CapFF Pty Ltd v Queensland Building and Construction Commission

Link copied
Case Copied 23 min read

QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL


CITATION:

CapFF Pty Ltd v Queensland Building and Construction Commission and Anor [2020] QCAT 408

PARTIES: CAPFF PTY LTD

(applicant)

v

QUEENSLAND BUILDING AND CONSTRUCTION COMMISSION

(first respondent)

PACIFIC DEVELOPMENTS GROUP PTY LTD

(second respondent)

APPLICATION NO/S:

GAR392-19

MATTER TYPE:

Building matters

DELIVERED ON:

26 October 2020

HEARING DATES:

30 September 2020 and 1 October 2020

HEARD AT:

Brisbane

DECISION OF:

Member McVeigh

ORDERS:

1.   The Queensland Building and Construction Commission’s decision reference number 563341 made on 18 September 2019 be set aside.

2.   The owner, CapFF Pty Ltd, is entitled to indemnity under the statutory insurance scheme.

CATCHWORDS:

ADMINISTRATIVE LAW – ADMINISTRATIVE TRIBUNALS – QUEENSLAND CIVIL AND ADMINISTRATIVE TRIBUNAL – where a statutory insurance scheme is in place pursuant to s 67X of the Queensland Building and Construction Commission Act 1991 (Qld) – where a claim has been made in relation to termination of a contract of a dwelling house under the insurance policy conditions – whether termination is valid

Queensland Building and Construction Commission Act 1991 (Qld), s 67X

Thompson Residential Pty Ltd v Hart [2014] QDC 132, applied

APPEARANCES & REPRESENTATION:

Applicant:

J Hughes instructed by McCullough Robertson

First Respondent:

R Ensby of Gadens Lawyers

Second Respondent:

J Dudley instructed by Crouch and Lyndon

REASONS FOR DECISION

Introduction

  1. This is an application to review a decision of the Queensland Building and Construction Commission (QBCC).

  2. By contract dated 31 August 2019, CapFF Pty Ltd (owner) engaged Pacific Developments Group Pty Ltd (contractor) to construct a home (contract). 

  3. On 9 February 2019 representatives of the owner and the contractor signed a revised payment schedule (payment schedule).  In addition to a deposit and payment on practical completion, the owner was to pay on completion of 16 designated stages (the deposit and payment for the first four stages was noted as made on the payment schedule). 

  4. On 22 March 2019 the contractor issued an invoice for ‘Balance on stage 16, electrical fit off, plumbing fit off and solar installed.’

  5. The owner did not pay that invoice.

  6. On 7 April 2019 the owner wrote to the contractor listing 38 ‘outstanding items’. 

  7. On 8 April 2019 Mr Hudspith (the governing mind of the contractor) emailed Mr McDonell (the governing mind of the owner) advising that ‘as the invoices are about 10 days overdue there will be no further works undertaken till such time as they are paid’. 

  8. By letter dated 16 April 2019 the owner’s solicitors gave the contractor notice of intention to terminate pursuant to clause 20 of the contract, unless the contractor remedied alleged substantial breaches of the contract within 10 business days of receipt of the notice.  The alleged substantial breaches were failing to proceed with due diligence and unlawfully suspending the works. 

  9. Mr Hudspith responded by letter dated 20 April 2019.  He maintained that the owner was in breach of contract due to failure to pay outstanding invoices and that the builder was…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read CapFF Pty Ltd v Queensland Building and Construction Commiss... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2020] QCAT 408
Decision Date

CaseChat Overview and Summary

CapFF Pty Ltd filed an application to review a decision made by the Queensland Building and Construction Commission (QBCC) in relation to a contract for the construction of a dwelling house. The central dispute is whether the contract was validly terminated by the owner, CapFF Pty Ltd, which is a prerequisite for the owner to make a claim under the statutory insurance scheme established by the Queensland Building and Construction Commission Act 1991 (Qld). The contractor contends that the contract was not validly terminated as the owner was in substantial breach by not paying the claim for Stage 16 works within the prescribed period. Conversely, CapFF Pty Ltd argues that it was not obliged to pay the Stage 16 claim because the contractor did not complete the works by the stipulated date. The court must decide if the owner’s non-payment of the Stage 16 claim invalidates the termination and if the owner was legally required to make that payment.

