Reed Constructions (Qld) Pty Ltd v Martinek Holdings Pty Ltd

Link copied
Case Copied 27 min read

SUPREME COURT OF QUEENSLAND

CITATION:

Reed Constructions (Qld) Pty Ltd v Martinek Holdings Pty Ltd [2009] QSC 345

PARTIES:

REED CONSTRUCTIONS (QLD) PTY LTD
(ACN 010 871 557)
(applicant)
v
MARTINEK HOLDINGS PTY LTD (ACN 106 533 242)
(respondent)

FILE NO:

BS 4723 of 2009

DIVISION:

Trial Division

PROCEEDING:

Application

ORIGINATING COURT:

Supreme Court of Queensland

DELIVERED ON:

4 November 2009

DELIVERED AT:

Brisbane

HEARING DATE:

29 July 2009; 30 July 2009

JUDGE:

Daubney J

ORDER:

1.     The application be dismissed

2.    The applicant pay the respondent’s costs of and incidental to the application

CATCHWORDS:

CONTRACT – BUILDING, ENGINEERING AND RELATED CONTRACT – REMUNERATION – STATUTORY REGULATION OF ENTITLEMENT TO AND RECOVERY OF PROGRESS PAYMENTS – where the applicant served on the respondent a payment claim pursuant to s 17 of the Building and Construction Payments Act 2004 (Qld) – where the respondent did not file a payment schedule within 10 days of receiving the payment claim – where applicant claimed in those circumstances the respondent became liable to pay the amount claimed –whether payment claim served on the correct date – whether the claim served was a final payment claim

TRADE AND COMMERCE – TRADE PRACTICES ACT 1974 (CTH) AND RELATED LEGISLATION – CONSUMER PROTECTION – MISLEADING OR DECEPTIVE CONDUCT OR FALSE REPRESENTATITIONS – CHARACTER OR ATTRIBUTES OF CONDUCT OR REPRESENTATION – CONDUCT CAUSING UNCERTAINTY OR CONFUSION – where respondent alleged misleading and deceptive conduct – where respondent claimed there was an agreement made or representations by the applicant that it would not pursue the payment claim for a period of time – where it was suggested that payment for a progress claim was not pursued so as not to prejudice joint venture negotiations between the respondent and applicant – whether there was any such agreement

Building and Construction Industry Payments Act 2004 (Qld)
Trade Practices Act 1974 (Cth)
Uniform Civil Procedure Rules 1999 (Qld)

Baxbex v Bickle [2009] QSC 194, applied
Beckhaus Civil Pty Ltd v Council of the Shire of Brewarrina Council [2002] NSWSC 960, cited
Bramble Holdings Ltd v Bathurst City Council (2001) 53 NSWLR 153, applied
Doolan v Rubikcon Pty Ltd [2008] 2 Qd R 117, considered
F.K. Gardner & Sons Pty Lt v Dimin Pty Ltd [2006] 1 Qd R 10, applied

Gemini Nominees Pty Ltd v Queensland Property Partners Pty Ltd ATF The Keith Batt Family Trust [2007] QSC 20, cited
Integrated Computer Services Pty Ltd v Digital Equipment Corp (Aust) Pty Ltd (1988) 5 BPR 11, applied

J Hutchinson Pty Ltd v Galform Pty Ltd [2008] QSC 205, applied
Okaroo Pty Ltd v Vos Construction and Joinery Pty Ltd [2005] NSWSC 45, cited
Salomon Smith Barney Australia Corp Finance Pty Ltd v Allgas Energy Ltd (2001) QSC 72, cited
Tailored Projects Pty Ltd v Jedfire Pty Ltd [2009] QSC 32, considered

COUNSEL:

M D Ambrose for the applicant
P Dunning SC and R Schulte for the respondent

SOLICITORS:

Holding Redlich for the applicant
McInnes…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Reed Constructions (Qld) Pty Ltd v Martinek Holdings Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2009] QSC 345
Decision Date

CaseChat Overview and Summary

In the matter of Reed Constructions (Qld) Pty Ltd v Martinek Holdings Pty Ltd, the applicant, a building contractor, sought payment from the respondent, a property developer, under the Building and Construction Payments Act 2004 (Qld). The applicant served a payment claim on the respondent under section 17 of the Act. The respondent failed to file a payment schedule within the stipulated 10 days, prompting the applicant to claim that the respondent was liable to pay the full amount of the claim. The respondent, however, disputed the applicant's entitlement to payment, alleging that the payment claim was not served on the correct date and that it was not a final payment claim. The respondent also argued that there was a prior agreement or representations by the applicant that it would not pursue the payment claim to avoid disrupting negotiations between the two parties.

The primary legal issues before the court were whether the payment claim was served on the correct date and whether it constituted a final payment claim. Additionally, the court had to determine whether there was an agreement or representations by the applicant that would prevent it from pursuing the payment claim. The court considered the statutory requirements for the service of a payment claim under the Building and Construction Payments Act and examined the terms of the contract between the parties. The court also evaluated the evidence regarding any alleged agreement or representations that might have influenced the timing of the payment claim.

After reviewing the evidence and the statutory provisions, the court found that the payment claim was indeed served on the correct date and was a final payment claim. The court further determined that there was no evidence of any agreement or representations made by the applicant that would prevent it from pursuing the payment claim. Consequently, the court dismissed the applicant's application and ordered that the applicant pay the respondent's costs of and incidental to the application. This decision underscores the importance of strict adherence to statutory requirements in the construction industry and the need for clarity in contractual agreements to avoid disputes.

Orders

Orders of the court

1. The application be dismissed

2. The applicant pay the respondent’s costs of and incidental to the application

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.