NEW SOUTH WALES COURT OF APPEAL
CITATION: Fyntray Constructions Pty Ltd v Macind Drainage & Hydraulic Services Pty Ltd [2002] NSWCA 238
FILE NUMBER(S):
41077/01
HEARING DATE(S): 20 June 2002
JUDGMENT DATE: 26/07/2002
PARTIES:
Fyntray Constructions Pty Ltd (Claimant)
Macind Drainage & Hydraulic Services Pty Ltd (Opponent)
JUDGMENT OF: Heydon JA Hodgson JA Ipp AJA
LOWER COURT JURISDICTION: District Court
LOWER COURT FILE NUMBER(S): DC 7013/01
LOWER COURT JUDICIAL OFFICER: Gibson DCJ
COUNSEL:
Mr G J McVay (Claimant)
Mr G O Blake (Opponent)
SOLICITORS:
James A Moustacas & Co (Claimant)
Toomey Pegg Drevikovsky (Opponent)
CATCHWORDS:
LEGISLATION CITED:
Building and Construction Industry Security of Payment Act 1999
Interpretation Act 1987
DECISION:
The Summons is dismissed; the claimant is to pay the opponent's costs.
JUDGMENT:
IN THE SUPREME COURT
OF NEW SOUTH WALES
COURT OF APPEAL
CA 41077/01
DC 7013/01
HEYDON JA
HODGSON JA
IPP AJA26 July 2002
FYNTRAY CONSTRUCTIONS PTY LTD v
MACIND DRAINAGE & HYDRAULIC SERVICES PTY LTD
Held (Heydon JA, Hodgson JA and Ipp AJA agreeing), refusing leave to appeal:
On the true construction of the Building and Construction Security of Payment Act 1999 (NSW) it is permissible for a person entitled to a progress payment under a construction contract to serve a payment claim on the person who under the contract is liable to make the payment even though the claim relates to work done in periods prior to the month in which the payment claim is served. Hence the defendant’s claim was not invalid: [53].
O R D E R S
The Summons is dismissed.
The claimant is to pay the opponent’s costs.
IN THE SUPREME COURT
OF NEW SOUTH WALES
COURT OF APPEAL
CA 41077/01
DC 7013/01HEYDON JA
HODGSON JA
IPP AJA26 July 2002
FYNTRAY CONSTRUCTIONS PTY LTD v
MACIND DRAINAGE & HYDRAULIC SERVICES PTY LTD
Judgment
HEYDON JA: This is an application for leave to appeal against orders made by Gibson DCJ on 14 December 2001. She gave judgment for the plaintiff in the sum of $77,376.05 and ordered the defendant to pay the plaintiff’s costs. The court has ordered that the leave application be heard concurrently with the appeal, to the intent that if leave is granted no further hearing need take place. The oral argument was presented by counsel on both sides with great capacity – a capacity not matched by those in the defendant’s camp responsible for compiling the White Book, which was in a quite unsatisfactory condition: see MacDonald v Martin [2002] NSWCA 178 at [38].
The grounds of appeal
The grounds of appeal set out in the defendant’s proposed Amended Notice of Appeal fall into three groups. First, it is said that the trial judge erred in her construction of the Building and Construction Industry Security of Payment Act 1999. It may be accepted at the outset that, as the defendant submitted, the points raised have not been determined before, or even raised before, and are important in view of the widespread use of the legislation…
Keep reading for free
Create a free CaseChat account to read Fyntray Constructions Pty Ltd v Macind Drainage & Hydraulic... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2002] NSWCA 238
- Decision Date
CaseChat Overview and Summary
The court was required to determine whether the plaintiff's payment claim was valid under the *Building and Construction Industry Security of Payment Act 1999*, particularly in relation to the timing of the work covered by the claim relative to its service. Additionally, the court considered whether the trial judge erred in refusing to grant a stay of proceedings and whether her reasons for judgment were adequate. The defendant also raised arguments concerning the plaintiff's contractual entitlement to payment and the defendant's own cross-claim.
