CITATION: Coordinated Construction Co. Pty. Ltd. v. Climatech (Canberra) Pty. Ltd. & Ors. [2005] NSWCA 229
HEARING DATE(S): 10 June 2005
JUDGMENT DATE:
13 July 2005JUDGMENT OF: Hodgson JA at 1; Ipp JA at 34; Basten JA at 37
DECISION: Appeal dismissed with costs
CATCHWORDS: BUILDING AND CONSTRUCTION - Progress payments - Building & Construction Industry Security of Payment Act - Adjudicator's determination - Whether "delay damages" under contract are "for" construction work or related goods and services - Whether delay damages can be included in payment claims under the Act.
LEGISLATION CITED: Building & Construction Security of Payment Act 1999, ss.3, 4, 6, 8, 9, 10, 11, 13, 17 and 22.
CASES CITED: Brodyn Pty. Ltd. v. Davenport [2004] NSWCA 394
Chen Shi Hai v Minister for Immigration and Multicultural Affairs (2000) 201 CLR 293
Coordinated Construction Co Pty Ltd v Climatech (Canberra) Pty Ltd [2005] NSWSC 312
Coordinated Constructions Co. Ltd v. J.M. Hargreaves (NSW) Pty. Ltd. [2005] NSWCA 228
Coordinated Constructions Co. Pty. Ltd. v. J.M. Hargreaves (NSW) Pty. Ltd. [2005] NSWSC 77
In Re An Arbitration Between Taylor Woodrow International Ltd. and The Minister of Health (1978) 19 SASR 1
John Holland Pty. Ltd. v. Cardno MBK (NSW) Pty. Ltd. [2004] NSWSC 258
Minister for Immigration and Ethnic Affairs v Guo Wei Rong (1997) 191 CLR 559
Minister for Immigration and Multicultural Affairs v Eshetu (1999) 197 CLR 611
Parisienne Basket Shoes Pty Ltd v Whyte (1938) 59 CLR 369
Project Blue Sky v Australian Broadcasting Authority (1998) 194 CLR 355
R v Connell; Ex parte Hetton Bellbird Collieries Ltd (1994) 69 CLR 407
Re Minister for Immigration and Multicultural and Indigenous Affairs; Ex parte Lam (2003) 214 CLR 1
The Minister for Commerce v. Contrax Plumbing (NSW) Pty. Ltd. [2005] NSWCA 142
Timbarra Protection Coalition Inc v Ross Mining NL (1999) 46 NSWLR 55PARTIES: Coordinated Construction Co. Pty. Ltd. - appellant
Climatech (Canberra) Pty. Ltd. - 1st respondent
Gerald Raftesath - 2nd respondent
LEADR - 3rd respondentFILE NUMBER(S): CA 40302/05
COUNSEL: Mr. M.G. Rudge SC with Mr. M. Christie for appellant
Mr. D.D. Feller SC with Mr. D.M. Loewenstein for respondentsSOLICITORS: Colin Biggers & Paisley, Sydney for appellant
James R. Knowles Lawyers, Sydney for respondents
LOWER COURT JURISDICTION: Supreme Court - Equity Division
LOWER COURT FILE NUMBER(S): SC55012/05
LOWER COURT JUDICIAL OFFICER: Bergin J
CA 40302/05
SC 55012/05Wednesday 13 July 2005HODGSON JA
IPP JA
BASTEN JA
1 HODGSON JA: On 13 April 2005, Bergin J gave judgment in proceedings in which the appellant (Coordinated) sought a declaration that an adjudication determination made by the second respondent (the adjudicator) was void, or alternatively an order quashing this determination; and also sought consequential relief against the first respondent (Climatech) and the fourth respondent (LEADR).
2 The primary judge refused the relief sought, and dismissed Coordinated’s summons. Coordinated has appealed from that decision.
CIRCUMSTANCES
3 On 23 June 2003,…
Keep reading for free
Create a free CaseChat account to read Coordinated Construction Co Pty Ltd v Climatech (Canberra) P... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2005] NSWCA 229
- Decision Date
CaseChat Overview and Summary
The primary legal issue before the Court of Appeal of the Supreme Court of the Australian Capital Territory was whether "delay damages" as defined in the parties' building contract constituted a claim for "construction work" or "related goods and services" within the meaning of the Act, thereby rendering them amenable to an adjudication claim. The court also considered whether the adjudicator had erred in law by including such damages in their determination.
The court reasoned that the Act is designed to facilitate cash flow within the building and construction industry by providing a statutory regime for progress payments. It held that the contractual entitlement to delay damages arose directly from the respondent's performance of its obligations under the contract, specifically its entitlement to be paid for work done and for losses incurred due to delays for which the applicant was responsible. Therefore, these damages were sufficiently connected to the provision of construction work and related goods and services to fall within the scope of the Act. The court distinguished between damages for breach of contract and a contractual entitlement to payment for losses arising from delays, finding the latter to be within the ambit of the Act.
The appeal was dismissed, and the applicant was ordered to pay the respondent's costs.
Orders
Orders of the court
Appeal dismissed with costs
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.