SUPREME COURT OF QUEENSLAND
CITATION:
Tenix Alliance P/L v Magaldi Power P/L [2010] QSC 7
PARTIES:
TENIX ALLIANCE PTY LTD (ABN 65 075 194 857)
(applicant)
v
MAGALDI POWER PTY LTD (ABN 51 105 805 418)
(respondent)FILE NO/S:
14104 of 2009
DIVISION:
Trial
PROCEEDING:
Application
ORIGINATING COURT:
Supreme Court at Brisbane
DELIVERED ON:
12, 15 January 2010
DELIVERED AT:
Brisbane
HEARING DATE:
12, 15 January 2010
JUDGE:
Fryberg J
ORDER:
1. Judgment against the Respondent in the amount of $890,930.26 including $28,788.71 interest.
2. Order that the Respondent pay the Applicant’s costs of and incidental to the Application, including the costs of the appearance on 15 January 2010, to be assessed.
CATCHWORDS:
Contracts – Building, engineering and related contracts – Remuneration – Statutory regulation of entitlement to and recovery of progress payments – Validity of payment claim – Claim made after reference date not invalid
Contracts – Building, engineering and related contracts – Remuneration – Statutory regulation of entitlement to and recovery of progress payments – Prolongation costs for period after payment claim – Not costs of construction work
Contracts – Building, engineering and related contracts – Remuneration – Statutory regulation of entitlement to and recovery of progress payments – Validity of payment schedule – Interpretation of schedule – Statement of amount proposed to be paid – Statement of reasons for withholding part of amount claimed – Non-compliance with statutory requirements
Building and Construction Industry Payments Act 2004 (Qld), s 12, s 15, s 17, s 18(2), s 18(3), s 19(2)
Doolan v Rubikcon Pty Ltd [2008] 2 Qd R 117; [2007] QSC 168, cited
J Hutchinson Pty Ltd v Galform Pty Ltd & Ors[2008] QSC 205, cited
Minimax Fire Fighting Systems Pty Ltd v Bremore Engineering (WA Pty Ltd) & Ors[2007] QSC 333, cited
Quasar Constructions v Demtech Pty Ltd [2004] NSWSC 116, cited
Reed Constructions (Qld) Pty Ltd v Martinek Holdings Pty Ltd[2009] QSC 345, consideredCOUNSEL:
M H Hindman for the applicant
R Wensley QC for the respondentSOLICITORS:
Norton Rose for the applicant
N J Papallo as town agents for Tucker & Cowen Solicitors for the respondent
SUPREME COURT OF QUEENSLAND
CIVIL JURISDICTION
FRYBERG J
No 14104 of 2009
| TENIX ALLIANCE | Applicant |
| and | |
| MAGALDI POWER | Respondent |
BRISBANE
..DATE 12/01/2010
JUDGMENT
HIS HONOUR: This is an application for judgment by a
sub-contractor against the head-contractor pursuant to s 19(2)(a)(i) of the Building and Construction Industry Payments Act 2004. The sum claimed is $2,703,149.30. At the outset I was informed that the head-contractor had already paid, before the application was filed, an amount of $872,569.50 inclusive of GST. The sum actually claimed was in fact the difference between those two amounts.
The applicant, Tenix, entered into a contract with the respondent contractor, Magaldi, to dismantle an existing system at the Millmerran Power Station Unit 1 and carry out the mechanical and electrical erection of a MAC system.
The contract price was $2,484,000 and that price was payable under cl…
Keep reading for free
Create a free CaseChat account to read Tenix Alliance Pty Ltd v Magaldi Power Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2010] QSC 7
- Decision Date
CaseChat Overview and Summary
The legal issues before the court involved the validity of payment claims made after a reference date, the recoverability of prolongation costs, and the compliance of the payment schedule with statutory requirements. The Applicant argued that the payment claim was valid and that the Respondent was liable for prolongation costs incurred after the payment claim was made. The Respondent contended that the payment claim was invalid as it was made after the reference date and that prolongation costs incurred after the claim was made were not recoverable.
The court held that the payment claim was not invalid simply because it was made after the reference date. The court found that the payment schedule did not comply with statutory requirements as it did not include a statement of reasons for withholding part of the amount claimed. However, this non-compliance did not affect the validity of the payment claim. The court also found that prolongation costs incurred after the payment claim was made were not costs of construction work and therefore not recoverable.
The court ordered judgment in favour of the Applicant for the amount of $890,930.26 plus interest and costs. The court also ordered that the Respondent pay the Applicant's costs of and incidental to the Application.
Orders
Orders of the court
1. Judgment against the Respondent in the amount of $890,930.26 including $28,788.71 interest.
2. Order that the Respondent pay the Applicant’s costs of and incidental to the Application, including the costs of the appearance on 15 January 2010, to be assessed.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.