CITATION: Leighton Contractors Pty Limited v Campbelltown Catholic Club Limited, Campbelltown Catholic Club Limited v Leighton Contractors Pty Limited [2003] NSWSC 1103 HEARING DATE(S): 27/11/03, 28/11/03 JUDGMENT DATE:
3 December 2003JURISDICTION:
Equity Division
Technology and Construction ListJUDGMENT OF: Einstein J DECISION: Summary judgment to be entered for Leighton Contractors Pty Limited. CATCHWORDS: Contract - building and construction - Building and Construction Industry Security of Payment Act 1999 (NSW) - Consideration of interrelationship of sundry provisions and analysis of principal's claimed entitlement to commence separate proceedings and/or to avoid summary judgment by invoking discretionary considerations - Progress claim submitted to Superintendent on same date as document purporting to be payment claim under the Act submitted to principal - Principal fails to serve payment schedule complying with sections 14(1) and (2) - Contractor commences proceedings and seeks summary judgment - Principal commences separate proceedings and seeks declaration that it does not owe any amount to contractor in respect of specific progress claim in excess of the amount specified in progress certificate issued by Superintendent and order that principal pay to the contractor such sum as it might recover against principal in the first proceedings - second proceedings held to be an abuse of process - Principal in first proceedings contends (as defendant) - That alleged payment claim was not a valid payment claim within s.13(2) of the Act because: (i) it did not identify construction work (or related goods and services) as required by s.13(2)(a) - (ii) there was no progress payment claimed as required by s.13(2)(b) - (iii) it did not bear the endorsement required by s. 13(2) (c) - - That contractor was and is not a person entitled or who claims to be entitled to a progress payment within s. 13(1) because: (i) it was not a person entitled to a progress payment under s. 8(1) - (ii) as at the date of the Alleged Payment Claim there was no reference date as and from which contractor was entitled to a progress payment within s. 8(1) and (2) - (iii) there was no amount calculated in accordance with the terms of the Contract which constituted a progress payment to which contractor was entitled under s. 9(a) - (iv) as at the date of the Alleged Payment Claim there was no progress payment under the Contract which had become due and payable within the meaning of s. 11(1) - - That Alleged Payment Claim was not a valid payment claim (in whole or in part) under s. 13 of the Act: (i) to the extent that it claimed for rock excavation, because it was not served within 12 months after such work was last carried out as required by s. 13(4)(b) - (ii) to the extent that it claimed for Delay Costs, because such claim was not permitted by the Act, the Delay Costs not being construction work to which the progress payment claimed by contractor related. - Alternatively, that if the Alleged Payment Claim were a valid…
Keep reading for free
Create a free CaseChat account to read Leighton Contractors Pty Ltd v Campbelltown Catholic Club Lt... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Details
- Case
- [2003] NSWSC 1103
- Decision Date
CaseChat Overview and Summary
The case of Leighton Contractors Pty Ltd v Campbelltown Catholic Club Ltd involved a dispute over a building contract governed by the Building and Construction Industry Security of Payment Act 1999 (NSW). The primary issue was whether a document submitted by the contractor, Leighton, constituted a valid payment claim under the Act, and if so, whether the principal, Campbelltown Catholic Club Ltd, was liable to pay the amount claimed. Additionally, the court had to determine if the principal's attempt to commence separate proceedings was an abuse of process.
The court examined the statutory requirements for a valid payment claim under the Act. It found that the document in question did not meet the criteria specified in section 13(2) of the Act as it did not properly identify the construction work or related goods and services, did not claim a progress payment, and lacked the necessary endorsement. The court also noted that the principal had not issued a payment schedule within the required timeframe, which further complicated the principal's position. The principal's attempt to commence separate proceedings was deemed an abuse of process, as it sought to avoid the consequences of the contractor's valid claim and the principal's failure to comply with the Act.
Given these findings, the court ruled in favour of the contractor, Leighton Contractors, and granted summary judgment in its favour. The court held that the principal was liable to pay the amount claimed by Leighton, as the principal had failed to serve a payment schedule within the required period, and the document submitted by Leighton constituted a valid payment claim under the Act. The principal's separate proceedings were dismissed as an abuse of process.
The final orders of the court were that the principal, Campbelltown Catholic Club Ltd, was liable to pay Leighton Contractors the amount claimed, and the separate proceedings were dismissed with costs. The court's decision reinforced the importance of adhering to the statutory requirements for payment claims under the Building and Construction Industry Security of Payment Act 1999 (NSW) and highlighted the consequences of failing to do so.
The court examined the statutory requirements for a valid payment claim under the Act. It found that the document in question did not meet the criteria specified in section 13(2) of the Act as it did not properly identify the construction work or related goods and services, did not claim a progress payment, and lacked the necessary endorsement. The court also noted that the principal had not issued a payment schedule within the required timeframe, which further complicated the principal's position. The principal's attempt to commence separate proceedings was deemed an abuse of process, as it sought to avoid the consequences of the contractor's valid claim and the principal's failure to comply with the Act.
Given these findings, the court ruled in favour of the contractor, Leighton Contractors, and granted summary judgment in its favour. The court held that the principal was liable to pay the amount claimed by Leighton, as the principal had failed to serve a payment schedule within the required period, and the document submitted by Leighton constituted a valid payment claim under the Act. The principal's separate proceedings were dismissed as an abuse of process.
The final orders of the court were that the principal, Campbelltown Catholic Club Ltd, was liable to pay Leighton Contractors the amount claimed, and the separate proceedings were dismissed with costs. The court's decision reinforced the importance of adhering to the statutory requirements for payment claims under the Building and Construction Industry Security of Payment Act 1999 (NSW) and highlighted the consequences of failing to do so.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi