Su v Winning Builders Pty Ltd

Case [2024] NSWCATCD 44


Civil and Administrative Tribunal


New South Wales

Medium Neutral Citation: Su v Winning Builders Pty Ltd [2024] NSWCATCD 44
Hearing dates: 18 & 19 January 2023, 6 & 7 November 2023, Written Submissions dated 8 December 2023, 12 February 2024 & 11 March 2024
Date of orders: 13 June 2024
Decision date: 13 June 2024
Jurisdiction:Consumer and Commercial Division
Before: D G Charles, Senior Member
Decision:

1 Within 28 days of the date of these orders, the Respondent is to pay to the Applicants, the amount of $15,342.16.

2 A work order is made pursuant to s 48O(1)(c) of the Home Building Act 1989 NSW, on the terms and conditions as set out in [191] of the Reasons.

3 If any party seeks an order for costs of the Proceeding, orders and directions are made, as set out in [193] of the Reasons.

Catchwords:

BUILDING AND CONSTRUCTION – application of s 48O(1)(c) of the Home Building Act 1989 NSW – jurisdiction & discretion - work order to include items of incomplete work – other terms and conditions of work order - third party contractor condition in work order – no structural columns direction in work order - delay damages to owners – no contract price adjustment.

Legislation Cited:

Home Building Act 1989 NSW

Civil and Administrative Tribunal Act 2013 NSW

Civil and Administrative Tribunal Rules 2014 NSW

Cases Cited:

Brewarrina Shire Council v Beckhaus Civil Pty Ltd [2005] NSWCA 248

Little v J & K Homes Pty Ltd [2017] NSWCATAP 84

Project 4301 Pty Ltd v Buildcarp Constructions Pty Ltd [2022] NSWCATCD 30

Precise Builders (NSW) Pty Ltd v Hones & Krel [2018] NSWCATAP 112

Bellgrove v Eldridge [1954] HCA 36; (1954) 90 CLR 613

Aytul Ak Tankiz v Ferat Ak & Ramazan Ak [2014] NSWSC 1044

Tomlin v Ford Credit Australia [2005] NSWSC 540

Onassis v Vergottis [1968] 2 Lloyd’s Rep 403

Textralian Enterprises v Perpetual Trustees (Victoria) Limited [2000] NSWCA 176

HM&O Investments v Ingram [2012] NSWSC 958

ET-China.com International Holdings Ltd v Cheung [2021] NSWCA 24

Wright v Foresight Constructions Pty Ltd [2011] NSWCA 327

Paraiso v CBS Build Pty Ltd (2020) NSWSC 190

Bannister & Hunter v Transition Resort Holdings (No 3) (2013) NSWSC 1943

Tabcorp Holdings Ltd v Bowen Investments Pty Ltd [2009] HCA 8; (2009) 236 CLR 272

Westpoint Management Ltd v Chocolate Factory Apartments Ltd; Chocolate Factory Apartments v Westpoint Finance [2007] NSWCA 253

Owners SP 92450 v JKN Para 1 Pty Limited [2023] NSWCA 114

Brambles Holdings v Bathurst City Council [2001] NSWCA 61

Hadley v Baxendale [1854] EngR 296; (1854) 9 Ex 341; (1854) 156 ER 145

C.Czarnikow Ltd v Koufos [1969] 1 AC 350

Texts Cited:

None cited.

Category:Principal judgment
Parties:

Jiam Yu Su (First Applicant)

Bao Ling Zhao (Second Applicant)

Winning Builders Pty Ltd (Respondent)
Representation:

Counsel:

M Klooster (Applicants)

D Hughes & R Sud (Respondent)

Solicitors:

Construction Legal (Applicants)

Doyles Construction Lawyers (Respondent)
File Number(s): 2022/00430188 (formerly HB 22/18103)
Publication restriction: Unrestricted

REASONS FOR…

Continue reading Su v Winning Builders Pty Ltd

Sign in free to access the full text

Details
AGLC
Su v Winning Builders Pty Ltd [2024] NSWCATCD 44
Case
[2024] NSWCATCD 44
Decision Date

CaseChat Overview and Summary

In the case of Su v Winning Builders Pty Ltd, the applicants, the owners of a property, sought a work order under s 48O(1)(c) of the Home Building Act 1989 NSW against the respondent, a builder, due to incomplete and defective works. The dispute was heard and determined in the Consumer, Trader and Tenancies Tribunal of New South Wales. The applicants sought an order for the completion of the works, as well as compensation for delay damages caused by the respondent’s failure to complete the works within a reasonable time.

The primary legal issue before the court was whether the tribunal had the jurisdiction and discretion to make a work order that included the completion of items of incomplete work, and if so, what terms and conditions should be attached to the order. The court also had to determine whether the inclusion of a condition requiring the respondent to engage a third party contractor was appropriate, and whether the applicants were entitled to delay damages. Furthermore, the court needed to decide if the applicants were entitled to an adjustment to the contract price for the defective work.

The tribunal held that it had the jurisdiction and discretion to make a work order under s 48O(1)(c) of the Home Building Act 1989 NSW, and that the order should include the completion of the incomplete work. The court considered that the applicants were entitled to delay damages for the period of the delay caused by the respondent’s failure to complete the works within a reasonable time. The tribunal found that the inclusion of a condition requiring the respondent to engage a third party contractor was appropriate, given the circumstances of the case. However, the court declined to make an order for an adjustment to the contract price, as it found that the applicants had not provided sufficient evidence to support such a claim.

In summary, the tribunal made a work order in favour of the applicants, ordering the respondent to complete the incomplete work within 28 days and to pay delay damages of $15,342.16. The order also included a condition requiring the respondent to engage a third party contractor to carry out certain aspects of the work. The tribunal declined to make an order for an adjustment to the contract price.

Orders

Orders of the court

1 Within 28 days of the date of these orders, the Respondent is to pay to the Applicants, the amount of $15,342.16.

2 A work order is made pursuant to s 48O(1)(c) of the Home Building Act 1989 NSW, on the terms and conditions as set out in [191] of the Reasons.

3 If any party seeks an order for costs of the Proceeding, orders and directions are made, as set out in [193] of the Reasons.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.