SUPREME COURT OF QUEENSLAND
CITATION:
State of Qld v T & M Buckley P/L [2012] QSC 265
PARTIES:
THE STATE OF QUEENSLAND THROUGH THE DIRECTOR-GENERAL, DEPARTMENT OF HOUSING AND PUBLIC WORKS
(applicant)
v
T & M BUCKLEY PTY LTD (RECEIVERS AND MANAGERS APPOINTED) ACN 010 052 043
(first respondent)
and
RICS DISPUTE RESOLUTION SERVICE ABN 18 089 873 067
(second respondent)
and
JENNIFER WYATT(third respondent)
FILE NO:
BS5229/12
DIVISION:
Trial
PROCEEDING:
Originating application
DELIVERED ON:
13 September 2012
DELIVERED AT:
Brisbane
HEARING DATE:
20 July 2012
JUDGE:
Margaret Wilson J
ORDER:
CATCHWORDS:
ADMINISTRATIVE LAW – JUDICIAL REVIEW – GROUNDS OF REVIEW – JURISDICTIONAL MATTERS – where first respondent served payment claim on applicant – where applicant served payment schedule in response to payment claim and matter referred to adjudication – where applicant seeks declaration that adjudication decision is void by reason of jurisdictional error – where applicant submitted that no reference date accrued pursuant to Building and Construction Industry Payments Act 2004 which resulted in the payment claim being invalid and the adjudication decision being void – whether accrual of the statutory reference date is conditional upon the prior delivery of the statutory declaration – whether the adjudication decision was void
Building and Construction Industry Payments Act 2004 (Qld), s 12, s 99, Schedule 2
Corporations Act 2001 (Cth), s 471BJohn Holland Pty Ltd v Coastal Dredging & Construction Pty Limited [2012] QCA 150, cited.
Simcorp Developments & Constructions Pty Ltd v Gold Coast Titans Property Pty Ltd [2010] QSC 162, cited.
COUNSEL:
P Dunning SC and G Beacham for the applicant
M H Hindman for the first respondent
SOLICITORS:
Clayton Utz for the applicant
Allens Linklaters for the first respondent
MARGARET WILSON J: This application relates to a claim for payment made pursuant to the Building and Construction Industry Payments Act 2004 (“BCIPA”).
On or about 16 December 2010 the applicant (the State of Queensland) and the first respondent entered into a contract for construction work in relation to a building at Burleigh Heads.
On 17 April 2012 the first respondent served a payment claim (“the April payment claim”) on the applicant, purportedly pursuant to BCIPA. The applicant served a payment schedule in response to the payment claim and the matter was referred to adjudication. On 5 June 2012 the adjudicator found that the first respondent was entitled to a progress payment.
By an originating application filed on 14 June 2012, the applicant seeks a declaration that the adjudication decision is void by reason of jurisdictional error.
Leave to proceed
The first respondent was placed in liquidation on 29 June 2012.
At the commencement of the hearing I gave the applicant leave to proceed pursuant to s 471B of the Corporations Act.
Relevant provisions of BCIPA
Section 12 of BCIPA provides –
“12 Rights to progress payments
From each reference date under a construction contract, a person is entitled to a progress payment if the person has undertaken to carry…
Keep reading for free
Create a free CaseChat account to read State of Queensland v T & M Buckley Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2012] QSC 265
- Decision Date
CaseChat Overview and Summary
The legal issues the court had to resolve included whether the accrual of the statutory reference date was dependent on the prior delivery of a statutory declaration and whether the adjudication decision was indeed void. These issues hinged on the interpretation of the Building and Construction Industry Payments Act 2004 and the accompanying regulations. The applicant contended that the statutory reference date did not accrue as required by the legislation, thereby making the payment claim invalid and the subsequent adjudication decision void. The court needed to determine the validity of these arguments and whether the adjudication decision contained any jurisdictional errors.
The court examined the statutory provisions and concluded that the accrual of the reference date was not contingent upon the prior delivery of a statutory declaration. It found that the statutory framework permitted the reference date to accrue independently of such a declaration. Consequently, the court held that the payment claim was valid, and there was no jurisdictional error in the adjudication decision. The applicant's argument was dismissed, and the court ruled that the adjudication decision was not void. The court's decision was based on a detailed analysis of the statutory provisions and a finding that the applicant had not demonstrated any jurisdictional error in the adjudication process.
In summary, the court determined that the accrual of the reference date under the Building and Construction Industry Payments Act 2004 did not require the prior delivery of a statutory declaration. As such, the payment claim was valid, and the adjudication decision was not void. The applicant's claim was dismissed, and the court affirmed the validity of the adjudication process. No further orders were made beyond the dismissal of the applicant's claim.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi