Jotham Property Holdings Pty Ltd v Cooperative Builders Pty Ltd & Ors

Link copied
Case Copied 23 min read
IN THE SUPREME COURT OF VICTORIA Not Restricted

AT MELBOURNE

COMMERCIAL AND EQUITY DIVISION

TECHNOLOGY, ENGINEERING AND CONSTRUCTION LIST

No. 04080 of 2013

JOTHAM PROPERTY HOLDINGS PTY LTD Plaintiff
v
COOPERATIVE BUILDERS PTY LTD First Named Defendant
and
DAMIAN MICHAEL Second Named Defendant
and
ADJUDICATE TODAY PTY LTD Third Named Defendant

---

JUDGE:

VICKERY J

WHERE HELD:

MELBOURNE

DATE OF HEARING:

14 OCTOBER 2013

DATE OF JUDGMENT:

17 OCTOBER 2013

CASE MAY BE CITED AS:

JOTHAM PROPERTY HOLDINGS PTY LTD v COOPERATIVE BUILDERS PTY LTD & ORS

MEDIUM NEUTRAL CITATION:

[2013] VSC 552

---

BUILDING CONTRACTS - Building and Construction Industry Security of Payment Act 2002 (Vic) - Application for judicial review of a determination of an adjudicator – Application for writ of certiorari to quash a decision of an adjudicator – Jurisdictional error – Whether a payment claim can be served multiple times - Application of s 14(8) and s 14(9) of the Building and Construction Industry Security of Payment Act2002 (Vic) - Whether “single” or “one off” payment claim – Application of s 14(5) and s 9(2)(c) of the Building and Construction Industry Security of Payment Act 2002 (Vic) – Whether payment claim made in time s 18 of the Building and Construction Industry Security of Payment Act2002 (Vic).

---

APPEARANCES:

Counsel Solicitors
For the Plaintiff Mr J.A. Twigg Millens Lawyers
For the First Named Defendant Mr P.H. Caillard Rockwell Oliver
For the Second Named Defendant No Appearance
For the Third Named Defendant No Appearance

HIS HONOUR:

Introduction

  1. The Plaintiff, Jotham Property Holdings Pty Ltd (“Jotham”), contends that an adjudication (the “Adjudication” or the “Adjudication Determination”) made under the Building and Construction Industry Security of Payment Act 2002 (Vic) (the “Act”) is invalid. The Act creates a statutory mechanism that compliments the provisions of construction contracts, which is intended to put builders and subcontractors in a position where they can promptly secure payment of progress claims.[1]

  1. On 9 September 2011 Jotham, as principal, and the First Defendant, Cooperative Builders Pty Ltd (“Cooperative”) as the main contractor, entered into 14 separate HIA building contracts (the “Construction Contracts”).  Pursuant to the Construction Contracts Cooperative was to construct 14 double storey residential townhouse dwellings at 57 Grey Street, Bacchus Marsh, Victoria (the “Property”).  Each contract was accompanied by separate drawings for each unit, but were otherwise in common form.

  1. Works were performed by Cooperative from September to November 2012 and progress claims were submitted. 

  1. Cooperative served Jotham with three payment claims which were made under the Act (the “Three Original Payment Claims”):

(a)the first, dated 27 September 2012, for the sum of $43,447.25 with respect to the “lock up” stage for unit 2;

(b)the second, dated 5 October 2012, for the sum of $43,447.25 with respect to the “lock up” stage for unit 3;  and

(c)the third, dated 2 October 2012, for the sum of $18,620.25 with respect to the “frame” stage for…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Jotham Property Holdings Pty Ltd v Cooperative Builders Pty... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2013] VSC 552
Decision Date

CaseChat Overview and Summary

The case of Jotham Property Holdings Pty Ltd v Cooperative Builders Pty Ltd & Ors involved a dispute between Jotham, the head contractor, and Cooperative Builders, a subcontractor. The matter was before the court as an application for judicial review of an adjudicator's determination and a writ of certiorari to quash the decision. The dispute centred around whether a payment claim could be served multiple times under the Building and Construction Industry Security of Payment Act 2002 (Vic), and if the payment claim was made within the statutory timeframe.

The court was required to decide several legal issues, including whether the adjudicator's decision contained a jurisdictional error by allowing a payment claim to be served multiple times, and whether the payment claim was a "single" or "one off" claim as required by the Act. The court also needed to determine whether the payment claim was made within the statutory timeframe.

The court found that the adjudicator had erred in law by allowing the subcontractor to serve multiple payment claims. The court held that the statutory provisions required a single payment claim to be made and that the adjudicator's decision to allow multiple claims was outside the scope of their jurisdiction. The court also found that the payment claim was not made within the statutory timeframe, and therefore, the adjudicator's decision was flawed. The court granted the application for judicial review and quashed the adjudicator's decision.

As a result of the court's decision, the adjudicator's determination was set aside, and the matter was remitted back to the adjudicator for reconsideration in accordance with the court's findings. The court did not make any orders for costs.