Façade Designs International Pty Ltd v Yuanda Vic Pty Ltd

Case

[2020] VSC 570

15 September 2020

IN THE SUPREME COURT OF VICTORIA Not Restricted

AT MELBOURNE
COMMERCIAL COURT

TECHNOLOGY, ENGINEERING AND CONSTRUCTION LIST

S ECI 2019 05113

FAÇADE DESIGNS INTERNATIONAL PTY LTD (ACN 099 706 859) Plaintiff
YUANDA VIC PTY LTD (ACN 166 473 089) Defendant

---

JUDGE:

RIORDAN J

WHERE HELD:

Melbourne

DATES OF HEARING:

13-14, 18-20 May 2020

27-28, 30 July 2020

DATE OF JUDGMENT:

15 September 2020

CASE MAY BE CITED AS:

Façade Designs International Pty Ltd v Yuanda Vic Pty Ltd

MEDIUM NEUTRAL CITATION:

[2020] VSC 570

---

BUILDING CONTRACTS – Building and Construction Industry Security of Payment Act 2002 (Vic) (‘the Act’) – Application for judgment after principal failed to provide payment schedule – Principles to be applied in determining validity under s 14 of the Act – Whether payment claim invalid for insufficient identification of construction work – Whether payment claim invalid if any part fails to sufficiently identify the construction work – Whether a court must be satisfied under s 16(4) of the Act that the claimed amount does not include any excluded amount on the face of the claim or in fact – Whether the claimed amount can be amended to delete an excluded amount – Whether an excluded amount can be severed from the claimed amount.

---

APPEARANCES:

Counsel Solicitors
For the Plaintiff Mr M G Roberts QC with
Ms C L Symons
Piper Alderman
For the Defendant Mr M R Scott QC with
Ms L Mills
K&L Gates

TABLE OF CONTENTS

Background......................................................................................................................................... 1

The Payment Claim........................................................................................................................... 1

Nature of the hearing........................................................................................................................ 1

Relevant provisions of the Act........................................................................................................ 1

Issues for determination................................................................................................................... 1

Principles of statutory interpretation............................................................................................. 1

Is the Payment Claim a valid payment claim under s 14 of the Act?....................................... 1

Is evidence of surrounding circumstances admissible in determining the validity of a payment claim?..................................................................................................................................... 1

Principles to be applied in determining the validity of a payment claim............................ 1

Is a payment claim invalid if any part fails to sufficiently identify the construction work?..... 1

Conclusion...................................................................................................................................... 1

As a matter of statutory construction, in determining whether or not any Claim Item constitutes or includes an excluded amount, should the Court have regard to:

(a). the description of the Claim Item as appearing on the face of the Payment Claim;  or

(b) evidence of the substance of the Claim Item?........................................................................ 1

Yuanda’s submissions.................................................................................................................. 1

Façade’s submissions.................................................................................................................... 1

Statutory scheme with respect to excluded amounts.............................................................. 1

Principles to be applied in relation to excluded amounts....................................................... 1

Conclusion...................................................................................................................................... 1

Does the inclusion of an excluded amount in the Payment Claim preclude the Court from giving judgment for any amount under s 16?........................................................................................... 1

Façade’s submissions.................................................................................................................... 1

Yuanda’s submissions.................................................................................................................. 1

Conclusion...................................................................................................................................... 1

Orders................................................................................................................................................... 1

Final observation................................................................................................................................ 1

Appendix 1 – Variations Table........................................................................................................ 1

Appendix 2.......................................................................................................................................... 1

HIS HONOUR:

  1. By originating motion filed 12 November 2019, the plaintiff (‘Façade’) seeks the following relief against the defendant (‘Yuanda’):

(a) an order that Yuanda pay Façade the amount of $3,469,365.58 (inclusive of GST) pursuant to s 16(2)(a) of the Building and Construction Industry Security of Payment Act 2002 (Vic) (‘the Act’);

(b) an order that Yuanda pay interest on the judgment sum, to be calculated on and from 30 October 2019 until the date of judgment, at the rate prescribed under s 2 of the Penalty Interest Rates Act 1983 (Vic); and

(c)        an order that Yuanda pay Façade’s costs of the proceeding.

  1. In support of the application, Façade relied upon the following affidavits:

(a)        Affidavits of Anthony Callipari sworn:

(i)       11 November 2019;

(ii)      19 November 2019 (No 1);

(iii)     19 November 2019 (No 2); 

(iv)     20 December 2019;

(v)      21 January 2020; and

(vi)     6 May 2020.

(b)      Affidavit of Faye Rozon sworn 5 May 2020.

(c)       Affidavit of Walter Bond sworn 6 May 2020.

  1. In opposition to the application, Yuanda relied upon the following affidavits:

(a)       Affidavits of Rith Nguon affirmed:

(i)         13 December 2019; and

(ii)       6 May 2020.

(b)      Affidavits of Zhijun Liu affirmed:

(i)       13 December 2019; and

(ii)      6 May 2020.

(c)       Affidavit of David Rees affirmed 12 May 2020.

Background

  1. By Supply and Installation Agreement dated 13 April 2018 (‘the Contract’), Façade agreed to carry out the installation of façade elements manufactured and supplied by Yuanda as part of the construction of commercial and residential towers at 447 Collins Street, Melbourne, Victoria, known as ‘the Arch on Collins’ (‘the Project’) for the price of $14.5 million.

  1. From September 2018 until the Contract was terminated in November 2019, Façade performed works under the Contract.[1]

    [1]On 6 November 2019, Façade served a notice of intention to suspend carrying out construction works under the Contract. On 13 November 2019, Façade suspended works on the Project pursuant to s 29 of the Act. On 14 November 2019, Yuanda purported to terminate the Contract by issuing a termination notice. On 14 November 2019, Façade responded to the purported termination notice by terminating the Contract and vacating the Project site.

  1. On 30 September 2019, Façade purported to provide a payment claim under s 14 of the Act for $4,584,820.68 (inclusive of GST) (‘the Payment Claim’).

  1. On 2 October 2019, Yuanda paid Façade the amount of $1,115,455 (inclusive of GST) reducing the amount claimed to $3,469,365.58.

  1. Yuanda failed to provide a payment schedule to Façade within 10 business days of receiving the Payment Claim, as required by s 15 of the Act.

  1. Accordingly, pursuant to s 15(4) of the Act, Façade contends that Yuanda became liable to pay the amount claimed on 30 October 2019, being the due date for the progress payments to which the Payment Claim related.

  1. By this proceeding, Façade seeks judgment for the amount claimed (after some conceded reductions) pursuant to s 16(2)(a) of the Act. However, pursuant to s 16(4), Façade is not entitled to judgment unless the Court is satisfied that:

(a)       Yuanda:

(i)became liable to pay the claimed amount to Façade under s 15(4) as a consequence of failing to provide a payment schedule within the time allowed by that section; and

(ii)failed to pay the whole or any part of the claimed amount on or before the due date for the progress payments to which the Payment Claim related; and

(b)      the claimed amount does not include any excluded amount.

  1. Yuanda contends that Façade is not entitled to judgment for the following reasons:

(a)the Payment Claim was invalid because it did not sufficiently identify the construction work or related goods and services to which the progress payments related within the meaning of s 14(2)(c), and therefore Yuanda did not become liable to pay the amount claimed to Façade under s 15(4); and/or

(b)the Payment Claim included excluded amounts within the meaning of ss 14(3)(b) and 16(4)(a)(ii).

The Payment Claim

  1. The Payment Claim was a three page excel spreadsheet which comprised the following:

(a)       The first page was headed:

Project: 447 Collins Street Project  Subcontract: Curtain Walling
Subcontract: Curtain Walling (Contract No. 3017/S00002)  Subcontract Value: $14,500,000
Issue Date: 30/09/2019 Variations: $5,698,425
Progress Claim No. 15: (Month of September 2019) Revised Contract Value: $20,198,425 (Excl GST)
Claimed to: Payment claim from:
YUANDA VIC PTY LTD Supplier: FAÇADE DESIGNS INTERNATIONAL Pty Ltd
Main Office: Unit 503, Level 5, 447 Kent Street, Sydney, NSW Address: 95 Stanhope Street, West Footscray, Vic, 3012
Vic Office: Suite 14, 255 Drummond St, Carlton
Vic 3000
ABN: 97 099 706 859
ABN: 99 166 473 089

(b)Under the heading ‘Contract Works’ were 72 line items identifying the percentage of the works completed to date.

(c)At the foot of the page was the following subtotal relating to ‘Original Contract Works’:

Description Total Complete to Date (Claimed in this Payment Claim) Previously Claimed Difference Yuanda Paid to Date (Excludes GST but includes any Security withholdings) Difference this Payment Claim
SUB-TOTAL – Original Contract Works $14,500,000.00 $9,913,452.50 $9,449,057.50 $464,395.00 $8,013,257.13 $1,900,195.38

(d)On the second page under the heading ‘Variations’ were 48 line items identifying work claimed by Façade to be variations under the Contract. The 25 variations (‘Claim Items’) set out in Appendix 1 to these reasons (‘the Variations Table’) are the individual claimed amounts comprising the Payment Claim. The Claim Items as finally claimed were summarised by Façade as follows:

Claim Item Reference Payment Claim Amount Revised Claim Amount
1B Original Contract Works $886,145.38 $886,145.38
2B 1099 $88,252.50 $88,252.50
3B 1109 $20,475.00 $20,475.00
4B 1120 $35,070.00 $35,070.00
5B 1128 $61,587.50 $61,587.50
6B 1129 $724,260.76 $724,260.76
7B 1131 $33,120.00 $33,120.00
8B 1132 $168,385.45 $168,385.45
9B 1140 $68,527.50 $68,527.50
10B 1141 & Credit Note 1141 $171,488.37 $171,488.37
11B 1142 & Credit Note 1142 $7,775.00 $7,775.00
12B 1143 & Credit Note 1143 $235,455.00 $235,455.00
13B 1144 & Credit Note 1144 $72,340.00 $72,340.00
14B 1145 & Credit Note 1145 $69,255.00 $69,255.00
15B 1146 & Credit Note 1146 $8,909.70 $8,909.70
16B 1149 $50,115.00 $50,115.00
17B 1150 $125,860.26 $125,860.26
18B 1151 $308,072.50 $292,502.50[2]
19B 1152 $36,187.50 $36,187.50
20B 1153 $85,217.90 $85,217.90
21B 1154 $5,500.00 $5,500.00
22B 1155 $140,301.11 $140,301.11
23B 1156 $19,255.63 $13,753.63[3]
24B 1157 $76,000.00 $76,000.00
25B 1158 $51,680.00 $35,360.00[4]
26B 1162 $64,154.37 $0 (not claimed)[5]
TOTAL ex GST $3,613,391.43 $3,511,845.00
Less Security (retention) - deducted from Item 1B ($459,422.63) ($459,422.63)
TOTAL ex GST $3,153,968.80 $3,052,422.43
TOTAL CLAIMED AMOUNT incl. GST $3,469,365.68 $3,357,664.67

[2]Reduced prior to trial.

[3]Reduced prior to trial.

[4]Reduced during closing submissions.

[5]Reduced during closing submissions.

  1. On the third page was the following table of totals, together with five explanatory notes, including a statement in accordance with s 14(2)(e) that the claim had been issued under the Act:

GROSS AMOUNT CLAIMED $15,611,877.91
Deduct Security - Maximum amount as per MC 20 & MC21 of Annexure J ([$14,500,000 - $725,000] x 5%) = $688,750.00
Security withholding in this payment claim is calculated as $9,913,452.50 less $725,000.00 (Site Establishment Fee ref
clause MC 20) = $9,188,452.50 x 5% = $459,422.62
As per Annexure J clause MC 21 Security should not withheld from Variations.

