing and determination of the issues regarding the breach notices and the “fixings complete” issue. The respondents were ordered to pay the appellants' costs of the appeal, unless there was any further submission. The court also recommended that the parties attempt mediation.
Orders
Orders of the court
1. The appeal be upheld.
2. The judgment and orders of the Magistrates Court of 1 June 2016 be set aside.
3. The matter be remitted to the Magistrates Court for rehearing and determination in respect of the breach notices and of the “fixings complete” issue.
4. The Respondent pay the Appellants' costs of the appeal, unless there is any further submission.
5. Her Honour recommends that the parties attempt mediation.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.