CITATION: Trysams Pty Limited v Club Constructions (NSW) Pty Ltd [2008] NSWSC 399 HEARING DATE(S): 15 April 2008
JUDGMENT DATE :
6 May 2008JUDGMENT OF: McDougall J at 1 DECISION: See paragraphs [104] and [105] of the judgment. CATCHWORDS: BUILDING AND ENGINEERING CONTRACTS – Building and Construction Industry Security of Payment Act 1999 – adjudication determination – adjudicator’s consideration of a issue not raised by parties – parties denied opportunity to put submissions on issue – whether issue material to determination – whether denial of natural justice – adjudicator’s failure to consider relevant contractual provisions – power of Court to order adjudicator to reconsider adjudication application. LEGISLATION CITED: Building and Construction Industry Security of Payment Act 1999
Building and Construction Industry Security of Payment Amendment Act 2002
Civil Procedure Act 2005
Supreme Court Act 1970CATEGORY: Principal judgment CASES CITED: Abacus v Davenport [2003] NSWSC 1027
Brewarrina Shire Council v Beckhaus Civil Pty Ltd (2003) 56 NSWLR 576
Brodyn Pty Limited v Davenport (2004) 61 NSWLR 421
Coordinated Construction Co Pty Ltd v JM Hargreaves (NSW) Pty Ltd [2005] NSWCA 228
Jemzone v Trytan [2002] NSWSC 395
John Goss Projects v Leighton Contractors [2006] NSWSC 798 66 NSWLR 707
John Holland Pty Limited v Roads and Traffic Authority of New South Wales [2007] NSWCA 140
Minister for Commerce v Contrax Plumbing (NSW) Pty Ltd [2005] NSWCA 142
Minister for Immigration and Ethnic Affairs v Wu Shan Liang (1996) 185 CLR 259
Minister for Immigration and Multicultural Affairs; ex parte Lam (2003) 214 CLR 1
Multiplex Constructions Pty Ltd v Luikens [2003] NSWSC 1140
Musico v Davenport [2003] NSWSC 977
Reiby Street Apartments v Winterton Constructions (2006) 22 BCL 426
Trysams Pty Ltd v Club Constructions (NSW) Pty Ltd [2007] NSWLR 941PARTIES: Trysams Pty Limited (ACN 098 992 744) (Plaintiff)
Club Constructions (NSW) Pty Ltd (ACN 072 479 193) (First Defendant)
Ted Smithies (Second defendant)
Mediate Today Pty Ltd t/a Adjudicate Today (ACN 055 563 760) (Third Defendant)
FILE NUMBER(S): SC 55012/08 COUNSEL: V Culkoff (Plaintiff)
M Christie (First Defendant)SOLICITORS: JPR Legal Pty Ltd (Plaintiff)
Doyles Construction Lawyers (First Defendant)
Philip Davenport (Second and Third Defendants)
IN THE SUPREME COURT
OF NEW SOUTH WALES
EQUITY DIVISION
TECHNOLOGY & CONSTRUCTION LIST
McDOUGALL J
6 May 2008
55012/08 TRYSAMS PTY LIMITED ACN 098 992 744 v CLUB CONSTRUCTIONS (NSW) PTY LIMITED ACN 072 479 193 & 2 ORS
JUDGMENT
1 HIS HONOUR: The plaintiff (Trysams) and the first defendant (Club) made a contract (the contract) on 11 July 2005, by which Club undertook to carry out renovations of and additions to a hotel at Gymea. The contract was a construction contract for the purposes of the Building and Construction Industry Security of Payment Act 1999 (the Act). On 23 November 2007, Club made a payment claim under the Act. It was in substance although not perhaps in form a final payment claim. The claim included the release of the retention fund. Trysams disputed the claim, including the release of the…
Keep reading for free
Create a free CaseChat account to read Trysams Pty Ltd v Club Constructions (NSW) Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2008] NSWSC 399
- Decision Date
CaseChat Overview and Summary
The court examined the principles of natural justice, particularly the rule that no person should be adversely affected by a decision without being given an opportunity to be heard. It was established that the adjudicator had considered an issue outside the scope of the dispute as defined by the parties. Despite this, the court found that the issue in question was not material to the adjudication determination, thus mitigating the potential unfairness. Nevertheless, the court held that the adjudicator's failure to provide the parties with an opportunity to address the issue constituted a breach of natural justice. The court also noted that the adjudicator had not considered certain relevant contractual provisions, which could have impacted the outcome of the adjudication.
The court concluded that while the breach of natural justice was significant, it did not necessarily invalidate the entire adjudication process. The court had the power to order the adjudicator to reconsider the application, ensuring that all relevant issues were properly addressed and that both parties were given a fair opportunity to be heard. This balanced approach aimed to uphold the integrity of the adjudication process while providing a fair resolution to the underlying dispute. The final orders included a direction for the adjudicator to reconsider the adjudication, taking into account all relevant issues and submissions from both parties.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.