–$459,422.63

NET AMOUNT CLAIMED THIS PAYMENT CLAIM (Excluding GST but including Security withholding) $15,152,455.29
Add GST $1,515,245.53
NET AMOUNT CLAIMED THIS PAYMENT CLAIM (Including GST) $16,667,700.81
Actual Amount Paid to Date (Including GST) $12,082,880.13
Actual Security Payment Retain to date (incl. GST) $463,925.42
Balance Due (Including GST) $4,584,820.68

Nature of the hearing

  1. An application for judgment under s 16 of the Act is intended to be summary in nature.[6] However that does not mean that the principles relevant to applications for summary judgment under s 61 of the Civil Procedure Act 2010 (Vic) or ord 22 of the Supreme Court (General Civil Procedure) Rules 2015 (Vic) apply.[7] Before entering judgment the Court does not need to be satisfied that the respondent has no real prospect of success. Rather, the Court should finally determine on the evidence, whether it is satisfied of the matters referred to in s 16(4)(a) of the Act according to the principles referred to in paragraphs 40 to 41 and 54 to 59 below.[8] Any enquiry into whether the respondent has arguable cross-claims or defences would be contrary to

    [6]Façade Treatment Engineering Pty Ltd (in liq) v Brookfield Multiplex Constructions Pty Ltd (2016) 337 ALR 452, 464-5 [56], 474 [92], 479-80 [112].

    [7]John Beever v Roads Corporation [2018] VSC 635, [60] (Digby J).

    [8]TFM Epping Land Pty Ltd v Decon Australia Pty Ltd [2020] NSWCA 93, [11] (Basten JA with whom Meagher JA and Emmett AJA agreed) (‘Epping Land’); Style Timber Floor Pty Ltd v Krivosudsky (2019) 100 NSWLR 133, 142 [43] (Leeming JA) (‘Style Timber’).

    s 16(4)(b).

Relevant provisions of the Act

  1. Section 3 sets out the object of the Act as follows:

(1)The object of this Act is to ensure that any person who undertakes to carry out construction work or who undertakes to supply related goods and services under a construction contract is entitled to receive, and is able to recover, progress payments in relation to the carrying out of that work and the supplying of those goods and services.

(2)The means by which this Act ensures that a person is entitled to receive a progress payment is by granting a statutory entitlement to that payment in accordance with this Act.

(3)The means by which this Act ensures that a person is able to recover a progress payment is by establishing a procedure that involves—

(a)the making of a payment claim by the person claiming payment; and

(b)the provision of a payment schedule by the person by whom the payment is payable; and

(c)the referral of any disputed claim to an adjudicator for determination; and

(d)the payment of the amount of the progress payment determined by the adjudicator; and

(e)the recovery of the progress payment in the event of a failure to pay.

(4)       It is intended that this Act does not limit—

(a)any other entitlement that a claimant may have under a construction contract; or

(b)any other remedy that a claimant may have for recovering that other entitlement.

  1. Section 9(1) establishes the right to progress payments as follows:

On and from each reference date under a construction contract, a person—

(a)who has undertaken to carry out construction work under the contract; or

(b)who has undertaken to supply related goods and services under the contract—

is entitled to a progress payment under this Act, calculated by reference to that date.

  1. Section 14 sets out the requirements with respect to payment claims as follows:

(1)A person referred to in section 9(1) who is or who claims to be entitled to a progress payment (the claimant) may serve a payment claim on the person who, under the construction contract concerned, is or may be liable to make the payment.

(2)       A payment claim—

(a)       must be in the relevant prescribed form (if any); and

(b)       must contain the prescribed information (if any); and

(c)must identify the construction work or related goods and services to which the progress payment relates; and

(d)must indicate the amount of the progress payment that the claimant claims to be due  (the claimed amount); and

(e)       must state that it is made under this Act.

(3)       The claimed amount—

(a)may include any amount that the respondent is liable to pay the claimant under section 29(4);

(b)       must not include any excluded amount.

  1. Section 15 provides for the serving of a payment schedule in reply to a payment claim and the consequences of failing to do so as follows:

(1)A person on whom a payment claim is served (the respondent) may reply to the claim by providing a payment schedule to the claimant.

(2)       A payment schedule—

(a)       must identify the payment claim to which it relates; and

(b)must indicate the amount of the payment  (if any) that the respondent proposes to make  (the scheduled amount); and

(c)must identify any amount of the claim that the respondent alleges is an excluded amount; and

(d)      must be in the relevant prescribed form (if any); and

(e)       must contain the prescribed information (if any).

(3)If the scheduled amount is less than the claimed amount, the schedule must indicate why the scheduled amount is less and (if it is less because the respondent is withholding payment for any reason) the respondent's reasons for withholding payment.

(4)       If—

(a)       a claimant serves a payment claim on a respondent; and

(b)the respondent does not provide a payment schedule to the claimant—

(i)within the time required by the relevant construction contract; or

(ii)within 10 business days after the payment claim is served;

whichever time expires earlier—

the respondent becomes liable to pay the claimed amount to the claimant on the due date for the progress payment to which the payment claim relates.

  1. Section 16 establishes the rights of a claimant arising from a respondent’s failure to provide a payment schedule or failure to pay the claimed amount as follows:

(1)       This section applies if the respondent—

(a)becomes liable to pay the claimed amount to the claimant under section 15(4) as a consequence of having failed to provide a payment schedule to the claimant within the time allowed by that section; and

(b)fails to pay the whole or any part of the claimed amount on or before the due date for the progress payment to which the payment claim relates.

(2)       In those circumstances, the claimant—

(a)       may—

(i)recover the unpaid portion of the claimed amount from the respondent, as a debt due to the claimant, in any court of competent jurisdiction; or

(ii)make an adjudication application under section 18(1)(b) in relation to the payment claim; and

(b)       may serve notice on the respondent of the claimant's intention—

(i)to suspend carrying out construction work under the construction contract; or

(ii)to suspend supplying related goods and services under the construction contract.

(3)A notice referred to in subsection (2)(b) must state that it is made under this Act.

(4)If the claimant commences proceedings under subsection (2)(a)(i) to recover the unpaid portion of the claimed amount from the respondent as a debt—

(a)judgment in favour of the claimant is not to be given unless the court is satisfied—

(i)of the existence of the circumstances referred to in subsection (1); and

(ii)that the claimed amount does not include any excluded amount; and

(b)       the respondent is not, in those proceedings, entitled—

(i)        to bring any cross-claim against the claimant; or

(ii)to raise any defence in relation to matters arising under the construction contract.

  1. Section 10B defines excluded amounts as follows:

(1)This section sets out the classes of amounts (excluded amounts) that must not be taken into account in calculating the amount of a progress payment to which a person is entitled under a construction contract.

(2)       The excluded amounts are—

(a)any amount that relates to a variation of the construction contract that is not a claimable variation;

(b)any amount (other than a claimable variation) claimed under the construction contract for compensation due to the happening of an event including any amount relating to—

(i)        latent conditions; and

(ii)       time-related costs; and

(iii)      changes in regulatory requirements;

(c)any amount claimed for damages for breach of the construction contract or for any other claim for damages arising under or in connection with the contract;

(d)any amount in relation to a claim arising at law other than under the construction contract;

(e)any amount of a class prescribed by the regulations as an excluded amount.

  1. Section 10A defines claimable variations as follows:

(1)This section sets out the classes of variation to a construction contract (the claimable variations) that may be taken into account in calculating the amount of a progress payment to which a person is entitled in respect of that construction contract.

(2)The first class of variation is a variation where the parties to the construction contract agree—

(a)that work has been carried out or goods and services have been supplied; and

(b)as to the scope of the work that has been carried out or the goods and services that have been supplied; and

(c)that the doing of the work or the supply of the goods and services constitutes a variation to the contract; and

(d)that the person who has undertaken to carry out the work or to supply the goods and services under the contract is entitled to a progress payment that includes an amount in respect of the variation; and

(e)as to the value of that amount or the method of valuing that amount; and

(f)       as to the time for payment of that amount.

(3)       The second class of variation is a variation where—

(a)the work has been carried out or the goods and services have been supplied under the construction contract; and

(b)the person for whom the work has been carried out or the goods and services supplied or a person acting for that person under the construction contract requested or directed the carrying out of the work or the supply of the goods and services; and

(c)the parties to the construction contract do not agree as to one or more of the following—

(i)that the doing of the work or the supply of goods and services constitutes a variation to the contract;

(ii)that the person who has undertaken to carry out the work or to supply the goods and services under the construction contract is entitled to a progress payment that includes an amount in respect of the work or the goods and services;

(iii)the value of the amount payable in respect of the work or the goods and services;

(iv)the method of valuing the amount payable in respect of the work or the goods and services;

(v)the time for payment of the amount payable in respect of the work or the goods and services; and

(d)subject to subsection (4), the consideration under the construction contract at the time the contract is entered into—

(i)        is $5 000 000 or less; or

(ii)exceeds $5 000 000 but the contract does not provide a method of resolving disputes under the contract (including disputes referred to in paragraph (c)).

(4)If at any time the total amount of claims under a construction contract for the second class of variations exceeds 10% of the consideration under the construction contract at the time the contract is entered into, subsection (3)(d) applies in relation to that construction contract as if any reference to ‘$5 000 000’ were a reference to ‘$150 000’.

Issues for determination

  1. The issues raised in this proceeding require determination of the following questions:

(a) Is the Payment Claim a valid payment claim under s 14 of the Act?

(b)As a matter of statutory construction, in determining whether or not any Claim Item constitutes or includes an excluded amount, should the Court have regard to:

(i)the description of the Claim Item as appearing on the face of the Payment Claim; or

(ii)      evidence of the substance of the Claim Item.

(c)Does the inclusion of an excluded amount in the Payment Claim preclude the Court from giving judgment for any amount under s 16?

Principles of statutory interpretation

  1. The primary object of statutory construction is to construe the relevant provision so that its legal meaning is consistent with:

(a)the language of the relevant provision, being the text; and

(b)the legislative purpose of the statute.[9]

The legal meaning is ‘the meaning that the legislature is taken to have intended [the provision] to have’.[10] It may or may not be the same as the literal meaning.[11]

[9]Project Blue Sky Inc v Australian Broadcasting Authority (1998) 194 CLR 355, 381 [69] (McHugh, Gummow, Kirby and Hayne JJ) (‘Project Blue Sky’).

[10]Ibid 384 [78].

[11]Ibid.

  1. Accordingly, in statutory construction, the focus is on the text and the legislative purpose as follows:

(a)The primacy of the text has been emphasised by the High Court.[12] It has been said that the process of statutory interpretation starts and ends with the text.[13]

(b)To ascertain the legislative purpose, the Court first considers the text of the relevant provision in its context.[14] The context means:

(i) the whole of the Act or other instrument;

(ii)      the existing state of the law;

(iii)     the mischief that the statute was intended to remedy;[15] and

(iv)     the history of the legislative scheme.[16]

[12]See the examples cited in Commissioner of State Revenue v EHL Burgess Properties Pty Ltd [2015] VSCA 269, [56]–[63]. See also Di Paolo v Salta Constructions Pty Ltd [2015] VSCA 230, [32]–[48] (Osborn and Kyrou JJA); Lowe v The Queen (2015) 48 VR 351, 357–9 [12]–[18] (Warren CJ).

[13]FederalCommissioner of Taxation v Consolidated Media Holdings Ltd (2012) 250 CLR 503, 519 [39] (French CJ, Hayne, Crennan, Bell and Gageler JJ). The expression was adopted by the High Court in Thiess v Collector of Customs (2014) 250 CLR 664, 671 [22] (French CJ, Hayne, Kiefel, Gageler and Keane JJ) and by the Court of Appeal in DPP v Walters (2015) 49 VR 356, 358 [2] (Maxwell P, Redlich, Tate and Priest JJA).

[14]This approach ‘needs no ambiguity or inconsistency; it allows a court to consider the purposes of an Act in determining whether there is more than one possible construction’: Mills v Meeking (1990) 169 CLR 214, 235 (Dawson J).

[15]For this purpose, courts may have regard to reports of law reform bodies: CIC Insurance Ltd v Bankstown Football Club Ltd (1997) 187 CLR 384, 408 (Brennan CJ, Dawson, Toohey and Gummow JJ) (‘CIC Insurance’).

[16]Ibid; Federal Commissioner of Taxation v Consolidated Media Holdings (2012) 250 CLR 503, 519 [39] (French CJ, Hayne, Crennan, Bell and Gageler JJ); Cooper Brookes (Wollongong) Pty Ltd v Commissioner of Taxation (Cth) (1981) 147 CLR 297, 305-6 (Gibbs CJ), 324, 334 (Aickin J) (‘Cooper Brookes’).

