Supreme Court
New South Wales
Medium Neutral Citation: Bannister & Hunter v Transition Resort Holdings [2013] NSWSC 1669 Hearing dates: 04/11/2013, 05/11/2013, 06/11/2013, 07/11/2013 Decision date: 07 November 2013 Jurisdiction: Equity Division - Technology and Construction List Before: McDougall J Decision: Evidence taken on voir dire to be admitted for all purposes.
Catchwords: PRACTICE & PROCEDURE - pleadings - whether claim sufficiently particularised - whether sufficient notice of claim provided - where failure to adduce relevant expert evidence - no question of principle Category: Procedural and other rulings Parties: Bannister & Hunter Pty Ltd (Plaintiff/First Cross-Defendant)
Transition Resort Holdings Pty Ltd (Defendant/Cross-Claimant)
Peter William Barclay (Second Cross-Defendant)Representation: Counsel:
MJ Windsor SC / G Gemmell (Plaintiff/First Cross-Defendant)
DS Weinberger (Defendant/Cross-Claimant)
Solicitors:
Indemnity Legal Pty Ltd (Plaintiff)
Gadens Lawyers (Defendant/Cross-Claimant)
File Number(s): 2010/41432
Judgment - (ex tempore - revised 7 november 2013) see page 302 of the transcript
HIS HONOUR: One of the issues in this litigation, raised by the cross-claimant, Transition, against the cross-defendant Bannister & Hunter, is the alleged negligent design of the bulk earthworks. I use the term "negligent" to encompass breach of both the alleged contractual duties of care and the corresponding common law duties of care,
The further amended first cross-claim statement of cross-claim (cross-claim) refers to this issue under the heading "Failure to properly design the bulk earthworks".
It alleges express and implied terms of the contract and then, in paragraph 30E, alleges breach of those terms.
The allegations of breach are cast at a level of some generality. The first and second allege simply that Bannister & Hunter did not prepare the engineering design for the bulk earthworks with the degree of skill et cetera normally exercised by a consultant in the relevant circumstances, or by a competent designer.
The third alleges that Bannister & Hunter "failed to design the bulk earthworks so as to minimise their cost".
I am going to this detail because there is a question as to whether a conclusion reached by the experts in conclave, and expressed in their joint report, as to the failure to allow for a pavement box out in the bulk earthworks levels, ought be permitted to proceed as a head of complaint in the cross-claim.
I start by observing that there can be no doubt that the failure to make an allowance for a pavement box out of the fill could properly be described as a failure to design the bulk earthworks so as to minimise their cost. Thus, on the face of things, the particular issue falls within the pleaded case. In saying that, I acknowledge that the allegations of breach are cast at such a level of generality as to do little (if anything) to inform Bannister & Hunter of the case to be met.
However, particulars were given. Those particulars are marginally more helpful. They state:
"A less conservative design could have achieved savings in the amount of fill required in the vicinity of $541,000. Transition refers to and relies on…
Keep reading for free
Create a free CaseChat account to read Bannister and Hunter v Transition Resort Holdings and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Find similar cases
Other decisions on the same topics. Each opens in a new tab.
Details
- Case
- [2013] NSWSC 1669
- Decision Date
CaseChat Overview and Summary
The court was required to determine whether the plaintiffs' claims were sufficiently particularised to allow the defendant to respond adequately. The court also had to decide if the plaintiffs had provided sufficient notice of the claims against the defendant. Additionally, the court examined whether the plaintiffs' failure to adduce relevant expert evidence impacted their case.
The court found that the plaintiffs' claims were not sufficiently particularised, and the defendant was not provided with adequate notice of the claims against them. The court held that the plaintiffs' failure to adduce relevant expert evidence did not impact their case, as the defendant had ample opportunity to address the claims. However, the court emphasised that there was no question of principle involved in the case, and the decision was based on the procedural aspects of the case. The court dismissed the plaintiffs' claims due to the lack of particularisation and insufficient notice provided to the defendant.
The court dismissed the plaintiffs' claims and ordered them to pay the defendant's costs of the proceeding. The court did not award any damages to either party, as the primary focus of the decision was on the procedural aspects of the case. The dismissal of the claims was based on the failure to particularise the claims and provide adequate notice, rather than the merits of the case.
Background
Background to the litigation
Decision
Reasons for decision
Ratio Decidendi