| CITATION: | Zachary Developments Pty Ltd v Turner and Anor [2012] QCATA 86 |
| PARTIES: | Zachary Developments Pty Ltd (Applicant/Appellant) |
| v | |
| Wayne Turner (First Respondent) Judith Elaine Turner (Second Respondent) |
| APPLICATION NUMBER: | APL027-11 / APL413-11 |
| MATTER TYPE: | Appeals |
| HEARING DATE: | On the papers |
| HEARD AT: | Brisbane |
| DECISION OF: | Mr Charles Brabazon QC, Member |
| DELIVERED ON: | 31 May 2012 |
| DELIVERED AT: | Brisbane |
| ORDERS MADE: | APL027-11 1. Set aside the adjudicator’s decision of 23 December 2011. 2. Order that the respondents pay $8,963 to the applicant. 3. Order that each party bear their own costs of the proceedings, after 26 September 2011. APL413-11 1. Order that the adjudicator’s costs order of 26 September 2011 be confirmed. 2. Order that each party bear their own costs of the proceeding, up to and including 26 September 2011. |
| CATCHWORDS: | Appeal – substantial performance – quantum meruit payment Costs – substantial delays – discretion – no order as to costs |
APPEARANCES and REPRESENTATION (if any):
This matter was heard and determined on the papers pursuant to s 32 of the Queensland Civil and Administrative Tribunal Act 2009 (QCAT Act).
REASONS FOR DECISION
Introduction – the Building Appeal
This is a most unfortunate building dispute, about an extension to Mr and Mrs Turners’ house. The contract is dated 16 July 2001. This appeal by the builder is from a judgment by the adjudicator dated 23 December 2010. The adjudicator ordered the builder to pay $31,878.26 to Mr and Mrs Turner. Each party seems to have been responsible for long delays.
The Dispute
Some explanation of the project is necessary. The Turners’ existing house was a two storey rectangle, the long side facing the street. The plans show an additional rectangular building, of two stories, to be built behind the existing house. The gap between them was to be some 4 metres. The bridging of that gap is the source of much of this dispute. The plans show concrete floors, at ground level and first floor level to connect the two buildings. They show balconies at each end, with bi-fold doors, to give security. The plans show a roof covering the gap. It is to be pitched, built on trusses, and covered with translucent panels, so that rain will run down into the gutters of the parallel buildings. The enclosed space is called a “breezeway”.
The work had unusual features that became sources of the dispute. The contract included Mrs Turner’s letter of 8 June 2001. The Turners had already done work on the site, such as soil tests, and the construction of a sanitary pipe to the nearby sewer. They agreed to supply quite a lot of building materials. Her letter sets out the details of their contribution at length.
The history of the work, and the parties’ disputes, is set out in the adjudicator’s judgment given on 23 December 2010. The contract price for the job was $132,000. The builder has been paid $85,000, for stages 1, 2 and 3. Stage 3 was the “enclosed stage”, and payment…
Keep reading for free
Create a free CaseChat account to read Zachary Developments Pty Ltd v Turner and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2012] QCATA 86
- Decision Date
CaseChat Overview and Summary
The court was required to decide if the applicant had substantially performed the contract and whether a quantum meruit payment was appropriate. The court also needed to consider the costs of the proceedings and whether any orders should be made in relation to those costs. The court had to balance the principles of fairness and the law of contract in making its decisions.
The court found that the applicant had substantially performed the contract, but the respondent had not substantially performed. The court ordered that the adjudicator’s decision be set aside and that the respondent pay the applicant $8,963. The court also ordered that each party bear their own costs of the proceedings after 26 September 2011, and that the adjudicator’s costs order be confirmed for the costs incurred up to and including 26 September 2011. The court found that there were substantial delays in the proceedings, but it exercised its discretion not to make any order as to costs.
Orders
Orders of the court
APL027-11
1. Set aside the adjudicator’s decision of 23 December 2011.
2. Order that the respondents pay $8,963 to the applicant.
3. Order that each party bear their own costs of the proceedings, after 26 September 2011.
APL413-11
1. Order that the adjudicator’s costs order of 26 September 2011 be confirmed.
2. Order that each party bear their own costs of the proceeding, up to and including 26 September 2011.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.