  1. Section 35(b) of the Interpretation of Legislation Act1984 (Vic) provides that ‘[i]n the interpretation of a provision of an Act … consideration may be given to’ extrinsic material to ascertain the purpose of the legislation, even if the language is clear and unambiguous.[17] I emphasise ‘may’ because if the meaning of the text is plain ‘there is no occasion to look to the extrinsic material’.[18] As the Court of Appeal has said in the context of this section:

(a)‘it would be inappropriate to resort to parliamentary debates in order to seek to create an ambiguity in a section which is otherwise, at least in relative terms, clear’;[19] and

(b)‘the court needs to be careful not to permit recourse to this section to undermine its primary function of seeking to ascertain the intention of the legislation from the content of the Act itself’.[20]

This section does permit ‘a court to consider the purposes of an Act in determining whether there is more than one possible construction’,[21] but such material cannot displace the meaning of the statutory text.[22]

[17]Mills v Meeking (1990) 169 CLR 214, 235 (Dawson J); Humphries v Poljak [1992] 2 VR 129, 136-7 (Crockett and Southwell JJ); Alcoa Portland Aluminum Pty Ltd v Victorian Workcover Authority (2007) 18 VR 146, 159 [39] (Chernov JA with whom Maxwell ACJ and Neave JA agreed); Secretary to the Department of Justice and Regulation v Century 21 Australia Pty Ltd (2017) 53 VR 234, 248 [48] (Whelan, Beach and Ferguson JJA).

[18]Catlow v Accident Compensation Commission (1989) 167 CLR 543, 550 (Brennan and Gaudron JJ).

[19]Rizza v Fluor Daniel GTI (Australia) Pty Ltd [1999] 1 VR 405, 414 [37] (Chernov JA with whom Winneke P and Brooking JA agreed).

[20]Masters v McCubbery [1996] 1 VR 635, 646 (Winneke P).

[21]Mills v Meeking (1990) 169 CLR 214, 235 (Dawson J). See also Acts Interpretation Act 1901 (Cth) s 15AB.

[22]Federal Commissioner of Taxation v Consolidated Media Holdings Ltd (2012) 250 CLR 503, 519 [39] (French CJ, Hayne, Crennan, Bell and Gageler JJ); Northern Territory v Collins (2008) 235 CLR 619, 642 [99] (Crennan J).

  1. If the literal meaning of the text is consistent with the identified legislative purpose, the literal meaning will be accepted as the legal meaning. 

  1. However, if the literal meaning conflicts with the identified legislative purpose, a departure from the literal meaning may be justified. The resultant tension was described by Francis Bennion in Statutory Interpretation as follows:

Consideration of the enactment in its context may raise factors that pull in different ways.  For example the desirability of applying the clear literal meaning may conflict with the fact that this does not remedy the mischief that Parliament intended to deal with.[23]

[23]Francis Bennion, Statutory Interpretation: A Code (Butterworths, 3rd ed, 1997) 344; referred to with approval in Project Blue Sky (1998) 194 CLR 355, 384 [78] (McHugh, Gummow, Kirby and Hayne JJ).

  1. Examples of conflicts between the literal meaning and the identified legislative purpose which have justified departure from the literal meaning, include where:

(a)       the literal meaning would conflict with other provisions of the statute;

(b)      the literal meaning is inconsistent with the purpose of the statute;

(c)       the literal meaning is incapable of practical application; and

(d)adoption of the literal meaning would lead to a result that is absurd, unreasonable or anomalous.[24]

[24]Colonial Range Pty Ltd v CES-Queen (Vic) Pty Ltd [2016] VSCA 328, [53] (Warren CJ, Whelan JA and Riordan AJA) (citations omitted).

  1. If it is determined that such a conflict exists, the approach to reconciliation of the conflict is as follows:

(a)First, if an alternative construction is to be adopted as the legal meaning, it is necessary that the alternative construction is ‘reasonably open’[25] and ‘consistent with the language in fact used by the legislature’.[26]  This is necessary because ‘the task remains the construction of the words the legislature has enacted’.[27] ‘The purpose of legislation must be derived from what the legislation says, and not from any assumption about the desired or desirable reach or operation of the relevant provisions’.[28]

(b)Section 35(a) of the Interpretation of Legislation Act 1984 (Vic) provides that ‘a construction that would promote the purpose or object underlying the Act … shall be preferred to a construction that would not promote that purpose or object’. The choice is only between a construction that will promote the purpose and one that will not. The section is not directed to the choice ‘as to the construction which “will best achieve” the object of the Act’. [29]

(c)If the inconsistency between the literal meaning and the legislative purpose is the result of ‘simple, grammatical, drafting errors which if uncorrected would defeat the object of the provision’, an alternative construction which is consistent with the legislative purpose may be more ‘readily’ adopted.[30]

(d)After the identification of an alternative construction, the legal meaning will be determined by balancing:

(i)the strength of the literal meaning as against the alternative construction; and

(ii)the extent to which these meanings are consistent with the promotion of the legislative purpose.

[25]CIC Insurance (1997) 187 CLR 384, 408 (Brennan CJ, Dawson, Toohey and Gummow JJ).

[26]Taylor v The Owners—Strata Plan No 11564 (2014) 253 CLR 531, 549 [39] (French CJ, Crennan and Bell JJ). Although the Court was here referring to a modified meaning as one which added or omitted words, a fortiori, it must also be a requirement whenever a court is to infer that the legal meaning is other than a literal or grammatical meaning.

[27]Ibid.

[28]Certain Lloyd’s Underwriters Subscribing to Contract No IH00AAQS v Cross (2012) 248 CLR 378, 390 [26] (French CJ and Hayne J).

[29]Chugg v Pacific Dunlop Ltd (1990) 170 CLR 249, 262 (Dawson, Toohey and Gaudron JJ).

[30]Taylor v The Owners—Strata Plan No 11564 (2014) 253 CLR 531, 548 [38] (French CJ, Crennan and Bell JJ). The unique nature of the power to correct drafting errors was recognised in Inco Europe Ltd v First Choice Distribution (a firm) [2000] 2 All ER 109, [115] (Lord Nicholls): ‘It has long been established that the role of the courts in construing legislation is not confined to resolving ambiguities in statutory language. The court must be able to correct obvious drafting errors. In suitable cases, in discharging its interpretative function the court will add words, or omit words or substitute words. … This power is confined to plain cases of drafting mistakes.’

  1. This balancing exercise has been explained by the High Court as follows:

(a)‘If the choice is between two strongly competing interpretations, as we have said, the advantage may lie with that which produces the fairer and more convenient operation so long as it conforms to the legislative intention.  If, however, one interpretation has a powerful advantage in ordinary meaning and grammatical sense, it will only be displaced if its operation is perceived to be unintended.’[31]

(b)‘[I]nconvenience or improbability of result may assist the court in preferring to the literal meaning an alternative construction which … is reasonably open and more closely conforms to the legislative intent.’[32]

[31]Cooper Brookes (1981) 147 CLR 297, 321 (Mason and Wilson JJ).

[32]CIC Insurance (1997) 187 CLR 384, 408 (Brennan CJ, Dawson, Toohey and Gummow JJ).

  1. With respect to interpreting a provision as if it contained additional words, guidance has been provided by the plurality of the High Court in Taylor v The Owners—Strata Plan No 11564.[33] Their Honours stated that ‘the task remains the construction of the words the legislature has enacted’ and ‘any modified meaning must be consistent with the language in fact used by the legislature’.[34]  The plurality further said that whether an interpretation of a provision as if it contained additional words is justified involves a judgment of matters of degree, and explained:

That judgment is readily answered in favour of addition or omission in the case of simple, grammatical, drafting errors which if uncorrected would defeat the object of the provision. It is answered against a construction that fills ’gaps disclosed in legislation’ or makes an insertion which is ‘too big, or too much at variance with the language in fact used by the legislature’.[35]

[33](2014) 253 CLR 531 (French CJ, Crennan and Bell JJ).

[34]Ibid 549 [39].

[35]Ibid 548 [38] (citations omitted).

Is the Payment Claim a valid payment claim under s 14 of the Act?

  1. Section 14(2)(c) of the Act states that a payment claim ‘must identify the construction work or related goods and services to which the progress payment relates’.

  1. Failure to comply with this requirement will render the purported payment claim invalid.[36]

    [36]Seabay Properties Pty Ltd v Galvin Construction Pty Ltd [2011] VSC 183, [141(c)] (Vickery J) (‘Seabay Properties’).

  1. In John Beever (Aust) Pty Ltd v Paper Australia Pty Ltd, Lyons J comprehensively reviewed the authorities relating to the requirements for a payment claim to comply with s 14(2) of the Act. He summarised the principles as follows:

(1)the test of whether a claim is a payment claim for the purpose of the Act is objective;

(2)however, the manner in which compliance is tested is not overly demanding and should not be approached in an unduly technical manner or from an unduly critical point of view;

(3)for the purposes of the identification requirement, it is necessary that the payment claim reasonably identifies the construction work to which it relates such that the basis of the claim is reasonably comprehensible to the recipient party when considered objectively ie from the perspective of a reasonable party who is in the position of the recipient;

(4)in evaluating the sufficiency of the identification of the work, it is appropriate to take into account the background knowledge of the parties from their past dealings and prior exchanges of information including correspondence passing between them before and at the time of the payment claim. To that extent, the Court may go beyond the face of the document itself.[37]

[37][2019] VSC 126, [83] (‘John Beever’).

  1. The case before me brings into sharp focus the extent to which evidence may be admitted about ‘the background knowledge of the parties from their past dealings and prior exchanges of information including correspondence passing between them before and at the time of the payment claim’.[38] On the basis that it related to background knowledge, each party adduced extensive evidence relating to the subjective knowledge of employees, including whether employees understood or were able to calculate various Claim Items, communications between employees of the respective parties (both before and after service of the Payment Claim), and matters relevant to the merits and quantum of Claim Items in the Payment Claim. The procedures adopted resulted in a hearing with the features set out in paragraph 71 below. The question arises as to whether this evidence is relevant and admissible in determining the validity of the Payment Claim.

    [38]Ibid.

Is evidence of surrounding circumstances admissible in determining the validity of a payment claim?

  1. In my opinion, in determining whether a payment claim complies with s 14(2)(c) of the Act, the Court should not have regard to extrinsic evidence of surrounding circumstances[39] for the following reasons:

    [39]In the context of contractual interpretation ‘surrounding circumstances’ are ‘events, circumstances and things external to the contract which are known to the parties or which assist in identifying the purpose or object of the transaction, which may include its history, background and context and the market in which the parties were operating’: Mount Bruce Mining Pty Ltd v Wright Prospecting Pty Ltd (2015) 256 CLR 104, 117 [50] (French CJ, Nettle and Gordon JJ) (‘Mount Bruce’).

(a) Compliance with s 14(2)(c) of the Act is assessed on an objective basis. Evidence of conversations between parties or the subjective ability of parties to understand a payment claim should not be permitted.

(b) The proposition that the validity of payment claims under s 14 of the Act should be determined by reference to the face of the payment claim is supported by the weight of authority, including the following:

(i)In Jemzone Pty Ltd v Trytan Pty Ltd, Austin J held that the claimant was obliged to ensure that the payment claim complied ‘on its face’ with s 13(2) of the Building and Construction Industry Security of Payment Act 1999 (NSW) (‘the NSW Act’), being the equivalent of s 14(2) of the Act.[40] He observed that extraneous circumstances and previous communications should not be considered, stating:

[40](2002) 42 ACSR 42, 50 [41].

[T]he payment claim must on its face contain all the ingredients required by the Act. While the court should not take an unduly strict approach to the construction of the claim, it ought not to cure defects in the claim document by reference to extraneous circumstances or previous communications.[41]

[41]Ibid.

(ii)In Nepean Engineering Pty Ltd v Total Process Services Pty Ltd (in liq), Hodgson JA said that a payment claim would not be a nullity unless its failure to comply with s 13(2) of the NSW Act was ‘patent on its face’.[42] His Honour held that the test of validity was whether the payment claim ‘purports in a reasonable way to identify the particular work in respect of which the claim is made’.[43]

[42](2005) 64 NSWLR 462, 475 [36] (‘Nepean Engineering’).

