| IN THE SUPREME COURT OF VICTORIA | Not Restricted |
AT MELBOURNE
COMMERCIAL AND EQUITY DIVISION
TECHNOLOGY, ENGINEERING AND CONSTRUCTION LIST
No. SCI 2012 02191
| 470 ST KILDA ROAD PTY LTD (ACN 006 075 341) | Plaintiff |
| v | |
| REED CONSTRUCTIONS AUSTRALIA PTY LTD (ACN 003 340 341) | First Defendant |
| and | |
| PHILIP MARTIN | Second Defendant |
---
JUDGE: | VICKERY J | |
WHERE HELD: | MELBOURNE | |
DATE OF HEARING: | 30 APRIL 2012 | |
DATE OF JUDGMENT: | 7 JUNE 2012 | |
| 470 ST KILDA ROAD PTY LTD v REED CONSTRUCTIONS AUSTRALIA PTY LTD & ANOR | ||
MEDIUM NEUTRAL CITATION: | [2012] VSC 235 | |
---
Building Contracts - Building and Construction Industry Security of Payment Act 2002 (Vic) – Adjudication conducted under Part 3 Division 2 of the Act – Whether ‘good faith’ a pre-condition to a valid payment claim – Whether ‘good faith’ implied into the statutory scheme for a payment claim - Whether compliance with the adjudication application time limits provided in s 18(3) of the Act a basic and essential condition of validity - Whether Adjudicator’s determination on compliance with the adjudication time limit reviewable – Allegedly false statutory declaration accompanying payment claim – Whether finding by adjudicator that payment claim valid reviewable – Whether reasons provided by adjudicator sufficient to comply with s 23 of the Act.
Statutory Interpretation – Implying words into the text of legislation – Implying “good faith” into statutory text.
---
APPEARANCES: | Counsel | Solicitors |
| For the Plaintiff | Mr T.J. Margetts SC Mr T. Cogley | Baker & McKenzie |
| For the First Defendant | Mr N. Pane | HWL Ebsworth Lawyers |
| For the Second Defendant | No Appearance |
TABLE OF CONTENTS
Background......................................................................................................................................... 1
The Good Faith Ground (Ground (a))............................................................................................ 3
The Case of St Kilda Road..................................................................................................... 3
The Case of Reed..................................................................................................................... 6
Must a Payment Claim be Made in Good Faith?............................................................... 6
Implying Words into Statutory Text.................................................................................. 10
Conclusion as to Good Faith Ground................................................................................ 11
The Payment Schedule (Grounds (b) & (c))................................................................................ 12
St Kilda Road’s Case............................................................................................................. 12
Reed’s Case............................................................................................................................ 15
Whether Time Compliance in s 18(3)(c) & (d) a Basic and Essential Requirement.... 15
Adjudicator’s Determination............................................................................................... 16
The Statutory Declaration (Grounds (d), (e), (f) & (g)).............................................................. 18
Finding as to the Power of the Adjudicator to Consider the Statutory Declaration... 21
Finding as to the Veracity of the Statutory Declaration.................................................. 22
Finding as to Compliance with Clause 38.1 and Adequacy of Reasons...................... 24
Failing to take into Account the Terms of the Construction Contract........................... 27
Conclusion as to Statutory Declaration Grounds (d), (e), (f) & (g)................................. 28
Orders................................................................................................................................................. 28
HIS HONOUR:
Background
This proceeding arises under the Building and Construction Industry Security of Payment Act 2002 (Vic) (the “Act”). It raises questions at to whether there was a valid payment claim and whether there was a valid adjudication determination under the Act.
The Plaintiff, 470 St Kilda Road Pty Ltd (“St Kilda Road”), seeks judicial review of an adjudication determination (the “Adjudication Determination”) dated 10 April 2012 of the Second Defendant, Mr Philip Martin (the “Adjudicator”), purportedly made pursuant to s 23 of the Act. The Adjudicator took no part…
Keep reading for free
Create a free CaseChat account to read 470 St Kilda Road Pty Ltd v Reed Constructions Australia Pty... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2012] VSC 235
- Decision Date
CaseChat Overview and Summary
The court found that "good faith" was not an implied term in the statutory scheme for a payment claim under the Act. It concluded that the Act was intended to provide a streamlined and efficient process for resolving payment disputes, and the inclusion of "good faith" as a condition would undermine this purpose. The court also determined that compliance with the adjudication application time limits was not a basic and essential condition of validity, and the adjudicator's decision on this compliance was not reviewable. However, the court held that a finding by the adjudicator that the payment claim was valid could be reviewed if the reasons provided were insufficient. In this case, the adjudicator's reasons were deemed sufficient, and the decision was upheld.
The court dismissed the proceedings brought by 470 St Kilda Road Pty Ltd against Reed Constructions Australia Pty Ltd. It found that the adjudicator's determination was valid and that the time limits for adjudication applications did not invalidate the payment claim. The court also held that the adjudicator's reasons were sufficient to meet the requirements of the Act, and the findings on the validity of the payment claim were not reviewable. The court's decision reinforced the importance of the streamlined adjudication process under the Act and the role of adjudicators in ensuring timely and efficient resolution of payment disputes in the building and construction industry.