SUPREME COURT OF QUEENSLAND
CITATION:
Martinek Holdings Pty Ltd v Reed Construction (Qld) Pty Ltd [2009] QSC 328
PARTIES:
MARTINEK HOLDINGS PTY LTD
ACN 106 533 242
(applicant)
v
REED CONSTRUCTION (QLD) PTY LTD ACN 010 871 557(respondent)
FILE NO/S:
BS 10664 of 2009
DIVISION:
Trial Division
PROCEEDING:
Application
ORIGINATING COURT:
Supreme Court Brisbane
DELIVERED ON:
8 October 2009
DELIVERED AT:
Brisbane
HEARING DATE:
5 October 2009
JUDGE:
White J
ORDER:
The application is dismissed.
CATCHWORDS:
CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – OTHER MATTERS – whether the respondent should be restrained from seeking an adjudication certificate and filing a judgment in court pursuant to ss 30 and 31 of the Building and Construction Industry Payments Act 2001 (Qld)
Building and Construction Industry Payments Act 2004 (Qld), s 18, s 21, s 24, s 30, s 31, s 100
Property Law Act 1974 (Qld), s 57
Dobbs v National Bank of Australasia Ltd (1935) 53 CLR 643
John Holland Pty Ltd v Roads and Traffic Authority of NSW (2006) 66 NSWLR 624
RJ Neller Building Pty Ltd v Ainsworth [2008] QCA 397
Sutcliffe v Thackrah [1974] AC 727Wormall Pty Ltd v Marchese Investments Pty Ltd [2008] WADC 173
COUNSEL:
P Dunning SC, with GD Beacham, for the applicant
JK Bond SC, with M Ambrose, for the respondent
SOLICITORS:
McInnes Wilson Lawyers for the applicant
Holding Redlich Lawyers for the respondent
The applicant, Martinek Holdings Pty Ltd (“Martinek”), has applied for a stay of the Adjudication Decision dated 17 September 2009 made by the adjudicator, Paul Roberts, in relation to Adjudication Application No. 1064504_486 and ancillary orders. In reality it is seeking an order restraining the respondent, Reed Construction (Qld) Pty Ltd (“Reed”), from proceeding under ss 30 and 31 of the Building and Construction Industry Payments Act 2004 (Qld) (“the Payments Act”) to seek an Adjudication Certificate and file a judgment in this court. It is concerned that if the Adjudication Amount is paid to Reed it will not be recoverable because of concerns about Reed’s financial position.
On 31 July 2006 Martinek and Reed entered into a contract[1] for the construction of a development in Mackay known as the Rivage Development. Martinek was the Principal and Reed was the Contractor. The parties appointed Paul Worroll of Reddog Architects as Superintendent for the Contract.
[1]AS4000-1997 – General Conditions of Contract as amended.
Practical completion of the contract was achieved on 4 April 2008. The defects liability period was extended until 4 July 2009. The Superintendent in his letter to Reed noted:
“We do advise that under Clause 35 should the defects not be completed prior to the completion of the Defects Liability Period then the Principal has the right to have the rectification works carried out by others. The cost incurred shall be certified by the Superintendent as monies due and payable to the Principal…”
By letter dated 22 July 2009 to Reed, the Superintendent noted that the extended defects liability period finished on 4 July…
Keep reading for free
Create a free CaseChat account to read Martinek Holdings Pty Ltd v Reed Construction (Qld) Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2009] QSC 328
- Decision Date
CaseChat Overview and Summary
The primary legal issue before the court was whether the applicant had demonstrated sufficient grounds to warrant the issuance of an injunction to restrain the respondent from proceeding with the adjudication and subsequent court filing. The applicant argued that the respondent's actions were an abuse of process and would result in prejudice to the applicant. The court was tasked with evaluating the merits of these arguments and determining whether the applicant had met the threshold for obtaining such an injunction.
The court considered the evidence and submissions presented by both parties and concluded that the applicant had not demonstrated a sufficient likelihood of success on the merits of the case to warrant the issuance of an injunction. The court found that the respondent's actions were not an abuse of process and that the applicant had not shown any substantial prejudice that would result from the respondent proceeding with the adjudication and subsequent court filing. As a result, the application was dismissed, and no injunction was issued. The court emphasised the importance of adhering to the processes set out in the Building and Construction Industry Payments Act 2001 (Qld) and cautioned against seeking to restrain such processes without clear justification.
Orders
Orders of the court
The application is dismissed.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi