| IN THE SUPREME COURT OF VICTORIA | Not Restricted |
AT MELBOURNE
COMMERCIAL AND EQUITY DIVISION
TECHNOLOGY, ENGINEERING AND CONSTRUCTION LIST
No. 04080 of 2013
| JOTHAM PROPERTY HOLDINGS PTY LTD | Plaintiff |
| v | |
| COOPERATIVE BUILDERS PTY LTD | First Named Defendant |
| and | |
| DAMIAN MICHAEL | Second Named Defendant |
| and | |
| ADJUDICATE TODAY PTY LTD | Third Named Defendant |
---
JUDGE: | VICKERY J | |
WHERE HELD: | MELBOURNE | |
DATE OF HEARING: | 14 OCTOBER 2013 | |
DATE OF JUDGMENT: | 17 OCTOBER 2013 | |
CASE MAY BE CITED AS: | JOTHAM PROPERTY HOLDINGS PTY LTD v COOPERATIVE BUILDERS PTY LTD & ORS | |
MEDIUM NEUTRAL CITATION: | [2013] VSC 552 | |
---
BUILDING CONTRACTS - Building and Construction Industry Security of Payment Act 2002 (Vic) - Application for judicial review of a determination of an adjudicator – Application for writ of certiorari to quash a decision of an adjudicator – Jurisdictional error – Whether a payment claim can be served multiple times - Application of s 14(8) and s 14(9) of the Building and Construction Industry Security of Payment Act2002 (Vic) - Whether “single” or “one off” payment claim – Application of s 14(5) and s 9(2)(c) of the Building and Construction Industry Security of Payment Act 2002 (Vic) – Whether payment claim made in time s 18 of the Building and Construction Industry Security of Payment Act2002 (Vic).
---
APPEARANCES: | Counsel | Solicitors |
| For the Plaintiff | Mr J.A. Twigg | Millens Lawyers |
| For the First Named Defendant | Mr P.H. Caillard | Rockwell Oliver |
| For the Second Named Defendant | No Appearance | |
| For the Third Named Defendant | No Appearance |
HIS HONOUR:
Introduction
The Plaintiff, Jotham Property Holdings Pty Ltd (“Jotham”), contends that an adjudication (the “Adjudication” or the “Adjudication Determination”) made under the Building and Construction Industry Security of Payment Act 2002 (Vic) (the “Act”) is invalid. The Act creates a statutory mechanism that compliments the provisions of construction contracts, which is intended to put builders and subcontractors in a position where they can promptly secure payment of progress claims.[1]
On 9 September 2011 Jotham, as principal, and the First Defendant, Cooperative Builders Pty Ltd (“Cooperative”) as the main contractor, entered into 14 separate HIA building contracts (the “Construction Contracts”). Pursuant to the Construction Contracts Cooperative was to construct 14 double storey residential townhouse dwellings at 57 Grey Street, Bacchus Marsh, Victoria (the “Property”). Each contract was accompanied by separate drawings for each unit, but were otherwise in common form.
Works were performed by Cooperative from September to November 2012 and progress claims were submitted.
Cooperative served Jotham with three payment claims which were made under the Act (the “Three Original Payment Claims”):
(a)the first, dated 27 September 2012, for the sum of $43,447.25 with respect to the “lock up” stage for unit 2;
(b)the second, dated 5 October 2012, for the sum of $43,447.25 with respect to the “lock up” stage for unit 3; and
(c)the third, dated 2 October 2012, for the sum of $18,620.25 with respect to the “frame” stage for…
Keep reading for free
Create a free CaseChat account to read Jotham Property Holdings Pty Ltd v Cooperative Builders Pty... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2013] VSC 552
- Decision Date
CaseChat Overview and Summary
The court was required to decide several legal issues, including whether the adjudicator's decision contained a jurisdictional error by allowing a payment claim to be served multiple times, and whether the payment claim was a "single" or "one off" claim as required by the Act. The court also needed to determine whether the payment claim was made within the statutory timeframe.
The court found that the adjudicator had erred in law by allowing the subcontractor to serve multiple payment claims. The court held that the statutory provisions required a single payment claim to be made and that the adjudicator's decision to allow multiple claims was outside the scope of their jurisdiction. The court also found that the payment claim was not made within the statutory timeframe, and therefore, the adjudicator's decision was flawed. The court granted the application for judicial review and quashed the adjudicator's decision.
As a result of the court's decision, the adjudicator's determination was set aside, and the matter was remitted back to the adjudicator for reconsideration in accordance with the court's findings. The court did not make any orders for costs.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi