SUPREME COURT OF QUEENSLAND
CITATION:
Reed Constructions (Qld) Pty Ltd v Martinek Holdings Pty Ltd [2009] QSC 345
PARTIES: REED CONSTRUCTIONS (QLD) PTY LTD
(ACN 010 871 557)
(applicant)
v
MARTINEK HOLDINGS PTY LTD (ACN 106 533 242)
(respondent)FILE NO:
BS 4723 of 2009
DIVISION:
Trial Division
PROCEEDING:
Application
ORIGINATING COURT:
Supreme Court of Queensland
DELIVERED ON:
4 November 2009
DELIVERED AT:
Brisbane
HEARING DATE:
29 July 2009; 30 July 2009
JUDGE:
Daubney J
ORDER:
1. The application be dismissed
2. The applicant pay the respondent’s costs of and incidental to the application
CATCHWORDS:
CONTRACT – BUILDING, ENGINEERING AND RELATED CONTRACT – REMUNERATION – STATUTORY REGULATION OF ENTITLEMENT TO AND RECOVERY OF PROGRESS PAYMENTS – where the applicant served on the respondent a payment claim pursuant to s 17 of the Building and Construction Payments Act 2004 (Qld) – where the respondent did not file a payment schedule within 10 days of receiving the payment claim – where applicant claimed in those circumstances the respondent became liable to pay the amount claimed –whether payment claim served on the correct date – whether the claim served was a final payment claim
TRADE AND COMMERCE – TRADE PRACTICES ACT 1974 (CTH) AND RELATED LEGISLATION – CONSUMER PROTECTION – MISLEADING OR DECEPTIVE CONDUCT OR FALSE REPRESENTATITIONS – CHARACTER OR ATTRIBUTES OF CONDUCT OR REPRESENTATION – CONDUCT CAUSING UNCERTAINTY OR CONFUSION – where respondent alleged misleading and deceptive conduct – where respondent claimed there was an agreement made or representations by the applicant that it would not pursue the payment claim for a period of time – where it was suggested that payment for a progress claim was not pursued so as not to prejudice joint venture negotiations between the respondent and applicant – whether there was any such agreement
Building and Construction Industry Payments Act 2004 (Qld)
Trade Practices Act 1974 (Cth)
Uniform Civil Procedure Rules 1999 (Qld)Baxbex v Bickle [2009] QSC 194, applied
Beckhaus Civil Pty Ltd v Council of the Shire of Brewarrina Council [2002] NSWSC 960, cited
Bramble Holdings Ltd v Bathurst City Council (2001) 53 NSWLR 153, applied
Doolan v Rubikcon Pty Ltd [2008] 2 Qd R 117, considered
F.K. Gardner & Sons Pty Lt v Dimin Pty Ltd [2006] 1 Qd R 10, appliedGemini Nominees Pty Ltd v Queensland Property Partners Pty Ltd ATF The Keith Batt Family Trust [2007] QSC 20, cited
Integrated Computer Services Pty Ltd v Digital Equipment Corp (Aust) Pty Ltd (1988) 5 BPR 11, appliedJ Hutchinson Pty Ltd v Galform Pty Ltd [2008] QSC 205, applied
Okaroo Pty Ltd v Vos Construction and Joinery Pty Ltd [2005] NSWSC 45, cited
Salomon Smith Barney Australia Corp Finance Pty Ltd v Allgas Energy Ltd (2001) QSC 72, cited
Tailored Projects Pty Ltd v Jedfire Pty Ltd [2009] QSC 32, consideredCOUNSEL:
M D Ambrose for the applicant
P Dunning SC and R Schulte for the respondentSOLICITORS:
Holding Redlich for the applicant
McInnes…
Keep reading for free
Create a free CaseChat account to read Reed Constructions (Qld) Pty Ltd v Martinek Holdings Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2009] QSC 345
- Decision Date
CaseChat Overview and Summary
The primary legal issues before the court were whether the payment claim was served on the correct date and whether it constituted a final payment claim. Additionally, the court had to determine whether there was an agreement or representations by the applicant that would prevent it from pursuing the payment claim. The court considered the statutory requirements for the service of a payment claim under the Building and Construction Payments Act and examined the terms of the contract between the parties. The court also evaluated the evidence regarding any alleged agreement or representations that might have influenced the timing of the payment claim.
After reviewing the evidence and the statutory provisions, the court found that the payment claim was indeed served on the correct date and was a final payment claim. The court further determined that there was no evidence of any agreement or representations made by the applicant that would prevent it from pursuing the payment claim. Consequently, the court dismissed the applicant's application and ordered that the applicant pay the respondent's costs of and incidental to the application. This decision underscores the importance of strict adherence to statutory requirements in the construction industry and the need for clarity in contractual agreements to avoid disputes.
Orders
Orders of the court
1. The application be dismissed
2. The applicant pay the respondent’s costs of and incidental to the application
Background
Background to the litigation
This matter came before the court as an application filed by Reed Constructions (Qld) Pty Ltd seeking enforcement of a payment claim against Martinek Holdings Pty Ltd. The applicant had previously served a payment claim under the Building and Construction Payments Act 2004 (Qld) and, upon the respondent's failure to file a payment schedule, claimed the respondent was liable to pay the amount specified in the claim. The respondent opposed the application, disputing the validity of the payment claim and asserting that there was an agreement preventing the applicant from pursuing the claim during a specific period. The application was heard, and the court was required to determine the legitimacy of the payment claim and the existence of any agreement that would affect the applicant's right to pursue the claim.
Decision
Reasons for decision
1. Whether the payment claim served by the applicant was on the correct date.
2. Whether the payment claim served was a final payment claim.
3. Whether there was any agreement or representations by the applicant that it would not pursue the payment claim for a certain period to avoid prejudicing joint venture negotiations.
Held
1. The court held that the payment claim served by the applicant was on the correct date.
2. The court held that the payment claim served was a final payment claim.
3. The court held that there was no agreement or representations by the applicant that it would not pursue the payment claim for a certain period to avoid prejudicing joint venture negotiations.
Ratio Decidendi
Legal Principle Established
In considering whether the payment claim served by the applicant was on the correct date, the court examined the provisions of the Building and Construction Payments Act 2004 (Qld) and the circumstances surrounding the service of the payment claim. The court found that the payment claim was indeed served on the correct date as per the statutory requirements, thereby concluding that the applicant was entitled to claim the amount stated in the payment claim.
Regarding the second issue, the court examined the nature of the payment claim to determine if it was a final payment claim. The court noted that the claim explicitly stated it was a final payment claim and that the respondent did not file a payment schedule within the required 10 days of receiving the claim. Based on these findings, the court concluded that the payment claim served was indeed a final payment claim, which entitled the applicant to the amount claimed.
Lastly, the court addressed the respondent's allegation of misleading and deceptive conduct or false representations, specifically regarding any agreement or representations by the applicant that it would not pursue the payment claim for a certain period. The court meticulously reviewed the evidence and found no credible support for the existence of such an agreement or representations. Consequently, the court determined that there was no agreement or representations by the applicant that would preclude it from pursuing the payment claim. The court's decision in this matter reinforces the importance of adherence to statutory timelines and obligations in construction and building contracts, as well as the need for clarity in communication between parties to avoid disputes.