Medium Neutral Citation: Rail Corporation of NSW v Nebax Constructions [2012] NSWSC 6 Hearing dates: 03/01/2012 Decision date: 03 January 2012 Jurisdiction: Equity Division Before: McDougall J Decision: Continue interlocutory orders. Stand over for final orders.
Catchwords: ADMINISTRATIVE LAW - Building and Construction Industry Security of Payment Act 1999 (NSW) - questions of administrative law - where adjudicator materially denied parties natural justice by determining his jurisdiction in a way for which neither party had contended and without giving them the opportunity to be heard - whether adjudicator's determination void.
BUILDING AND CONSTRUCTION - Building and Construction Industry Security of Payment Act 1999 (NSW) - whether s 7(1) authorizes more than one adjudication application to be made at the one time for the one payment claim.Legislation Cited: Building and Construction Industry Security of Payment Act 1999 (NSW)
Civil Procedure Act 2005 (NSW)Cases Cited: Alan Connolly & Co v Commercial Indemnity [2005] NSWSC 339
Brodyn Pty Ltd v Davenport (2004) 61 NSWLR 421
Chase Oyster Bar v Hamo Industries [2010] NSWCA 1990
Dualcorp Pty Ltd v Remo Constructions Pty Ltd (2009) 74 NSWLR 190
Olympia Group (NSW) Pty Ltd v Hansen Yuncken Pty Ltd [2011] NSWSC 165
Watpac Constructions (NSW) Pty Ltd v Austin Corp Pty Ltd [2010] NSWSC 168Category: Procedural and other rulings Parties: Rail Corporation New South Wales (ABN 59 325 778 353) (Plaintiff)
Nebax Constructions Australia Pty Limited trading as TrackSyde Constructions (ACN 101 054 068) (First Defendant)
Adjudicate Today Pty Limited (ABN 3910 9605 021) (Second Defendant)
Callum Campbell (Third Defendant)Representation: Counsel:
N J Kidd (Plaintiff)
A W Smith (First Defendant)
Solicitors:
Maddocks (Plaintiff)
Warren McKeon Dickson (First Defendant)
File Number(s): 2011/410319
Judgment - EX TEMPORE
HIS HONOUR: The plaintiff (RailCorp) and the first defendant (Nebax) are parties to a contract made on about 15 December 2009 (the contract). That contract is a construction contract for the purposes of the Building and Construction Industry Security of Payment Act 1999 (NSW) (the Act). Under the contract, Nebax was required to undertake platform resurfacing work at some 25 separately identified railway stations under the control of RailCorp.
A disputed progress claim
On 31 October 2011, Nebax made what it described as "Progress claim No 18" by email addressed to the relevant officer of RailCorp. That email read, so far as it is relevant:
"Please find attached invoices in relation to progress claim No 18 in the platform resurfacing programme 2009-10. The above claims are for the month of September 2011 ...".
There were sent with the email some five invoices, four of which remain in issue, and various other required documents. RailCorp served a payment schedule in respect of each of those invoices. Presumably it took that course because each individual invoice stated that that it was "a payment claim made under the [Act]". In some cases, the payment schedule provided for a scheduled amount of nil. In other cases, the payment schedule indicated a scheduled amount of less than…
Keep reading for free
Create a free CaseChat account to read Rail Corporation of NSW v Nebax Constructions and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2012] NSWSC 6
- Decision Date
CaseChat Overview and Summary
The legal issues before the court included whether the adjudicator had materially denied the parties natural justice by determining his jurisdiction in a manner not argued by either party and without providing them a chance to be heard. Furthermore, the court had to consider whether section 7(1) of the Act allows for more than one adjudication application to be made concurrently for the same payment claim. This involved a detailed examination of the statutory language and the principles of administrative law, particularly the requirement of procedural fairness.
The court found that the adjudicator's determination of his jurisdiction was indeed flawed as it did not align with the submissions made by the parties, and they were not given an opportunity to address this new jurisdictional issue. This procedural defect was considered a material denial of natural justice, leading to the conclusion that the adjudicator's determination was void. The court also clarified that section 7(1) of the Act does not permit more than one adjudication application for the same payment claim at the same time, as such a procedure would undermine the purpose of the security of payment scheme.
The final orders of the court included declaring the adjudicator's determination void due to the procedural unfairness and affirming that only one adjudication application can be made at a time for the same payment claim under the Act. This decision underscores the importance of adhering to procedural fairness and statutory interpretation in adjudication processes within the building and construction industry.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi