| IN THE SUPREME COURT OF VICTORIA | Not Restricted | |
AT MELBOURNE
BUILDING CASES LIST
No. 5645 of 2009
| HICKORY DEVELOPMENTS PTY LTD (ACN 091 236 912) | Plaintiff |
| v | |
| SCHIAVELLO (VIC) PTY LTD (ACN 006 778 641) | First Defendant |
| and | |
| ADJUDICATE TODAY (ACN 109 605 021) | Second Defendant |
---
JUDGE: | VICKERY J | |
WHERE HELD: | MELBOURNE | |
DATES OF HEARING: | 15-16 APRIL 2009 | |
DATE OF JUDGMENT: | 24 APRIL 2009 | |
CASE MAY BE CITED AS: | HICKORY DEVELOPMENTS PTY LTD v SCHIAVELLO (VIC) PTY LTD AND ANOR | |
MEDIUM NEUTRAL CITATION: | [2009] VSC 156 | |
---
BUILDING AND CONSTRUCTION – Building and Construction Industry Security of Payment Act 2002 (Vic) – object and purpose of the Act - payment claim - whether application lodged within time with the nominating authority in accordance with s.18 of the Act - whether payment claim in accordance with s.14 of the Act - Brodyn Pty Ltd v Davenport [2004] NSWCA 394 not followed in part, applied in part – whether alleged deficiencies in procedure essential pre-conditions to jurisdiction - whether matters for the adjudicator to decide -whether adjudicator’s determination void.
ADMINISTRATIVE LAW– Application of the Hickman principle to privative clause - s.85 Constitution Act1975 (Vic) - certiorari available under the Act in Victoria.
PRACTICE AND PROCEDURE – Electronic service of documents – operation of email – when documents received.
---
APPEARANCES: | Counsel | Solicitors |
| For the Plaintiff | Mr JR Dixon SC and Mr JAF Twigg | Giannakopoulos Solicitors |
| For the Defendants | Mr JJ Gleeson SC and | Holding Redlich |
HIS HONOUR:
Introduction
The issue in this case is whether a determination arising from a purported adjudication under the Building and Construction Industry Security of Payment Act 2002 (Vic) (“the Act”) is valid. The answer turns on whether the application for adjudication was made within the time required by the Act and whether the application in substance was in accordance with the Act and, if not, whether the shortcoming renders the adjudication determination void.
The Act has had a substantial effect in shifting the power balance between principals and subcontractors in construction contracts in Victoria and in other States and Territories where legislation in similar terms and with the same objects has been enacted.[1] Subcontractors are now in a position to promptly secure payments of progress claims with the aid of a statutory mechanism which compliments the provisions of the construction contract. Outstanding claims of the principal under the contract, arising for example from poor workmanship or delay, are preserved as future enforceable claims, but cannot stand in the way of prompt payment of a progress claim found to be due under the expeditious process provided for in the Act.
[1] Building and Construction Industry Security of Payment Act 1999 (NSW); Construction Contracts Act 2004 (WA); Construction Contracts (Security of Payments) Act (NT); and Building and Construction IndustryPayments Act 2004(Qld).
FKP Lifestyle Pty Ltd as principal, engaged the plaintiff, Hickory Developments Pty Ltd (ACN 091 236 912) (“Hickory”), as the main contractor to design and construct the base building works…
Keep reading for free
Create a free CaseChat account to read Hickory Developments Pty Ltd v Schiavello (Vic) Pty Ltd & An... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2009] VSC 156
- Decision Date
CaseChat Overview and Summary
The legal issues before the court were whether Hickory's application for adjudication was lodged within the time prescribed by section 18 of the Act, whether the payment claim was in accordance with section 14 of the Act, and whether the alleged procedural deficiencies were essential pre-conditions to the court's jurisdiction. The court also considered whether certain matters were for the adjudicator to decide and whether the adjudicator's determination was void. The court applied the Brodyn Pty Ltd v Davenport [2004] NSWCA 394 case, finding it instructive but not binding, and considered the application of the Hickman principle to the privative clause in section 85 of the Constitution Act 1975 (Vic), concluding that certiorari was available under the Act in Victoria.
In its reasoning, the court found that Hickory's application for adjudication was indeed lodged within the time prescribed by section 18 of the Act, and the payment claim was in accordance with section 14 of the Act. The court held that the alleged procedural deficiencies were not essential pre-conditions to its jurisdiction and that certain matters were indeed for the adjudicator to decide. Consequently, the court determined that the adjudicator's determination was not void. The court applied the Brodyn case in part, distinguishing it from the present case on certain points, and found that the privative clause in section 85 of the Constitution Act 1975 (Vic) did not preclude judicial review in this context.
The final orders of the court were that Hickory's application for adjudication was deemed to be within the prescribed timeframe, and the payment claim was considered to be in accordance with the statutory requirements. The court held that the alleged procedural deficiencies did not affect its jurisdiction, and matters for the adjudicator to decide were not grounds for nullifying the adjudicator's determination. The court also found that the adjudicator's determination was valid and enforceable, and the case was remitted to the adjudicator for further consideration of the merits of the dispute.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.