[43]Ibid (Ipp JA agreeing at 484 [76], Santow JA dissenting on this point at 477 [47]) (emphasis added), quoted with approval in Epping Land [2020] NSWCA 93, [21] (Basten JA, with whom Meagher JA and Emmett AJA agreed). Adopted by Brookhollow Pty Ltd v R & R Consultants Pty Ltd [2006] NSWSC 1, [41(iv)] (Palmer J); Pacific General Securities Ltd v Soliman & Sons Pty Ltd (2006) 196 FLR 388, 399 [45] (Brereton J); KDV Sport Pty Ltd v Muggeridge Constructions Pty Ltd [2019] QSC 178, [17] (Brown J); T & M Buckley Pty Ltd v 57 Moss Rd Pty Ltd [2010] QCA 381, [35] (Philippides J, with whom Fraser and White JJA agreed).

(iii)Ipp JA agreed with the reasons of Hodgson JA and formulated the test of validity as being whether the payment claim ‘is made in good faith and purports to comply with s 13(2) of the [NSW] Act’.[44] 

[44]Nepean Engineering (2005) 64 NSWLR 462, 484 [76] (emphasis added), quoted with approval in Epping Land [2020] NSWCA 93, [22] (Basten JA, with whom Meagher JA and Emmett AJA agreed). Applied in AC Hall Airconditioning Pty Ltd v Schiavello (Vic) Pty Ltd (No. 2) [2008] VCC 1490, [19] (Judge Shelton).

(iv)In TFM Epping Land Pty Ltd v Decon Australia Pty Ltd, the New South Wales Court of Appeal held that, for the purposes of the New South Wales equivalent of s 16 of the Act, the question of whether a claim was made for a variation under the NSW Act was resolved by reference to the face of the claim.[45]  

[45]Epping Land [2020] NSWCA 93, [23] (Basten JA, with whom Meagher JA agreed), [92] (Emmett AJA).

In my opinion, the admission of extrinsic evidence of surrounding circumstances would be inconsistent with the assessment of compliance on the basis of the purport of the payment claim document.[46]

[46]Cf Clarence Street Pty Ltd v Isis Projects Pty Ltd (2005) 64 NSWLR 448, 457 [40] (Mason P with whom Giles and Santow JJA agreed). I do not read Mason P as considering the issue of whether ‘earlier contractual dealings’ would be relevant if not referred to in the payment claim.

(c)        To the extent that guidance can be gained by reference to another area of the law which requires an objective assessment, the exclusion of extrinsic evidence of surrounding circumstances is consistent with the ‘true rule’ as applied by Mason J in objectively interpreting contracts.[47] The principal reasons for excluding evidence of surrounding circumstances under the true rule are as follows:

[47]Codelfa Construction Pty Ltd v State Rail Authority of NSW (1982) 149 CLR 337, 352.

(i)Admission of such evidence would undermine the Court’s ability to avoid ‘difficult, time-consuming, expensive and problematic’ consideration of extraneous material.[48]

[48]Equuscorp Pty Ltd v Glengallan Investments Pty Ltd (2004) 218 CLR 471, 483 [35] (Gleeson CJ, McHugh, Kirby, Hayne and Callinan JJ).

(ii)The parties should be held to their written words, which appear plain on their face.[49] 

[49]See the discussion in J D Heydon, Heydon on Contract (Lawbook Co, 2019) 404-6 [9.1520].

(d) Similar considerations are particularly applicable to interpreting the requirements of a payment claim under the Act for the following reasons:

(i)If, as in this case, the validity of a payment claim under the Act could be challenged by reference to extrinsic evidence of surrounding circumstances, it could cause long delays and very substantial costs to be incurred in making claims under the Act. It is not consistent with the purpose of the Act for the assessment of whether a payment claim successfully identified the construction work for which payment is claimed, to be undertaken ‘in hindsight’,[50] or ‘after a full investigation of all the facts and circumstances’.[51]

(ii)The admission of evidence of dealings and communications between parties to a project, which may extend over years, on the basis of relevance to an extended view of ‘context’ or otherwise, ‘would drive a horse and cart (or perhaps a B-double) through the legislative scheme’.[52] As Vickery J explained in Hickory Developments Pty Ltd v Schiavello (Vic) Pty Ltd:

The Act also manifests another central aspiration, that of freedom from excessive legal formality. The provisions demonstrate a pragmatic concern to provide a dispute resolution process which is not bedevilled with unnecessary technicality. The Building and Construction Industry Security of Payment Act 1999 (NSW) has led to a spate of litigation in its relatively short life. If the Victorian Act became prone to challenges founded on fine legal points, an important object of the Act would be defeated by the twin adversaries of cost and time.[53]

(e)If the Court applies an objective test to assessing the validity of a payment claim and its supporting documents, such documents should be readily available for the Court’s assessment. Accordingly, determination of whether a payment claim has satisfied the requirement of s 14(2)(c) should be relatively straightforward. As was observed by Leeming JA in Style Timber Floor Pty Ltd v Krivosudsky:

Whether or not a document is a payment schedule must be something which is capable of ascertainment readily, and (at least ordinarily) without the assistance of a lawyer.[54]

[50]KDV Sport Pty Ltd v Muggeridge Constructions Pty Ltd [2019] QSC 178, [17] (Brown J).

[51]Nepean Engineering (2005) 64 NSWLR 462, 474 [34] (Hodgson JA).

[52]Abergeldie Contractors Pty Ltd v Fairfield City Council [2017] NSWCA 113, [47] (Basten JA, with whom Beazley ACJ and Meagher JA agreed) with reference to the prospect of the Court being required to consider when practical completion had been achieved, rather than when an appropriate certificate had been issued. In Coordinated Construction Co Pty Ltd v Climatech (Canberra) Pty Ltd [2005] NSWCA 229, [45] Basten JA identified the purpose of the Act as being ‘to provide a speedy and effective means of ensuring that progress payments are made during the course of the administration of a construction contract, without undue formality or resort to the law’.

[53](2009) 26 VR 112, 121 [46] (citations omitted).

[54] (2019) 100 NSWLR 133, 142 [44].

  1. As compliance is ‘not overly demanding and should not be approached in an unduly technical manner or from an unduly critical point of view’,[55] it is not unfair on the claimant that the payment claim and its supporting documents should identify the relevant work as required by s 14(2)(c).

    [55]John Beever [2019] VSC 126, [83] (Lyons J).

  1. The undemanding standard for compliance with s 14(2)(c) is demonstrated by the following principles:

(a)A payment claim is only required to be bona fide and reasonably purport to identify the particular work in respect of which the claim is made.[56]

[56]Nepean Engineering (2005) 64 NSWLR 462, 475 [36] (Hodgson JA), 484 [76] (Ipp JA).

(b)A payment claim is only a claim. It is unlike a payment schedule, which is intended to identify the scope of the dispute,[57] and articulate the respondent’s case to be determined by the adjudicator.[58]

[57]Clarence Street Pty Ltd v Isis Projects Pty Ltd (2005) 64 NSWLR 448, 455 [31] (Mason P with whom Giles and Santow JJA agreed) (‘Clarence Street’).

[58]Style Timber (2019) 100 NSWLR 133, 142 [45] (Leeming JA).

(c)A payment claim is not required to be as precise or as particularised as a pleading.[59] It need only provide sufficient detail to enable the respondent to identify the subject matter of the claim, not to make its own assessment of the amount payable.[60]

[59]Multiplex Constructions Pty Ltd v Luikens [2003] NSWSC 1140, [76] (Palmer J), quoted with approval in Style Timber (2019) 100 NSWLR 133, 143 [46] (Leeming JA).

[60]Clarence Street (2005) 64 NSWLR 448, 454 [25], 456-7 [38]-[39] (Mason P with whom Giles and Santow JJA agreed).

(d)Evidence of what officers did in response to a payment claim is unhelpful and whether they were able to understand the payment claim in fact is not relevant, because ‘the focus must remain on the objective circumstances, not the subjective intentions or perceptions of one of the parties’.[61]

(e)The fact that there may be typographical omissions or other errors does not invalidate a payment claim.[62] As was said by the Full Federal Court in Pyneboard Pty Ltd v Trade Practices Commission:

[T]he mere fact that parsing and analysis in the artificial atmosphere of the courtroom can lead to the identification of a number of latent ambiguities will not invalidate what, as a matter of commonsense, is reasonably clear.[63]

(f)To interpret the identification requirement under s 14(2)(c) as imposing a more exacting standard would encourage challenges to the validity of purported payment claims in the courts. The words of s 14(2)(c) do not mandate such an approach. I consider that a more exacting standard would not accord with the legislative intention. As Hodgson JA observed in Nepean Engineering, it cannot be consistent with the scheme of the Act for it to be construed as promoting:

[A] respondent [to] avoid the effect of the Act by not serving a payment schedule, and defending the [s 16] proceedings by raising a question as to identification, which could be as to just one of many items in a claim and could be such as to depend upon a very detailed examination of all the circumstances of the contract.[64]

[61]Ibid 457 [38]-[39].

[62]Nepean Engineering (2005) 64 NSWLR 462, 474 [34] (Hodgson JA).

[63](1982) 39 ALR 565, 571 (Northrop, Deane and Fisher JJ) which referred to notice requirements under the Trade Practices Act1974 (Cth), quoted with approval in the context of a payment claim in Walter Construction Group Ltd v CPL (Surry Hills) Pty Ltd [2003] NSWSC 266, [83] (Nicholas J).

[64]Nepean Engineering (2005) 64 NSWLR 462, 475 [38].

  1. A possible consequence of finding a payment claim to be valid simply by examining the claim document ‘on its face’, may be that the respondent is unable in fact to identify the work to which the claim related. However, this issue is remedied by the adjudication process set out in pt 3, div 2 of the Act. A respondent in such a case is entitled to serve a payment schedule refusing to make payment on the basis that it cannot identify the work. The dispute would then be referred to and settled by an adjudicator, who would determine whether or not the work was adequately identified in the payment claim under s 23 of the Act.[65]

    [65]Ibid 474-5 [35] (Hodgson JA), quoted with approval in Epping Land [2020] NSWCA 93, [21] (Basten JA, with whom Meagher JA and Emmett AJA agreed).

Principles to be applied in determining the validity of a payment claim

  1. On the basis of the above analysis, I would state the relevant principles as follows:

(a)A payment claim is construed objectively. A payment claim will comply with s 14(2)(c) if a reasonable building practitioner in the position of the recipient would have understood the payment claim to be bona fide and to purport in a reasonable way to identify the particular work in respect of which the claim is made.[66]

[66]Nepean Engineering (2005) 64 NSWLR 462, 475 [36] (Hodgson JA), 484 [76] (Ipp JA).

(b)The payment claim will include documentation expressly or impliedly referred to on the face of the payment claim. Documentation will be impliedly incorporated by reference if a reasonable building practitioner in the position of the recipient would have understood the payment claim to refer to such supporting documentation. By way of example:

(i)       In this case, the Payment Claim included a claim for $20,475 relating to Invoice 1109. It referenced Invoice 1109, but contrary to the notation in the Payment Claim, the invoice and supporting documents were not issued with the Payment Claim.[67] However, a reasonable building practitioner in the position of the recipient would have understood that the Payment Claim related to Invoice 1109 and its supporting documents, which had been sent to the respondent by email on 4 June 2019.

[67]See paragraphs 89 to 90 of Appendix 2.

(ii)      In John Beever (Aust) Pty Ltd v Paper Australia Pty Ltd, a payment claim sent to the respondent on 11 August 2014 identified the construction work as follows:

Project No: 20,139 PE705 - DIP Plant Mechanical Package 03
Order No / Contract: 50030556

Description:

Progress Claim 6 (MAY 2014).[68]

A reasonable building practitioner in the position of the recipient would have understood that the payment claim related to the ‘May 2014’ claim and its supporting documents, which had been sent to the respondent by email on 3 June 2014.[69]

[68][2019] VSC 126, [20] (Lyons J).

[69]Ibid [13].

  1. The objective approach requires reference to the context, being the construction contract and the entire payment claim, together with documentation expressly or impliedly referred to in the payment claim.[70] This process of reference to the context is ‘[o]rdinarily … possible by reference to the [construction] contract alone’,[71] together with the abovementioned documentation. The plurality in Mount Bruce Mining Pty Ltd v Wright Prospecting Pty Ltd said ‘ordinarily’ because: 

[S]ometimes, recourse to events, circumstances and things external to the contract is necessary [for the purpose of facilitating] … an understanding ‘of the genesis of the transaction, the background, the context and the market in which the parties are operating’.[72]

However, for the reasons expressed in paragraph 36(d) above, the courts should be wary to ensure that the exception allowing for evidence of context is not used as a Trojan horse to admit extrinsic evidence of surrounding circumstances, including prior dealings and the subjective intentions or understanding of parties, which is irrelevant.[73]

[70]See Mount Bruce (2015) 256 CLR 104, 116 [46] (French CJ, Nettle and Gordon JJ), analogous to the construction of a commercial contract.

