QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION:
CapFF Pty Ltd v Queensland Building and Construction Commission and Anor [2020] QCAT 408
PARTIES: CAPFF PTY LTD (applicant)
v
QUEENSLAND BUILDING AND CONSTRUCTION COMMISSION (first respondent)
PACIFIC DEVELOPMENTS GROUP PTY LTD
(second respondent)
APPLICATION NO/S:
GAR392-19
MATTER TYPE:
Building matters
DELIVERED ON:
26 October 2020
HEARING DATES:
30 September 2020 and 1 October 2020
HEARD AT:
Brisbane
DECISION OF:
Member McVeigh
ORDERS: 1. The Queensland Building and Construction Commission’s decision reference number 563341 made on 18 September 2019 be set aside.
2. The owner, CapFF Pty Ltd, is entitled to indemnity under the statutory insurance scheme.
CATCHWORDS: ADMINISTRATIVE LAW – ADMINISTRATIVE TRIBUNALS – QUEENSLAND CIVIL AND ADMINISTRATIVE TRIBUNAL – where a statutory insurance scheme is in place pursuant to s 67X of the Queensland Building and Construction Commission Act 1991 (Qld) – where a claim has been made in relation to termination of a contract of a dwelling house under the insurance policy conditions – whether termination is valid
Queensland Building and Construction Commission Act 1991 (Qld), s 67X
APPEARANCES & REPRESENTATION:
Applicant:
J Hughes instructed by McCullough Robertson
First Respondent:
R Ensby of Gadens Lawyers
Second Respondent:
J Dudley instructed by Crouch and Lyndon
REASONS FOR DECISION
Introduction
This is an application to review a decision of the Queensland Building and Construction Commission (QBCC).
By contract dated 31 August 2019, CapFF Pty Ltd (owner) engaged Pacific Developments Group Pty Ltd (contractor) to construct a home (contract).
On 9 February 2019 representatives of the owner and the contractor signed a revised payment schedule (payment schedule). In addition to a deposit and payment on practical completion, the owner was to pay on completion of 16 designated stages (the deposit and payment for the first four stages was noted as made on the payment schedule).
On 22 March 2019 the contractor issued an invoice for ‘Balance on stage 16, electrical fit off, plumbing fit off and solar installed.’
The owner did not pay that invoice.
On 7 April 2019 the owner wrote to the contractor listing 38 ‘outstanding items’.
On 8 April 2019 Mr Hudspith (the governing mind of the contractor) emailed Mr McDonell (the governing mind of the owner) advising that ‘as the invoices are about 10 days overdue there will be no further works undertaken till such time as they are paid’.
By letter dated 16 April 2019 the owner’s solicitors gave the contractor notice of intention to terminate pursuant to clause 20 of the contract, unless the contractor remedied alleged substantial breaches of the contract within 10 business days of receipt of the notice. The alleged substantial breaches were failing to proceed with due diligence and unlawfully suspending the works.
Mr Hudspith responded by letter dated 20 April 2019. He maintained that the owner was in breach of contract due to failure to pay outstanding invoices and that the builder was…
Keep reading for free
Create a free CaseChat account to read CapFF Pty Ltd v Queensland Building and Construction Commiss... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2020] QCAT 408
- Decision Date
CaseChat Overview and Summary
The court examined the statutory framework and the specific contractual conditions to determine whether the owner’s failure to pay the Stage 16 claim invalidated the contract termination. The court applied the principle that the doctrine of substantial performance does not apply in this context and that the completion of work must meet the precise contractual definitions. The court also considered the case of Thompson Residential Pty Ltd v Hart, which provided guidance on assessing whether a staged payment claim has been made prematurely. In applying these principles, the court concluded that the practical completion of the work must align with the detailed contractual definitions rather than general business practices or functional considerations. The court held that the owner’s non-payment did not invalidate the termination, as the primary focus was on whether the work met the contractual definitions.
Based on its findings, the court set aside the QBCC’s decision that the contract was not validly terminated. The court determined that CapFF Pty Ltd was entitled to indemnity under the statutory insurance scheme, as the owner had validly terminated the contract. This decision underscores the importance of precise contractual compliance and the practical interpretation of staged payment claims in construction contracts.
ORDERS:
1. The Queensland Building and Construction Commission’s decision reference number 563341 made on 18 September 2019 be set aside.
2. The owner, CapFF Pty Ltd, is entitled to indemnity under the statutory insurance scheme.
Orders
Orders of the court
1. The Queensland Building and Construction Commission’s decision reference number 563341 made on 18 September 2019 be set aside.
2. The owner, CapFF Pty Ltd, is entitled to indemnity under the statutory insurance scheme.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.