Ausipile Pty Ltd v Bothar Boring and Tunnelling (Australia) Pty Ltd

Link copied
Case Copied 49 min read

SUPREME COURT OF QUEENSLAND

CITATION:

Ausipile Pty Ltd v Bothar Boring and Tunnelling (Australia) Pty Ltd [2021] QCA 223

PARTIES:

AUSIPILE PTY LTD
ACN 101 402 322
(appellant)
v
BOTHAR BORING AND TUNNELLING (AUSTRALIA) PTY LTD

ACN 622 309 264
(respondent)

FILE NO/S:

Appeal No 3642 of 2021
SC No 8953 of 2019

DIVISION:

Court of Appeal

PROCEEDING:

General Civil Appeal

ORIGINATING COURT:


Supreme Court at Brisbane – [2021] QSC 39 (Wilson J)

DELIVERED ON:

15 October 2021

DELIVERED AT:

Brisbane

HEARING DATE:

19 August 2021

JUDGES:

Fraser and Morrison JJA and North J

ORDERS:

1.   Appeal allowed.

2.   Set aside the orders made on 5 March 2021.

3. Pursuant to s 78(2)(a) of the Building Industry Fairness (Security of Payment) Act 2017 (Qld) judgment be entered for the appellant against the respondent in the amount of $761,296.75.

4.   The parties have leave to make such submissions as they are advised on the question of interest as follows:

a.   by the appellant, within 14 days of the publication of these reasons;

b.   by the respondent, within 14 days thereafter; and

c.   in each case, limited to four pages.

5.    The respondent pay the appellant’s costs of and incidental to the appeal, and the costs of proceeding BS 8953 of 2019.

CATCHWORDS:

CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – REMUNERATION – STATUTORY REGULATION OF ENTITLEMENT TO AND RECOVERY OF PROGRESS PAYMENTS – PAYMENT CLAIMS – where the appellant and respondent entered a subcontract agreement to design and construct a secant pile launch shaft – where the respondent hired a crawler crane from the appellant to complete works under the head contract – where the appellant applied for judgment pursuant to s 78(2)(a) of the Building Industry Fairness (Security of Payment) Act 2017 (Qld) to recover amounts owing under a payment claim but the application was dismissed – whether the variation in relation to the hire of the crawler crane related to a contract other than the subcontract – whether the payment claim contained claims in relation to two contracts – whether the payment claim was void for the purpose of the Building Industry Fairness (Security of Payment) Act 2017 (Qld)

CONSUMER PROTECTION – MISLEADING OR DECEPTIVE CONDUCT OR FALSE REPRESENTATIONS – CHARACTER OR ATTRIBUTES OF CONDUCT OR REPRESENTATION – SILENCE AND NON-DISCLOSURE – where the respondent sent the appellant a letter stating that it would withhold further payment claims “as discussed” – where the appellant did not respond to the letter – whether the appellant’s silence was misleading or deceptive or likely to mislead or deceive

Building Industry Fairness (Security of Payment) Act 2017 (Qld), s 67, s 68, s 69, s 70, s 75, s 76, s 77, s 78, s 100

Acciona Infrastructure Australia Pty Ltd v Holcim (Australia) Pty Ltd [2020] NSWSC 1330, considered
Alcan (NT) Alumina Pty Ltd v Commissioner of Territory Revenue (2009) 239 CLR 27; [2009] HCA 41, applied
Class Electrical Services Pty Ltd v Go Electrical Pty Ltd [2013] NSWSC…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Ausipile Pty Ltd v Bothar Boring and Tunnelling (Australia)... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2021] QCA 223
Decision Date

CaseChat Overview and Summary

Ausipile Pty Ltd appealed against a decision dismissing its application for judgment under s 78(2)(a) of the Building Industry Fairness (Security of Payment) Act 2017 (Qld). Ausipile and Bothar Boring and Tunnelling (Australia) Pty Ltd entered a subcontract agreement for Ausipile to design and construct a secant pile launch shaft. Ausipile hired a crawler crane from Bothar for use under the head contract. Ausipile submitted a payment claim, which included a claim for a variation in relation to the hire of the crawler crane. Bothar argued that the variation related to a contract other than the subcontract, and that the payment claim contained claims in relation to two contracts, and was void for the purpose of the Act. The primary judge dismissed Ausipile’s application for judgment. Ausipile appealed to the Supreme Court of Appeal.

The appeal raised issues about the nature of the agreement between Ausipile and Bothar for the hire of the crawler crane. The court considered the terms of the subcontract and the circumstances surrounding the hire of the crawler crane. The court examined the context in which the exchange concerning the hire of the crawler crane occurred, and considered the presumed intention of the contracting parties. The court concluded that the hire of the crawler crane was a variation under the subcontract, and that the payment claim did not contain claims in relation to two contracts. The court held that the payment claim was not void for the purpose of the Act.