The court held that the *Building and Construction Industry Security of Payment Act 1999* permits a payment claim to include work done in periods prior to the month in which the claim is served, meaning the defendant's payment claim was not invalid on this ground. The court found that the defendant's arguments were highly technical and could have been raised against earlier, already paid, progress claims. Furthermore, the defendant had not provided evidence of formal complaints or explanations for withholding payment for the claims in question. The court noted that the defendant had filed a cross-claim and that the appropriate venue for litigating such claims and any associated stay applications was the District Court, not the appellate court. The court concluded that the trial judge's orders did not finally prejudice the defendant, as its cross-claim could still be pursued.
The Summons was dismissed, and the claimant was ordered to pay the opponent's costs.
Orders
Orders of the court
The Summons is dismissed; the claimant is to pay the opponent's costs.
Background
Background to the litigation
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Ratio Decidendi
Legal Principle Established
Accordingly, on the true construction of the Building and Construction Industry Security of Payment Act 1999 it is permissible for a person entitled to a progress payment under a construction contract to serve a payment claim on the person who under the contract is liable to make the payment even though the claim relates to work done in periods prior to the month in which the payment claim is served. Hence the defendant’s payment claim was not invalid. Discretionary considerations The defendant’s submissions need to be evaluated in the light of the following circumstances. The 28 February 2001 Tax Invoice, Progress Claim No 9, was served on or about that day. By that day two earlier Tax Invoices had not been paid: one dated 28 December 2000 and one dated 25 January 2001. Mr A T McLennan, who signed the Subcontract on behalf of the plaintiff and who is said by Mr Penglis in an affidavit to have been the plaintiff’s representative for six years and to have been one of the two plumbers who with two apprentices carried out the work, swore an affidavit dated 1 February 2002. It was filed by the plaintiff in resistance to the defendant’s application to this Court for a stay of the trial judge’s orders pending the application for leave to appeal. Mr McLennan described the Tax Invoices dated 28 December 2000, 25 January 2001 and 28 February 2001 as being respectively Progress Claims Nos 7, 8 and 9. So to speak was to speak the language of clause 42.1 of the Subcontract, and each document so described itself. He said that each document was delivered to the plaintiff on or about the date it bears. He said that none of the money claimed had been paid by 6 April (so that the payments required by clause 42.1 were respectively at least two months six days, one month six days and six days overdue). According to Mr Penglis’ affidavit of 24 December 2001, when he told Mr McLennan that all the areas that Mr McLennan needed to work on were now ready for him, Mr McLennan said “I am not going to do any more work until I’ve been paid”. On that date Progress Claim No 7 was about six weeks overdue. On 6 April 2001 Mr McLennan sent the following letter to Mr Penglis:“Please be advised that we put Fyntray Constructions Pty Ltd on notice under Clause 44 of the subcontract conditions for failure to make payments in breach of Clause 42.1We require Fyntray Constructions Pty Ltd to show cause, in writing within 7 days of this notice, why Macind Drainage & Hydraulic Services Pty Ltd should not exercise it’s rights as stated in Clause 44.9 and request notice of cause be sent to our postal address.It is with deep regret that we take this action but feel contractual process should be followed.”Clause 44.7 provided in part: “If the Main Contractor commits a substantial breach of contract and the Subcontractor considers that damages may not be an adequate remedy, the Subcontractor may give the Main Contractor a written notice to show cause.” One substantial breach indicated was “failing to make a payment, in breach of Clause 42.1”. Clause 44.9 provided in part: “If by the time specified in a notice under Clause 44.7 the Main Contractor fails to show reasonable cause why the Subcontractor should not exercise a right referred to in Clause 44.9, the Subcontractor may by notice in writing to the Main Contractor suspend the whole or any part of the work under the Subcontract.”