CITATION: Perform (NSW) Pty Limited v Mev-Aus Pty Limited trading as Novatec Construction Systems & Anor [2008] NSWSC 858 HEARING DATE(S): 18/08/08, 19/08/08 JURISDICTION: Equity Division
Technology and Construction ListJUDGMENT OF: Einstein J EX TEMPORE JUDGMENT DATE: 19 August 2008 DECISION: Summons dismissed CATCHWORDS: Building and Construction Industry Security of Payment Act 1999 (NSW) - Whether section 14 (3) of the Act permits incorporation by reference into a payment schedule - Whether respondent’s payment schedule indicated, within the meaning of s. 14 (4) of the Act as reasons for withholding payment, the reasons contained in an anterior payment schedule - Whether the Adjudicator made an error of a character that was within his jurisdiction - Whether the Adjudicator’s findings constitute a failure by the Adjudicator to comply with the requirements contained in s.22(2)(d) of the Act - Whether Adjudicator denied natural justice - Whether the Adjudicator failed in good faith to exercise the power to make an adjudication. LEGISLATION CITED: Building and Construction Industry Security of Payment Act 1999 (NSW) CATEGORY: Principal judgment CASES CITED: Brodyn Pty Ltd v Davenport (2004) 61 NSWLR 421
Coordinated Construction Co Pty Ltd v JM Hargreaves (NSW) Pty Ltd (2005) 63 NSWLR 385; [2005] NSWCA 228
Coordinated Construction Co Pty Ltd v Climatech (Canberra) Pty Ltd [2005] NSWCA 229
Downer Construction (Australia) Pty Ltd v Energy Australia [2007] NSWCA 49
Downsouth Constructions Pty Ltd v Jigsaw Corporate Childcare Australia Pty Ltd [2007] NSWSC 597
Halkat Electrical Contractors Pty Ltd v Holmwood Holdings Pty Ltd [2007] NSWCA 32
Holmwood Holdings Pty Ltd v Halkat Electrical Contractors Pty Ltd [2005] NSWSC 1129
Inten Constructions Pty Ltd v Refine Electrical Services Pty Ltd [2006] NSWSC 1282
Isis Projects Pty Ltd v Clarence Street Pty Ltd [2004] NSWSC 714
John Goss Projects Pty Ltd v Leighton Contractors Pty Ltd (2006) 66 NSWLR 707
John Holland Pty Ltd v Roads & Traffic Authority of NSW [2007] NSWCA 19
Multiplex Constructions Pty Ltd v Luikens [2003] NSWSC 1140
Nepean Engineering Pty Ltd v Total Process Services Pty Ltd (in liq) [2005] NSWCA 409
Pacific General Securities Ltd v Soliman & Sons Pty Ltd [2006] NSWSC 13
Procorp Civil Pty Ltd v Napoli Excavations and Contracting Pty Ltd [2006] NSWSC 358
Reiby Street Apartments Pty Ltd v Winterton Constructions Pty Ltd [2006] NSWSC 375
Rothnere Pty Ltd v Quasar Constructions NSW Pty Ltd [2004] NSWSC 1151
SAAG v Minister for Immigration and Multicultural and Indigenous Affairs [2002] FCA 547
SBBS v Minister for Immigration and Multicultural and Indigenous Affairs (2002) 194 ALR 749
SBAU v Minister for Immigration and Multicultural and Indigenous Affairs [2002] FCA 1076
SCAA v Minister for Immigration and Multicultural and Indigenous Affairs [2002] FCA 668
The Minister for Commerce v Contrax Plumbing (NSW) Pty Ltd [2005] NSWCA 142
Transgrid v Siemens Ltd (2004) 61 NSWLR 521
Trysams Pty Ltd v Club Constructions (NSW) Pty Ltd [2008] NSWSC 399PARTIES: Perform (NSW) Pty Limited (Plaintiff)
Mev-Aus Pty Limited trading as Novatec Construction Systems (First Defendant)
David…
Keep reading for free
Create a free CaseChat account to read Perform (NSW) Pty Limited v Mev-Aus Pty Limited trading as N... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Details
- Case
- [2008] NSWSC 858
- Decision Date
CaseChat Overview and Summary
Perform (NSW) Pty Limited sought adjudication of a dispute under the Building and Construction Industry Security of Payment Act 1999 (NSW) against Mev-Aus Pty Limited trading as Novatec Construction Systems. The central issue was whether the Adjudicator had correctly interpreted the payment schedules provided by Mev-Aus and made the adjudication in accordance with the statutory requirements. The dispute revolved around the interpretation of sections 14(3) and 14(4) of the Act, which pertain to the content and incorporation by reference of reasons for withholding payment.
The court was required to determine whether the Adjudicator had correctly interpreted the payment schedules and if the reasons provided by Mev-Aus were adequately referenced within the statutory framework. The court also had to consider whether the Adjudicator had made an error in jurisdiction, whether the findings of the Adjudicator constituted a failure to comply with the Act, and if the Adjudicator had denied natural justice or failed to exercise the power to make an adjudication in good faith.
The court held that the Adjudicator's interpretation of the payment schedules and the reasons for withholding payment were correct. The court found that the Adjudicator had not erred in jurisdiction and had properly applied the provisions of the Act. The findings of the Adjudicator were held to comply with the requirements of the Act, and there was no denial of natural justice. Furthermore, the court determined that the Adjudicator had exercised the power to make an adjudication in good faith, and there was no failure on the part of the Adjudicator to comply with the statutory requirements.
The court dismissed the application by Perform (NSW) Pty Limited, affirming the decision of the Adjudicator.
The court was required to determine whether the Adjudicator had correctly interpreted the payment schedules and if the reasons provided by Mev-Aus were adequately referenced within the statutory framework. The court also had to consider whether the Adjudicator had made an error in jurisdiction, whether the findings of the Adjudicator constituted a failure to comply with the Act, and if the Adjudicator had denied natural justice or failed to exercise the power to make an adjudication in good faith.
The court held that the Adjudicator's interpretation of the payment schedules and the reasons for withholding payment were correct. The court found that the Adjudicator had not erred in jurisdiction and had properly applied the provisions of the Act. The findings of the Adjudicator were held to comply with the requirements of the Act, and there was no denial of natural justice. Furthermore, the court determined that the Adjudicator had exercised the power to make an adjudication in good faith, and there was no failure on the part of the Adjudicator to comply with the statutory requirements.
The court dismissed the application by Perform (NSW) Pty Limited, affirming the decision of the Adjudicator.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence before the court
Decision
Reasons for decision
Ratio Decidendi