[71]Ibid 116 [48].

[72]Ibid 117 [49] (citations omitted).

[73]Similar to the ‘true rule’ as explained in Codelfa Construction Pty Ltd v State Rail Authority of NSW 149 CLR 337, 352 (Mason J).

Is a payment claim invalid if any part fails to sufficiently identify the construction work?

  1. If the validity of the payment claim is determined in accordance with the principles set out in paragraphs 40 and 41 above, no question of severance arises. Section 14 of the Act does not permit a payment claim to be partially invalid because, for example, some aspect of an item is insufficiently particularised or there are arithmetical errors. In my opinion, the scheme of the Act contemplates such inadequacies being dealt with as part of the adjudication process.[74] As Hodgson JA said in Nepean Engineering:

In my opinion, a document which purports to be a payment claim does not fail to be a payment claim, within the meaning of the Act, merely because it can be seen, after a full investigation of all the facts and circumstances, not to successfully identify all the construction work for which payment is claimed. This could be the case, for example, if there is some typographical omission or other error in relation to one of a large number of items included in the claim; and the question whether or not the other party, by reason of its knowledge of the project, would have been able to fill in or correct that error could be one depending on a great deal of evidence concerning the circumstances of the case. In my opinion, it is inconceivable that it was the intention of the legislature that the existence of a payment claim under the Act should depend on that kind of consideration.[75]

[74]Nepean Engineering (2005) 64 NSWLR 462, 474-5 [35] (Hodgson JA), quoted with approval in Epping Land [2020] NSWCA 93, [21] (Basten JA, with whom Meagher JA and Emmett AJA agreed).

[75]Nepean Engineering (2005) 64 NSWLR 462, 474 [34] (emphasis added).

Conclusion

  1. In this case, the Payment Claim served by Façade was detailed. It attached and referred to extensive supporting documentation. In my opinion, for the reasons stated above and in Appendix 2, a reasonable building practitioner in the position of Yuanda would have understood the Payment Claim to be bona fide and to purport in a reasonable way to identify the particular work in respect of which the claim was made. Accordingly, I consider that the Payment Claim was a valid claim under s 14 of the Act.

  1. Yuanda contended that many of the individual Claim Items comprising the Payment Claim failed to sufficiently identify the construction work or related goods and services to which the progress payments related. In my opinion, for the reasons expressed above, the validity of the Payment Claim is to be considered in its totality.  

  1. In case I am in error, I have set out my reasons for rejecting Yuanda’s submissions with respect to each of the disputed Claim Items in Appendix 2 to these reasons. In summary, Yuanda’s contentions of insufficient identification were principally made on one of the following grounds, which I reject for the reasons set out below:

(a) The Claim Item was not a claim for construction work under the Act, but was rather a claim for:

(i)       idle time;

(ii)      acceleration of works; and/or

(iii)     compensation arising from the inability to access the site.

In my opinion, the relevant invoices and supporting documentation provided in respect of each such Claim Item sufficiently identified the services (being the provision of labour) which Façade claimed related to construction work. If Yuanda had wanted to contend that the claimed work was not construction work or related goods and services, it should have done so in a payment schedule.

(b)       The Claim Item was a claim for construction work:

(i)referred to in the Settlement Agreement which was back-dated and invalid;

(ii)with insufficient details of how the claimed amount was calculated; and/or

(iii)that had not been properly authorised.

In my opinion, the relevant invoices and supporting documentation provided in respect of each such Claim Item sufficiently identified the construction work claimed. A payment claim does not need to include sufficient particulars to disclose the calculation of the claimed amount. The validity of supporting documentation is a matter for determination by an adjudicator after service of a payment schedule, not for the Court under s 16 of the Act.

(c)        Mr Nguon, a project manager employed by Yuanda, gave evidence that he was unable to comprehend the construction work referred to in particular Claim Items and that insufficient details were provided as to how the claim was calculated. Façade contested this evidence on the basis that Yuanda had filed a payment schedule out of time, which demonstrated that it did comprehend the construction work to which the Payment Claim related.

In my opinion, none of this evidence is relevant to an inquiry into compliance with s 14(2)(c) because evidence of the subjective opinions and knowledge of the parties’ employees is not admissible for the purpose of the objective inquiry into the validity of a payment claim.

(d)       The Payment Claim included insufficient particulars of the request or direction from Yuanda to enable identification of the claims. 

With respect to each of the Claim Items in the Variations Table, I have found that the Payment Claim and supporting documentation expressly or inferentially claimed that the relevant work was requested or directed by Yuanda or a person acting on its behalf. Yuanda’s contention that, on full investigation of the facts and circumstances, it was unable to identify the construction work claimed because:

(i)       the work claimed was not the work so requested or directed; or

(ii)the claim included both work within the scope of the Contract and additional work beyond the scope, which could not be differentiated,

is not relevant for the purpose of assessing compliance with s 14(2)(c). On the face of the invoices and supporting documentation, the claims were for work requested or directed by Yuanda. Any challenge to that claim should have been made in a payment schedule.

(e)        The evidence established that the Payment Claim included some incorrect references to site instructions and other documents alleged to contain or refer to a direction or instruction by Yuanda. 

Such errors do not invalidate a payment claim and an inquiry into whether a payment claim includes such errors is not relevant to the question of compliance with s 14(2)(c). For similar reasons, the fact that Façade acknowledged that there was some double counting between various Claim Items was not relevant because the Payment Claim, on its face, complied with s 14(2)(c).

As a matter of statutory construction, in determining whether or not any Claim Item constitutes or includes an excluded amount, should the Court have regard to:

(a)the description of the Claim Item as appearing on the face of the Payment Claim;  or

(b)      evidence of the substance of the Claim Item?

  1. Under s 16(4)(a)(ii) of the Act, before entering judgment in favour of a claimant, the Court must be satisfied that the claimed amount does not include any excluded amount.

Yuanda’s submissions

  1. Yuanda submitted that, for the Court to be satisfied that the claimed amount does not include any excluded amount, the Court should have regard to extrinsic evidence beyond the face of the claim, for the following reasons:

(a)It would be anomalous if extrinsic facts were considered to establish a prior communication as the basis for a claim under s 14(2)(c), but then excluded for the purposes of evaluating whether it included an excluded amount.

(b)It would be contrary to public policy to deprive a respondent of reference to contextual facts to establish that a claim was based on selective, misleading or even fraudulent creation and use of documents.

Accordingly, the respondent should not be prevented from raising matters relevant to the question of whether the payment claim contains excluded amounts.

Façade’s submissions

  1. Façade submitted as follows:

For the purpose of both s 14(3)(b) and s 16(4)(a)(ii) of the Act, in determining whether or not any Claim Item constitutes or includes an Excluded Amount, the starting point of the Court’s inquiry is the description of the Claim Item as appearing on the face of the Payment Claim. However, the Court is not otherwise restricted in its assessment and may, including on the initiative of a claimant, take into account evidence of the substance of the Claim Item, provided that by doing so, the Court does not entertain an argument that involves the introduction by a respondent of a defence under the contract, contrary to s 16(4)(b)(ii) of the Act.

Statutory scheme with respect to excluded amounts

  1. The concept of ‘excluded amounts’ was introduced by the Building and Construction Industry Security of Payment (Amendment) Act 2006 (Vic).

  1. On the second reading of the bill introducing the amendments, Mr Hulls, the Minister for Planning, stated that the bill substantially adopted recommendations contained in a report of the Security of Payment Working Group dated 8 October 2004 (‘the Report’).[76]

    [76]Victoria, Parliamentary Debates, Legislative Assembly, 9 February 2006, 219.

  1. The Report recommended that, if a respondent failed to serve a payment claim, it would be automatically liable to pay the amount owing without regard to defences or counterclaims. The Report recorded concerns with respect to applications to the courts for judgment where a respondent had failed to serve a payment schedule as follows:

Section 15 of the Act states that, if a respondent fails to serve a payment schedule and fails to pay the claimed amount by the due date, the respondent becomes liable to pay the claimed amount as a debt due to the claimant. This means that the claimant can recover the unpaid claimed amount, as a debt due, in a court of competent jurisdiction.

However, if a claimant does initiate court proceedings on the basis of section 15(4), it is uncertain whether the courts will undertake a full hearing, in order to evaluate the respondent’s defence or counter-claims, before making a final decision. This would ensure that both parties have been afforded natural justice. However, this approach does not appear to be consistent with the intention of section 15 of the Act, which was supposed to make a respondent automatically liable to pay a claimed amount if they fail to serve a payment schedule and if that amount is not paid when due.

Due to the uncertainty surrounding the purpose and effect of section 15, claimants are reluctant to apply to the courts on the basis of that provision. A court hearing of the dispute would be expensive, time consuming and the final decision may fall in favour of the respondent. Therefore, the risks of court proceedings are too high for many claimants.[77]

[77]Security of Payment Working Group, Review of the Building and Construction Industry Security of Payment Act, Victoria 2002 (Report, 8 October 2004) 44-5 (emphasis added).

  1. Accordingly, the Report recommended that the Act be amended to expressly state that, if the claimant exercises its right to apply to a court pursuant to s 15(4), the respondent is precluded from raising a defence or counterclaim.[78]

    [78]Ibid 46.

  1. The Act as amended, adopted the following scheme with respect to excluded amounts:

(a)Under s 10(3), an excluded amount must not be taken into account in calculating the amount of a progress payment.

(b)Under s 14(3)(b), the amount of the progress payment the claimant claims to be due must not include any excluded amount.

(c)Under s 15(2)(c), a payment schedule must identify any amount of the claim that the respondent alleges is an excluded amount.

(d)Under s 21(2)(ca), an adjudication response must identify any amount of the payment claim that the respondent alleges is an excluded amount.

(e)Under s 23(2A), an adjudicator must not take into account any part of the claimed amount that is an excluded amount in determining an adjudication application, and under sub-s (2B), the determination is void to the extent that it is based on an excluded amount.

(f)Under s 28B, a respondent may apply for the review of an adjudication determination only:

(i)on the ground that the adjudicated amount included an excluded amount;  and

(ii)if the respondent has identified that amount as an excluded amount in the payment schedule or the adjudication response.

(g)Under s 28C, a claimant can only apply for the review of an adjudication determination on the ground that an amount was wrongfully determined to be an excluded amount.

(h)Under s 28I(3), a review adjudicator must not take into account any excluded amount in determining an adjudication review application, and under sub-s (4) the determination is void to the extent that it is based on an excluded amount.

(i)Under s 28M, the respondent is required to pay an adjudicated amount (subject to the provisions with respect to applications for review in ss 28B and 28N).

(j)Under s 28N, a respondent is required to pay an amount under a review determination.

(k)Under s 28O, if the respondent fails to pay any part of an adjudicated amount in accordance with s 28M or s 28N, the claimant may request an adjudication certificate.

(l)Under s 28R, a party may recover the amount of an adjudication certificate as a debt in any court of competent jurisdiction.

(m)Under s 28R(5), a person who seeks to set aside a judgment cannot challenge an adjudication determination or a review determination, except under sub-s (6) on the ground that the person making the determination took into account a variation of the construction contract that was not a claimable variation.

Principles to be applied in relation to excluded amounts

  1. The first constructional choice presented by s 16(4)(a)(ii) is whether the Court must satisfy itself that:

(a)on the face of the Payment Claim, including the supporting documents, there is no claim for an excluded amount (‘the former construction’); or

(b)after full investigation of the facts and circumstances, there is no claim for any amount which should be properly classified as an excluded amount (‘the latter construction’).

  1. In my opinion, the former construction should be preferred for the following reasons:

(a) As set out above, the Act provides a detailed mechanism that:

(i)       prohibits claimants claiming for excluded amounts;

(ii)requires respondents to identify any amount it alleges is an excluded amount; and

(iii)directs adjudicators and review adjudicators not to take into account any part of a claimed amount that is an excluded amount and makes any determination void to the extent that it does so.

(b)       This scheme is detailed and it is inconsistent with the legislative intention to:

(i)       permit avoidance of the scheme;

(ii)      substitute an investigative role on the courts; and

(iii)     advantage respondents who do not provide a payment schedule.

(c)        It would be strange indeed if, by failing to provide a payment schedule, the respondent could avoid:

(i)       the need to identify any excluded amount to an adjudicator; and

(ii)the balance of the scheme adopted by the Act with respect to an adjudicator not taking into account excluded amounts,

but rather argue, as a knock out point before the Court, that it should not be satisfied that ‘the claimed amount does not include an excluded amount’. As was observed by Hodgson JA in Nepean Engineering, such a construction would result in ‘a very detailed examination of all the circumstances of the contract’ and be ‘wholly inconsistent with the scheme of the Act’.[79]

[79](2005) 64 NSWLR 462, 475 [38] commenting on a construction of the Act that permits a respondent to oppose judgment under the New South Wales equivalent of s 16 of the Act on the basis that the payment claim was invalid. See paragraph 39 above.

(d) As it is accepted that the inclusion of an excluded amount does not invalidate a payment claim for the purposes of the adjudication scheme under the Act, it is not consistent with the object of the Act for such an inclusion to effectively invalidate a payment claim for the purposes of s 16. As Hodgson JA said in Nepean Engineering:

If a payment claim which thus purports to identify the work in respect of which the claim is made is sufficient to support a valid determination … it would in my opinion be wholly inconsistent with the scheme of the Act if it was not also sufficient to support a cause of action under s 15 of the [NSW Act] in a case where no payment schedule is served.[80]

[80]Ibid.

(e)There are textual differences in the respective roles to be undertaken by the Court and the adjudicator under the Act, being:

(i)under s 23, the adjudicator is required to determine an adjudication application by considering the matters referred to in sub-s (2) and not taking into account any part of the claimed amount that is an excluded amount under sub-s (2A); and

(ii)under s 16, the Court is not required to give consideration to specified matters or to make a determination.

The task imposed on the Court is different to the task imposed on the adjudicator, which is consistent with the fact that the Act requires the Court to be satisfied that there is no claim for an excluded amount.

(f)Courts investigating and determining final claims would be inconsistent with the purpose of the Act. The Act is specifically not intended to determine the final rights of the contracting parties,[81] and must be construed in that context. Applying the latter construction would result in a final determination of contractual liability issues with all the associated delay and expense, which the Act is intended to avoid. Such a final determination after a full hearing on the merits may well give rise to an issue estoppel on aspects of contractual liability, which would be inconsistent with s 47 of the Act.

[81]Building and Construction Industry Security of Payment Act 2002 (Vic) s 47.

(g)Permitting the respondent to lead evidence to establish that a claimed amount was an excluded amount, for example because it was not a claimable variation, would permit it to raise a defence in relation to matters arising under the construction contract, which is not permitted under s 16(4)(b)(ii). As Basten JA observed in Epping Land:

It is possible that the amounts claimed for variations did not properly arise under the contract because, for example, relevant procedural steps had not been followed. However, to pursue that issue would involve raising a defence in relation to matters arising under the construction contract, a course prohibited by s 15(4) of the Security of Payment Act. Had the principals wished to challenge the claim on that basis, they could have done so by way of a payment schedule provided pursuant to s 14, indicating the claimed items intended to be paid and the reason for non-payment of any item not accepted. Such an issue would then have been addressed by the adjudicator appointed to determine any dispute thus arising. However, that course was not taken.[82]

To similar effect Emmett AJA said:

The scheme of the Payment Act contemplates that disputes be determined by an adjudicator. The Principal failed to take advantage of the procedure afforded to it. Contractual defences are not intended to be raised at this stage of adjudication.[83]

I am mindful of the fact that their Honours were considering the NSW Act which does not include s 16(4)(a)(ii). However I consider the construction which permits the subsection to be read consistently with the prohibition on raising a defence, as construed under the NSW Act, is to be preferred.

[82][2020] NSWCA 93, [20].

[83]Ibid [95].

  1. In Epping Land, the New South Wales Court of Appeal considered an appeal against a judgment made in favour of a builder under the NSW Act. The relevant facts were that:

(a)The builder lodged a progress claim under the NSW Act seeking payment of some $6.4 million.

(b)The principals failed to provide a payment schedule to the builder within 10 business days after service of the payment claim.

(c)The builder applied for judgment. The principals resisted judgment on various grounds, including that the payment claim was invalid.[84]

(d)The principals submitted that it was arguable that, as a matter of construction of the payment claim, the amounts claimed for variations were not available pursuant to the contract, but were rather a quantum meruit claim. A quantum meruit claim does not give rise to an entitlement to a progress payment under the NSW Act because it would not arise ‘under a construction contract’.[85]

[84]Ibid [1]-[2], [15].

[85]Ibid [18].

  1. Basten JA accepted that it was possible that the amounts claimed for variations did not properly arise under the contract, but said that, if the principals had wished to challenge the claim on that basis, they could have done so by way of a payment schedule.[86] His Honour rejected the principals’ contention because ‘[o]n the face of the claim, the payments were sought under the contract’,[87] stating:

If [the variation claims] were not available under the contract, it might have been open to an adjudicator to reject those elements of the claimed amount. It was not open to the principals to resist judgment for the full amount of the payment claim on this basis. The trial judge was correct to reject this contention.[88]

[86]Ibid [20].

[87]Ibid [23].

[88]Ibid.

  1. Similarly, Emmett AJA rejected the principals’ contention, stating:

There is nothing in the Progress Claim to suggest that the claim for variations was made otherwise than under the Contract. Indeed, the Progress Claim states specifically that they are made under the Contract. Had the Principal filed a payment schedule, which it failed to do, it would have been a matter for an adjudicator to determine whether the amounts claimed were payable under the Contract.[89]

[89]Ibid [92].

  1. Accordingly, in my opinion, s 16(4)(a)(ii) requires a Court to be satisfied that the claimed amount does not include, on the face of the payment claim, any excluded amount.

Conclusion

  1. The Payment Claim relating to Invoice 1162 was, on its face, a claim for interest under the Act and therefore an excluded amount within the meaning of s 10B(2)(d), a matter ultimately conceded by Façade.

  1. Except for Invoice 1162, for the reasons set out in Appendix 2, I have rejected Yuanda’s submissions that the Payment Claim included claims for excluded amounts. I have found that on the face of the Payment Claim, including the supporting documentation, each of the Claim Items in the Variations Table were expressly or inferentially claimed on the basis that the relevant work was carried out in accordance with a request or direction or the agreement of Yuanda or a person acting on its behalf.

  1. In summary, Yuanda’s contentions that the Payment Claim included claims for excluded amounts were principally made on one of the following grounds, which I reject for the reasons set out below:

(b)The description of the work was contained in the Daily/Hourly Labour Records and timesheets executed by Yuanda.

  1. The Payment Claim did not, on its face, include a claim for an excluded amount for the following reasons:

(a)        The work was claimed as being pursuant to Order/Variation Requisitions and Yuanda NCRs.

(b)       The Payment Claim was expressed to be for ‘On site additional works requested by Yuanda’.

(c)        Invoice 1143 described the work as ‘On Site Variations issued by Yuanda’.

  1. The evidence of the subjective knowledge and inquiries of Mr Nguon and Ms Rozon is not admissible for the purposes of determining the validity of the Payment Claim or whether the Payment Claim, on its face, includes a claim for an excluded amount.

Invoice 1144

  1. The Payment Claim relating to Invoice 1144 claimed $73,960 for the work described in the Variations Table, although Façade subsequently issued a credit note for $1,620.  The claim was supported by the following documents provided with the Payment Claim:

(a)        Invoice 1144 dated 29 August 2019 for $73,960 which described the work as:

447 CS - Supply of Additional Equipment & Labour as per Yuanda Variation No VAR-021 & Multiplex SI - 000344.

(b)       A table headed ‘Aug-19’ which set out equipment and labour costs.

(c)        Yuanda Order/Variation Requisition 447CS-OR0012 dated 22 August 2019 which referenced VAR 021 and noted the reason for order as ‘Variation to contract-MPX Site Instruction to procure additional plant and works’.

(d)       Yuanda Subcontractor Advice 000344 dated 3 May 2019 which attached an email referring to MPX SI-000335, stating:

As per discussed, MPX have acknowledged that they will reimburse costs of plant and equipment hire to assist with catching lost install opportunities at the east tower. Please refer Aconex MPX-CONTADV-009389 sent today.

As such, please proceed to procure plant and equipment require as instructed.

(e)        Various invoices from Leader Access Hire, Mass Group, Chadwick Forklifts and Daca Construction.

Yuanda’s submissions

  1. Yuanda submitted that the Payment Claim did not sufficiently identify the construction work relating to Invoice 1144 for the following reasons:

(a)The Payment Claim referenced Multiplex Site Instruction MPX-SI-000344 which did not exist.

(b)Timesheets were not provided for the labour costs, except for the table headed ‘Aug-19’.

(c)Multiplex Site Instruction MPX-SI-000335 was to ‘hire the additional equipment to assist with the recovery work’ and made no reference to additional labour.

(d)The Order/Variation Requisition referencing VAR 021 did not refer to additional labour and did not purport to relate to Invoice 1144.

  1. Yuanda further submitted that this Claim Item included an excluded amount for the following reasons:

(a)The site instruction only directed the hiring of additional equipment, not additional labour.

(b)The Yuanda subcontractor advice only referred to the ‘costs of plant and equipment hire to assist with catching lost install opportunities at the east tower’ which, on its face, does not suggest that the works were additional to the contractual scope of the works.

Conclusion

  1. In my opinion, the Payment Claim has sufficiently identified the construction work referrable to Invoice 1144 for the following reasons:

(a)The invoice referred to the additional equipment and labour being required pursuant to an Order/Variation Requisition and Multiplex site instruction.

(b)The Order/Variation Requisition referred to it as a variation.

(c)The fact that the Payment Claim erroneously referred to Multiplex Site Instruction MPX-SI-000344, rather than Yuanda Subcontractor Advice 000334 or Multiplex Site Instruction MPX-SI-000335, does not invalidate the Payment Claim.

(d)Yuanda Subcontractor Advice 000334 specifically referred to the work requested.

(e)If Yuanda wanted to assert that the labour exceeded the request, direction or agreement, it could have done so in a payment schedule.

  1. For the same reasons, I am satisfied that the Payment Claim with respect to Invoice 1144 does not claim any excluded amount. This Claim Item is a claim for construction work or related goods and services based on variations which, as is apparent from the face of the supporting documents, is based on it being requested, directed or agreed by Yuanda.

Invoice 1145

  1. The Payment Claim relating to Invoice 1145 claimed $74,565 for the work described in the Variations Table, although Façade subsequently issued a credit note for $5,310.  The claim was supported by the following documents provided with the Payment Claim:

(a)       Invoice 1145 dated 29 August 2019 for $74,565 which described the work as:

447 CS - Provide Alimak Scar acceleration works after hours to Residential Tower Refer Yuanda Variation No VAR-020.

(b)Daily/Hourly Labour Records which referenced MPX-SI-000475 and described the work as ‘Alimak Scar’.

(c)Yuanda Order/Variation Requisition 447CS-OR0010 dated 20 August 2019 which referenced VAR 020 and noted the reason for the order as ‘over time work for Alimak Scar 1-3, grid 1b to 2a of East Elevation’.

(d)Yuanda Subcontractor Advice dated 12 June 2019 which referenced MPX-SI-000475 and instructed Façade to ‘provide labour after 5.30pm each night to assist in maintaining the recovery strategy’ and to ‘continue with overtime works for the month of June’.

(e)Fifteen Yuanda timesheets, each sighting MPX-SI-000475 and executed by a representative of Yuanda.

Yuanda’s submissions

  1. Yuanda submitted that the Payment Claim did not sufficiently identify the construction work relating to Invoice 1145 for the following reasons:

(a)        Mr Nguon gave evidence that the timesheets did not identify which workers worked the additional hours and that he could not assess the amount claimed for additional labour.

(b)       The failure to obtain the signature of a Multiplex representative on the timesheets was contrary to the Multiplex site instruction and Yuanda subcontractor advice and meant that the work was not sufficiently identified.

(c)        The claim did not identify how a request for additional labour is a change to the scope of the contractual works.

  1. Yuanda further submitted that this Claim Item included an excluded amount for the following reasons:

(a)        The Multiplex site instruction and Yuanda subcontractor advice did not direct work beyond June 2019, however the timesheets related to work in July 2019.

(b)       The work was a claim for compensation due to the happening of an event, not a claim for a change to the scope of the works.

Conclusion

  1. In my opinion, the Payment Claim has sufficiently identified the construction work referrable to Invoice 1145 for the following reasons:

(a)The invoice referred to the after-hours work being required due to ‘Yuanda Variation No VAR-020’.

(b)The Daily/Hourly Labour Records set out the labour claim in some detail and referenced the relevant Multiplex site instruction.

(c)The Order/Variation Requisition confirmed the direction for overtime work.

(d)If Yuanda wanted to assert that:

(i)the work was supplied outside the period it was requested;

(ii)the failure to obtain Multiplex’s signature disentitled Façade; or

(iii)the work did not constitute a change to the scope of the works,

it could have made such assertion in a payment schedule.

  1. For the same reasons, I am satisfied that the Payment Claim with respect to Invoice 1145 does not claim any excluded amount. This Claim Item is a claim for construction work or related goods and services, being the work referred to in ‘Yuanda Variation No VAR-020’ which, as is apparent from the face of the supporting documents, is based on it being requested, directed or agreed by Yuanda.

Invoice 1146

  1. The Payment Claim relating to Invoice 1146 claimed $9,172 for the work described in the Variations Table, although Façade subsequently issued a credit note for $262.30.  The claim was supported by various documents, including Invoice 1146 dated 29 August 2019 for $9,172.20 which described the work as:

447 CS - Supply of qualified Riggers to operate all Mast Climbers 1, 2, 3, 4 & 5. Refer to Yuanda variation 447CS-OR0016 .

  1. Yuanda does not contest this Claim Item.

Invoice 1149

  1. The Payment Claim relating to Invoice 1149 claimed $50,115 for the work described in the Variations Table. It was supported by the following documents provided with the Payment Claim:

(a)Invoice 1149 dated 24 September 2019 for $50,115 which described the work as:

447 Collins Street; Procure additional plant & labour refer to Yuanda Variation no VAR-021 & Multiplex Sl-000334.

(b)A table headed ‘INVOICE – 1149’ and ‘Sep-19’ which set out the equipment and labour costs.

(c)Yuanda Order/Variation Requisition 447CS-OR0012 dated 22 August 2019 which referenced VAR 021 and noted the reason for the order as ‘Variation to contract–MPX Site Instruction to procure additional plant and works’.

(d)Yuanda General Correspondence dated 22 August 2019 which referenced MPX-SI-000335 and VAR 021, stating:

Please refer to MPX site instruction and Yuanda confirmation of the hire of additional access equipment & 2 labourers

until level 13 -17 are complete.

(e)Various invoices from Leader Access Hire, Mass Group, Chadwick Forklifts and Daca Construction.

Yuanda’s submissions

  1. Yuanda submitted that the Payment Claim did not sufficiently identify the construction work relating to Invoice 1149 for the following reasons:

(a)The invoice referred to Multiplex Site Instruction MPX-SI-000334 which did not exist. 

(b)No timesheets were provided with the Payment Claim and the cost calculation in the table headed ‘Sep-19’ was too general.

(c)The Order/Variation Requisition referred to Invoice 1121 rather than Invoice 1149.

(d)Multiple site instruction MPX-SI-000335 only instructed the hire of additional equipment ‘to assist with the recovery work’ and did not identify labour.

(e)The claim did not identify how additional labour can constitute a change in the scope of the works. The work was a claim for compensation due to the happening of an event.

  1. Yuanda further submitted that this Claim Item included excluded amounts because:

(a)        Multiplex Site Instruction MPX-SI-000334 did not exist; and

(b)       VAR 021 did not support Invoice 1149 and therefore was not a request for labour.

Conclusion

  1. In my opinion, the Payment Claim has sufficiently identified the construction work referrable to Invoice 1149 for the following reasons:

(a)The Yuanda general correspondence provided in support of the invoice referred to ‘the hire of additional access equipment & two labourers until level 13 -17 are complete’. The additional equipment and labour was required due to an Order/Variation Requisition and Multiplex site instruction.

(b)The Order/Variation Requisition expressly referred to the work as ‘Variation to contract – MPX Site Instruction to procure additional plant and works’.

(c)The error in the Multiplex site instruction number did not invalidate the Payment Claim. In any event, the Multiplex note of 2 May 2019 contained in the general correspondence, which was attached to the Payment Claim, correctly referred to MPX-SI-000335.

(d)If Yuanda wanted to assert that the additional labour exceeded the request, direction or agreement, or did not constitute a change to the scope of the works, it could have done so in a payment schedule.

  1. For the same reasons, I am satisfied that the Payment Claim with respect to Invoice 1149 does not include a claim for any excluded amount. This Claim Item is a claim for construction work or related goods and services, being the hire of additional access equipment and two labourers which, as is apparent from the face of the supporting documents, is based on it being requested, directed or agreed by Yuanda.

Invoice 1150

  1. The Payment Claim relating to Invoice 1150 claimed $125,860.26 for the work described in the Variations Table. It was supported by the following documents provided with the Payment Claim:

(a)Invoice 1150 dated 24 September 2019 for $125,860.26 which described the work as:

447 CS -Supply of qualified riggers for the operation of all Mast Climbers 1, 2, 3, 4 & 5. Refer to Yuanda variation 447CS-OR0016.

(b)Yuanda Order/Variation Requisition 447CS-OR0016 dated 20 September 2019 which noted the reason for the order as:

447CS-OR0016-Hiring Qualified Rigger as per Work Safe Instruction to operate M C Winch (M.C 1; 2;3;4;5)

(c)Daily/Hourly Labour Records which referenced Site Records 554, 565-573, 579 and NCR 447CS-OR0016, and described the work respectively as ‘[h]ire of Maeda 285 and Crane Driver for MC3’ and ‘[s]upply of Riggers’ for MC1, MC3, MC4 and/or MC5.

(d)Site Records 554, 565-573 and 579, signed by representatives of Façade and Yuanda.

Yuanda’s submissions

  1. Yuanda submitted that the Payment Claim did not sufficiently identify the construction work relating to Invoice 1150 because Mr Nguon ‘understood that there [was] double claiming for the same work’ and further said that ‘the duplicated Site Records 0568 and 0571 record inconsistent times’.

Conclusion

  1. In my opinion, Mr Nguon’s evidence as to his subjective understanding is inadmissible. If Yuanda wanted to assert that the invoice involved double counting, it could have done so in a payment schedule.

Invoice 1151

  1. The Payment Claim relating to Invoice 1151 claimed $308,072.50 for the work described in the Variations Table. It was supported by the following documents provided with the Payment Claim:

(a)Invoice 1151 dated 24 September 2019 for $308,072.50 which described the work as:

447 CS - Supply of additional labour for late delivery of sliding doors and additional works requested by Yuanda. Refer to Yuanda variation no VAR-022 & 024. Also refer to Yuanda NCR-069, 028 & 010.

(b)Daily/Hourly Labour Records which referenced:

(xi)      Site Records 560-564, 574-576, 581, 591 and 595-613;

(xii)     NCR-YUA 069, 028 and 010; and

(xiii)    VAR 022 and 024;

and described the work respectively as:

(i)         sliding doors – logistic labour to install/load/remove via Alimak/goods lift;

(ii)       rope access – fall out of sequences works level 15-16;

(iii)      East Tower Lvl 1, 2 east elevation – change in methodology;

(iv)      rope guys and tower crane installation (Sunday work);

(v)       Plantroom weather seal flashing level 28-29;

(vi)      rotation of panels levels 27-30, 34, 35 – East Tower and 28-29 Comm Tower; and

(vii)     nose cone modification L16, 21-31 East Tower.

(c)Yuanda Order/Variation Requisition 447CS-OR0013 dated 23 August 2019 which referenced VAR 022 and noted the reason for order as ‘FDI Variation to contract’.

(d)Yuanda Order/Variation Requisition 447CS-OR0014 dated 4 September 2019 which referenced VAR 024 and noted the reason for order as ‘MPX & YUANDA Site Instruction– FDI Variation –Install Flashing’.

(e)Site Records 560-564, 574-576, 581, 591 and 595-613, which described the work consistently with the Daily/Hourly Labour Records.

Yuanda’s submissions

  1. Yuanda submitted that the Payment Claim did not sufficiently identify the construction work relating to Invoice 1151 for the following reasons:

(a)Mr Nguon gave evidence that the only additional works he could identify were logistics, which he could not separate from the installation charges that were already part of the scope of the works under the Contract.

(b)The supporting documents did not identify a request or direction by Yuanda to provide additional labour for the recovery program.

(c)Mr Nguon described the descriptions on the invoice as ‘summarised and vague’ and gave evidence that he was unable to assess them.

(d)Some works in this invoice were also included in Invoice 1157, which is conceded because Façade no longer presses an amount claimed in this invoice for $15,570.

(e)The Order/Variation Requisitions do not, on their face, refer to Invoice 1151. VAR 024 referenced ‘install flashing’ but only one item (being item 10) of the 29 items in the Daily/Hourly Labour Records referred to flashing.

Conclusion

  1. In my opinion, the Payment Claim has sufficiently identified the construction work referrable to Invoice 1151 for the following reasons:

(a)        The invoice referred to additional works and labour and referenced the relevant VARs and NCRs.

(b)       The Daily/Hourly Labour Records described the additional works.

(c)The site records referenced the relevant  NCRs and VARs and were each signed by a representative of Yuanda.

(d)If Yuanda wanted to assert that the work claimed exceeded the request, direction or agreement or that there was double counting, it could have done so in a payment schedule.

  1. For the same reasons, I am satisfied that the Payment Claim with respect to Invoice 1151 does not claim any excluded amount. This Claim Item is a claim for construction work or related goods and services, being the work referred to in VAR 022 and 024 and NCR 069, 028 and 010 which, as is apparent from the face of the supporting documents, is based on it being requested, directed or agreed by Yuanda.

  1. It is noted that Façade conceded that $15,570 should be reduced from this Claim Item because of a duplication with Invoice 1157.

Invoice 1152

  1. The Payment Claim relating to Invoice 1152 claimed $36,187.50 for the work described in the Variations Table. It was supported by the following documents:

(a)Invoice 1152 dated 24 September 2019 for $36,187.50 which described the work as:

447 CS - Alimak Scar Acceleration after hours due to delay of program by builder. Refer Yuanda Variation No VAR-020.

As per site instruction.

(b)Daily/Hourly Labour Records which referenced Site Records 557-559 and MPX-SI-00475, and described the work as ‘Alimak Scar – Acceleration Hours’.

(c)Yuanda Order/Variation Requisition 447CS-OR0010 dated 20 August 2019 which referenced VAR 020 and noted the reason for order as: ‘over time work for Alimak Scar 1-3, grid 1b to 2a of East Elevation’.

(d)Site Records 557-559 which described the work consistently with the Daily/Hourly Labour Records and were each executed by representatives of Façade and Yuanda.

(e)Yuanda Subcontractor Advice dated 12 June 2019 which referenced MPX-SI-000475, and stated: 

Please refer below MPX’s SI to continue to perform after hour works for your quoting when submitting costs.

Please ensure, all those day sheets are signed by a MPX staff member for cost submission.

(f)A table headed ‘summary variation invoices Sept 2019’ which referred to Invoices 1149-1158.

Yuanda’s submissions

  1. Yuanda submitted that the Payment Claim did not sufficiently identify the construction work relating to Invoice 1152 for the following reasons:

(a)The timesheets were not signed by a Multiplex representative, which was contrary to Yuanda subcontractor advice and Multiplex site instructions.

(b)Mr Nguon said the timesheets did not record the time of day that the works were completed and so he could not assess whether the work was completed in overtime hours.

(c)The documents did not identify how the additional labour was a change to the scope of the works.

  1. Yuanda further submitted that this Claim Item included excluded amounts for the following reasons:

(a)VAR 020, Multiplex Site Instruction MPX-SI-000475 and Yuanda subcontractor advice only related to overtime works in May and June, but the timesheets provided in support of the Payment Claim recorded overtime work in September 2019.

(b)Mr Nguon gave evidence that the acceleration claim was due to a change in the installation access, which was a claim for compensation due to the happening of an event.