The court examined the statutory framework and the specific contractual conditions to determine whether the owner’s failure to pay the Stage 16 claim invalidated the contract termination. The court applied the principle that the doctrine of substantial performance does not apply in this context and that the completion of work must meet the precise contractual definitions. The court also considered the case of Thompson Residential Pty Ltd v Hart, which provided guidance on assessing whether a staged payment claim has been made prematurely. In applying these principles, the court concluded that the practical completion of the work must align with the detailed contractual definitions rather than general business practices or functional considerations. The court held that the owner’s non-payment did not invalidate the termination, as the primary focus was on whether the work met the contractual definitions.

Based on its findings, the court set aside the QBCC’s decision that the contract was not validly terminated. The court determined that CapFF Pty Ltd was entitled to indemnity under the statutory insurance scheme, as the owner had validly terminated the contract. This decision underscores the importance of precise contractual compliance and the practical interpretation of staged payment claims in construction contracts.

ORDERS:
1. The Queensland Building and Construction Commission’s decision reference number 563341 made on 18 September 2019 be set aside.
2. The owner, CapFF Pty Ltd, is entitled to indemnity under the statutory insurance scheme.

Orders

Orders of the court

1. The Queensland Building and Construction Commission’s decision reference number 563341 made on 18 September 2019 be set aside.

2. The owner, CapFF Pty Ltd, is entitled to indemnity under the statutory insurance scheme.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

On review the QBCC overturned the initial decision (decision). On 18 September 2019 the QBCC notified the owner that it had decided that the contract had not been validly terminated by the owner. On 16 October 2019 the owner filed this application to review the decision. On 14 January 2020 the contractor was joined as the second respondent. The ultimate issue is the entitlement of the owner to claim for non-completion under the statutory insurance scheme. If the owner validly terminated, it is entitled to make the claim. The contractor argues that the owner did not validly terminate because the owner was in substantial breach of contract as it had not paid the claim for the Stage 16 works within the period prescribed by the contract. The owner accepts that it had not paid the claim for the stage 16 works, but denies it was obliged to pay, on the basis that the contractor was not entitled to make progress claim 16 on 22 March 2019 as it had not completed the Stage 16 works by 22 March 2019. The Queensland Building and Construction Commission Act 1991 (Qld) (QBCC Act) establishes a statutory insurance scheme to provide assistance to consumers of residential construction work that is incomplete.[1] [1]Section 67X(2), Queensland Building and Construction Commission Act 1991 (Qld). The statutory insurance scheme provides cover if a contract is validly terminated on the default of a licensed builder.[2] [2]Section 4 of Schedule 6 of the Queensland Building and Construction Commission Regulation 2018 (Qld). The QBCC’s decision that the contract was not validly terminated by the owner on the default of the builder is a reviewable decision under section 86(1)(i) of the QBCC Act. Thompson Residential Pty Ltd v Hart[3] is an analogous decision. It sets out the test to be applied in assessing whether a staged payment claim has been made prematurely. The doctrine of substantial performance does not apply.[4] When considering whether the work in question had reached the enclosed stage, His Honour Judge McGill SC stated:[5]… once the stages are defined by reference to particular work having been completed, or having reached a particular point, then what matters is whether that work has been completed or reached that point, not whether the work on the project has reached a stage which could reasonably be characterised in terms of ordinary business practice as the equivalent of that. This follows from the fact that the stage is defined in some detail. Once the entitlement to a progress payment is based on the completion of a particular stage as defined, it is satisfaction of that definition rather than practical or functional considerations which determines whether the enclosed stage has been achieved for that purpose. …[3][2014] QDC 132.[4]Ibid, [70].[5]Ibid, [39]. Applying the law to the facts of the particular case, His Honour noted:[6]There remains the question … of just what is required before what has been done matches the description of the condition precedent in the contract. That I think is best resolved essentially as a practical question of fact, but it is necessary to ask the right question. The practical question is not whether what has been done can properly be described as a completion of “the enclosed stage”, but whether what has in fact been done can be said to constitute satisfaction of the definition of “enclosed stage” in the contract. Commercial contracts are usually to be interpreted in a commonsense practical way, and building contracts in particular need to be interpreted in a practical and workable fashion. But I do not think that justifies any substantial difference between what has occurred and what is required. Obviously the difference between what has occurred and what is required might be so slight or trivial that it could be said that in a practical sense the definition had been satisfied. Thus, if the owner could find one loose tile on the roof I do not think that it could be said that that in itself meant that it was not correct to say that the roof covering was fixed. [6]Ibid, [72].

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.