The court allowed the appeal, set aside the orders made on 5 March 2021, and entered judgment for Ausipile against Bothar in the amount of $761,296.75. The parties were granted leave to make submissions on the question of interest. Bothar was ordered to pay Ausipile’s costs of and incidental to the appeal, and the costs of proceeding BS 8953 of 2019.

Orders

Orders of the court

1. Appeal allowed.

2. Set aside the orders made on 5 March 2021.

3. Pursuant to s 78(2)(a) of the Building Industry Fairness (Security of Payment) Act 2017 (Qld) judgment be entered for the appellant against the respondent in the amount of $761,296.75.

4. The parties have leave to make such submissions as they are advised on the question of interest as follows:

a. by the appellant, within 14 days of the publication of these reasons;

b. by the respondent, within 14 days thereafter; and

c. in each case, limited to four pages.

5. The respondent pay the appellant’s costs of and incidental to the appeal, and the costs of proceeding BS 8953 of 2019.

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established

Mr O’Connor agreed that the price for the hire of the crane and operator had been agreed before Bothar’s use of the crane commenced.[5] The following exchange occurred in cross-examination:[6]“No. Okay. Now, at the time that Bothar asked to hire the crawler crane and Ausipile agreed to that, there was no formal subcontract provided?---For the hire of the crane?Yes?---No.No indication that it would be a separate contract?---No.No indication that it would be subject to terms different from those in the subcontract?---No.No indication that it would be a different subcontractor at all?---There was no different subcontract.And because there was no different subcontract, … Bothar didn’t complain when it got payment claim 6 and saw that the claim for a variation for the crawler crane was included?---No.”[5]AB 596 lines 33-37.[6]AB 598 lines 4-19.Consideration – crawler crane hire a variation? Bothar’s contention was that the crane hire was a separate contract, quite distinct from the subcontract between Bothar and Ausipile. For that reason it argued that payment claim 6 was not a valid payment claim because it related to two different contracts. In determining the nature of the agreement made between Ausipile and Bothar in respect of the crawler crane, the court seeks to determine in an objective way the presumed intention of the contracting parties. The court examines all the relevant indicia, including the communications and the context in which they occurred. The context in which the exchange concerning the hire of the crawler crane can be summarised as follows. Ausipile and Bothar were commercial contracting parties in the construction industry. On 14 November 2018 they entered into a formalised subcontract agreement.[7] That subcontract contained detailed provisions governing matters relevant to the relationship between the two parties, including:[7]AB 150.(a)a stipulation as to when payment claims would be made, and paid; payment claims had to be submitted on the twenty-second day of the month to which the claim related, to be paid within 30 days;[8][8]AB 151.(b)insurance was specified in respect of workers compensation, public liability, professional indemnity and subcontractors’ plant and machinery;[9] for subcontractors’ plant and machinery the limit of cover was $9,785,000 under an identified policy with an expiry date of 8 July 2019;[9]AB 152.(c)all other expiry dates for insurance were 8 July or 30 September 2019;(d)Ausipile was responsible for the provision of piling rig, plant and specialist crew for the drilling work;[10](e)by clause 1.1, Ausipile’s work was to be carried out in accordance with the provisions of the subcontract agreement, and the provisions of Bothar’s head contract, to the extent they were relevant to the performance of the subcontract work and were incorporated by reference;[11](f)by clause 3.1, Ausipile was required to vary the work as required by Bothar, but would not be entitled to claim extra payment for any variation not authorised in writing;[12] clause 5.2 obliged Ausipile to ensure that the persons engaged by it were to be “careful, skilled and experienced in their respective trades and calling”;[13](g)clause 6 obliged Ausipile and its employees and subcontractors to be familiar with and comply with all rules and regulations in force at the worksite, and Ausipile had to provide equipment required in accordance with those rules and regulation;[14](h)clause 7 obliged Bothar to make payment in accordance with the terms of the subcontract, and required Ausipile to provide Bothar with evidence that wages owing to employees engaged in the work had been paid, and that all statutory and insurance obligations had been met;[15](i)clause 8.1 contained an indemnity by Ausipile in favour of Bothar, against all losses, liabilities, claims and expenses which might arise from the death of or injury to any person, and the loss or damage to the property of any person, arising out of or in connection with the performance of the work;[16](j)under clause 8.3, Ausipile had to maintain employer’s indemnity and workers compensation insurance covering liability, including common law liability, to employees of Ausipile, as well as public liability insurance covering liability to any third party for death, bodily injury, loss of or damage to property arising out of any act or omission in the performance of the work;[17](k)clause 8.3(d) obliged Ausipile, at its own cost, to insure its plant and equipment;[18](l)clause 8.7 contained a separate indemnity from Ausipile to Bothar in respect of liability, loss or expense arising out of a failure on Ausipile’s part to comply with its obligations under clause 8.[19][10]AB 160.[11]AB 154.[12]AB 154.[13]AB 155.[14]AB 156.[15]AB 156.[16]AB 156.[17]AB 156-157.[18]AB 157.[19]AB 157.