Conclusion

  1. In my opinion, the Payment Claim has sufficiently identified the construction work referrable to Invoice 1152 for the following reasons:

(a)        The work was identified by reference to VAR 020 and MPX-SI-000475.

(b)       The work was described in the Payment Claim and the invoice as after-hours acceleration works.

(c)        The fact that the timesheets were not signed by a Multiplex representative may have constituted a defence, which could have been raised in a payment schedule.

(d)The site records referenced MPX-SI-00475 and VAR 020 and were signed by a representative of Yuanda.

(e)If Yuanda wanted to assert that the claim:

(viii)   was for work that exceeded a request, direction or agreement;

(ix)      did not constitute a change to the scope of the works; or

(x)        was a claim for compensation,

it could have done so in a payment schedule.

  1. For the same reasons, I am satisfied that the Payment Claim with respect to Invoice 1152 does not claim any excluded amount. This Claim Item is a claim for construction work or related goods and services, being acceleration works which, as is apparent from the face of the supporting documents, is based on it being requested, directed or agreed by Yuanda.

Invoice 1153

  1. The Payment Claim relating to Invoice 1153 claimed $85,217.90 for the work described in the Variations Table.

  1. Yuanda takes no issue with respect to this invoice.

Invoice 1154

  1. The Payment Claim relating to Invoice 1154 claimed $5,500 for the work described in the Variations Table.

  1. Yuanda takes no issue with respect to this invoice.

Invoice 1155

  1. The Payment Claim relating to Invoice 1155 claimed $140,301.11 for the work described in the Variations Table. It was supported by the following documents provided with the Payment Claim:

(a)Invoice 1155 dated 24 September 2019 for $140,301.11 which described the work as:

447 CS - For the Removal Re-Loading bay of MC2 materials due to restricted access by builder & Acceleration of Commercial Tower Level 28-29 Plantroom. Refer Yuanda variation no VAR-019.

As per SI-000756

(b)Daily/Hourly Labour Records which referenced Site Records 555 and 556 and Multiplex Site Instruction MPX-SI-000756, and described the work respectively as:

(i)       ‘Removal/Loading of MC2 (Labour)’; and

(ii)‘Removal/Loading of MC2 (Material & supply of equipment/plant)’.

(c)Yuanda Order/Variation Requisition 447CS-OR0009 dated 20 August 2019 which referenced VAR 019 and noted the reason for the order as ‘MPX -SI to accelerate L28-29 Plantroom and relocating MC2 Materials’.

(d)      Multiplex Site Instruction MPX-SI-000756 dated 14 August 2019.

(e)Yuanda Subcontractor Advice dated 15 August 2019 which requested the completion of works in accordance with the provided site instruction.

(f)Letter from Façade to Yuanda dated 15 August 2019 which submitted the ‘budget price for the relocation of materials to designated levels and logistics yard as per MPX site instruction SI-000756’.

(g)Multiplex Site Instruction MPX-SI-000756 dated 14 August 2019 which stated:

As per our meeting today regarding MC2 loading please provide the following :

-  Dollies to load materials up the Alimak and spread onto floors.

-  Provide ply protection to currently installed ASP flooring.

Please provide material costs to us for review as per normal process.

Please commence the delivery and movement of this material from 15/08/19 .

(h)Site Record 555 signed by representatives of Façade and Yuanda.

(i)Four invoices from Total Tools dated 29 and 30 August and 6 and 19 September 2019.

Yuanda’s submissions

  1. Yuanda submitted that the Payment Claim did not sufficiently identify the construction work relating to Invoice 1155 because the supporting timesheet, being Site Record 555, was not signed by Multiplex as required. As a result, Mr Nguon gave evidence that he could not approve the claim.

Conclusion

  1. In my opinion, the Payment Claim sufficiently identified the construction work referrable to Invoice 1155. Whether Multiplex’s signing of timesheets was a pre-requisite for liability was a matter that ought to have be raised by Yuanda in a payment schedule.

Invoice 1156

  1. The Payment Claim relating to Invoice 1156 claimed $19,255.63 for the work described in the Variations Table. It was supported by the following documents provided with the Payment Claim:

(a)Invoice 1156 dated 24 September 2019 for $19,255.63 which described the work as:

447 CS - Level 16 Residential Tower requires Rope Access due to nose cone manufacture defect. Refer to Yuanda variation No 010 & 021.

(b)Daily/Hourly Labour Records which referenced Invoice 1156 and NCR YUA-010 and described the work as ‘Required Rope Access Guys due to nose cone manufacture issues’.

(c)Yuanda Order/Variation Requisition 447CS-OR003 dated 15 August 2019 which referenced VAR 010 and noted the reason for the order as: ‘Big panels need tools – Spreader Beam to lift and install’.

(d)Yuanda Order/Variation Requisition 447CS-OR0012 dated 22 August 2019 which referenced VAR 021 and noted the reason for the order as: ‘Variation to contract–MPX Site Instruction to procure additional plant and works’.

(e)Invoices from:

(xi)      Waynes High Access dated 11 September 2019;

(xii)     Total Tools dated 23 September 2019;

(xiii)    Sergi Mobile Crane Solutions dated 30 September 2019;

(xiv)    Grimleys dated 1 and 7 August 2019; and

(xv)     Leader Access Hire dated 17 September 2019.

(f)Site Record 578 which referred to VAR 022 and was unsigned.

Yuanda’s submissions

  1. Yuanda submitted that the Payment Claim did not sufficiently identify the construction work relating to Invoice 1156 for the following reasons:

(a)Mr Nguon gave evidence that the Daily/Hourly Labour Records were incomplete and confusing in a number of respects and that no signed timesheets were provided in support of the claim.

(b)Ms Rozon gave evidence that Façade reduced this claim by $5,520 because the same work was also included in Invoice 1143.

  1. Yuanda further submitted that this Claim Item included excluded amounts for the following reasons:

(a)VAR 021 and 010, which were referred to in the invoice, did not relate to this invoice. VAR 021 expressly referred to Invoice 1121.

(b)The descriptions contained in the Order/Variation Requisitions were not consistent with the descriptions of the works contained in the invoice.

(c)VAR 010 and 021 were dated 15 and 22 August 2019 respectively. Many of the costs recorded in the supporting documents were charged before those dates and therefore the documents could not constitute a request or direction to complete such works.

Conclusion

  1. In my opinion, the Payment Claim has sufficiently identified the construction work referrable to Invoice 1156 for the following reasons:

(a)The work was described in the Payment Claim and the invoice as works performed in accordance with Order/Variation Requisitions VAR 010 and 021.

(b)The site records referenced VAR 022 and described the work as ‘Hire of Nifty Boom to install WL 14-15 Panels East Tower’.

(c)If Yuanda wanted to raise issues such as double counting or inconsistencies in the descriptions, it could have made such assertions in a payment schedule.

  1. For the same reasons, I am satisfied that the Payment Claim with respect to Invoice 1156 does not claim any excluded amount. This Claim Item is a claim for construction work or related goods and services, being the works referred to in VAR 010 and 021 which, as is apparent from the face of the supporting documents, is based on it being requested, directed or agreed by Yuanda.

  1. The evidence of the subjective understanding of Mr Nguon or Ms Rozon is not relevant or admissible for the purpose of determining whether the Payment Claim sufficiently identified the construction work or included a claim for an excluded amount.

Invoice 1157

  1. The Payment Claim relating to Invoice 1157 claimed $76,000 for the work described in the Variations Table.  It was supported by the following documents provided with the Payment Claim:

(a)       Invoice 1157 dated 24 September 2019 for $76,000 which described the work as:

447 CS - Supply of Labour & Materials for additional works required by Yuanda. Refer to Yuanda Variation 024.

(b)Daily/Hourly Labour Records which referenced Invoice 1157, NCR PO 3017/S00001 and described the work as ‘MPX & YUA Site Instruction – Installation of flashing’.

(c)Email of 9 September 2019 to Façade from Yuanda which stated:

Please find attached approved PO to proceed with the following FDI quotations,

•447CS-LLGS(A) - MPX-SI-000817 (L4-16 Lift lobby MPX defect rectifications)

•447CS-Flash(A) - L28/29 Plantroom weather seal flashings (YC-NCR)

•447CS-BP(A) - MPX-SI-000707 (L01H Back pan, covert vision into spandrel panels)

(d)Yuanda Order/Variation Requisition 447CS-OR0014 dated 4 September 2019 which referenced VAR 024 and noted the reason for the order as ‘MPX & YUANDA - Site Instruction-FDI Variation –Install Flashing’.

(e)Letter from Façade to Yuanda dated 3 September 2019 which attached ‘budget costing for defect rectification to loft lobby, Level 4 to 16 … as per Multiplex site instruction’ for $48,750 plus GST, together with supporting documents.

(f)Letter from Façade to Yuanda dated 3 September 2019 which attached ‘budget costing for supply and install of flashing for West Tower Level 28/29 … as per Yuanda specifications’ for $18,500 plus GST, together with supporting documents.

(g)Letter from Façade to Yuanda dated 3 September 2019 which attached ‘budget costing for supply and install of folded aluminium sheets to Level 01H … as per Multiplex site instruction’ for $8,750 plus GST, together with supporting documents.

Yuanda’s submissions

  1. Yuanda submitted that the Payment Claim did not sufficiently identify the construction work relating to Invoice 1157 for the following reasons:

(a)Mr Nguon gave evidence that the Daily/Hourly Labour Records were incomplete and that there was no breakdown of hours charged or the rates used to calculate the cost of each item.

(b)Ms Rozon said that there was double claiming and works included in this invoice were also included in Invoice 1151. Accordingly, Façade no longer intends to press for the amount of $15,570, which was also claimed in Invoice 1151.

  1. Yuanda further submitted that that this Claim Item included excluded amounts for the following reasons:

(a)There were no timesheets or site records supporting the Daily/Hourly Labour Records.

(b)      There were no documents showing that the work had been completed.

Conclusion

  1. In my opinion, the Payment Claim has sufficiently identified the construction work referrable to Invoice 1157 and I am satisfied that the Payment Claim does not include a claim for any excluded amount for substantially the same reasons as those applicable to Invoice 1156.

Invoice 1158

  1. The Payment Claim relating to Invoice 1158 claimed $51,680 for the work described in the Variations Table.  It was supported by the following documents provided with the Payment Claim:

(a)Invoice 1158 dated 24 September 2019 for $24,480 and $27,200 which described the work respectively as:

447 CS - Installation of 9 off Dorma's auto operator

447 CS - Installation of auto door sashes 10 off

(b)      Email of 23 August 2019 from Yuanda to Façade, which stated:

As per discussed (sic), please submit costing to install the following,

•  Dorma’s auto operators (9 off)

•  Install auto door sashes (10 off doors)

As advised, please submit asap for our PO approval submission.

Yuanda’s submissions

  1. Yuanda submitted that the Payment Claim did not sufficiently identify the construction work relating to Invoice 1158 because of Mr Nguon’s evidence that he was unable to assess the claim as it was not substantiated and he did not know how the amount claimed was calculated.

  1. Yuanda further submitted that this Claim Item included excluded amounts for the following reasons:

(a)The email of 23 August 2019 was only a request for a costing to be submitted and was not a request or direction to complete works.

(b)There was no reference to any contractual provision or why the work was additional to the scope of the works under the Contract. The claim was a claim for compensation for time-related costs.

(c)Mr Nguon gave evidence that the works claimed by Invoice 1158 had not been completed.

Conclusion

  1. In my opinion, the Payment Claim has sufficiently identified the construction work referrable to Invoice 1158, being the work in respect of which Yuanda requested Façade submit a costing in its email of 23 August 2019.

  1. I am satisfied that the Payment Claim does not include an excluded amount for the following reasons:

(a)The claim is for the construction work in respect of which Yuanda requested Façade submit a costing, presumably because it considered that the work was a variation that did not fall within the scope of the works.

(b)If the Payment Claim for the variation referred to in Invoice 1158 was not requested or directed or the work was not completed, then Yuanda would have been entitled to raise those defences in a payment schedule.

Invoice 1162

  1. The Payment Claim relating to Invoice 1162 claimed $64,154.37 for interest on previous late payments pursuant to s 12(2) of the Act.

  1. On its face, this is not a claim for interest arising out of or under the Contract. It is therefore a claim for an excluded amount within the meaning of s 10B(2)(d).

_____