| IN THE SUPREME COURT OF VICTORIA | Not Restricted |
AT MELBOURNE
COMMERCIAL AND EQUITY DIVISION
TECHNOLOGY ENGINEERING AND CONSTRUCTION LIST
S ECI 2015 000325
| SSC PLENTY ROAD PTY LTD (ACN 124 197 128) | Plaintiff |
| v | |
| CONSTRUCTION ENGINEERING (AUST) PTY LTD (ACN 392 781 199) & Anor | Defendants |
---
JUDGE: | VICKERY J |
WHERE HELD: | MELBOURNE |
DATE OF HEARING: | 17 SEPTEMBER 2015 |
DATE OF JUDGMENT: | 13 NOVEMBER 2015 |
CASE MAY BE CITED AS: | SSC PLENTY ROAD v CONSTRUCTION ENGINEERING (AUST) |
MEDIUM NEUTRAL CITATION: | [2015] VSC 631 1st Revision 17 November 2015 |
---
BUILDING CONTRACTS – Building and Construction Industry Security of Payment Act 2002 (Vic) (the “Act”) – Whether a contractual provision in the relevant construction contract that mandates attendance of the parties at mediation is a “method of resolving disputes” for the purposes of s 10A(3)(d)(ii) of the Act – Whether adjudicator valued work in accordance with the Act – Valuation task of adjudicator under the Act considered – Whether terms of construction contract void under s 48 of the Act for inconsistency with the Act.
ADMINISTRATIVE LAW – Judicial review – Determination of an adjudicator appointed under the Building and Construction Industry Security of Payment Act 2002 (Vic) (the “Act”) – Whether error of law amounting to jurisdictional error – Robust approach to be taken to review of adjudicator’s valuation – Standard of adjudicator’s reasons towards the lower end of the scale - Certiorari to quash the decision allowed in part.
STATUTORY INTERPRETATION – Contemporary maxim “Laws must not command the impossible”.
---
APPEARANCES: | Counsel | Solicitors |
| For the Plaintiff | Mr J A F Twigg QC with Dr K Weston-Scheuber | Baker & McKenzie |
| For the First Defendant | Mr T J Margetts QC | Piper Alderman |
HIS HONOUR:
This is an application by the Plaintiff, SSC Plenty Road Pty Ltd (“Plenty Road”) for judicial review of an adjudication determination made by the Second Defendant (the “Adjudicator”) on 21 August 2015 (the “Adjudication Determination”) under the Building and Construction Industry Security of Payment Act 2002 (Vic) (the “Act”).
The Adjudicator agreed to be bound by the decision of the Court, and took no part in the proceeding.
By a construction contract entered into on or about 20 December 2013, Plenty Road as the principal engaged the Defendant, Construction Engineering (Aust) Pty Ltd (“Construction Engineering”) as the designer and builder to design and construct a shopping centre at 850 Plenty Road, Reservoir in Victoria (the “Project”), for the sum of $35,554,985 (plus GST) (the “Construction Contract”).
Trevor Main & Associates Pty Ltd was appointed the superintendent under the Construction Contract (the “Superintendent”).
The Adjudication Determination arises from a payment claim made by Construction Engineering as the claimant purportedly under the Act, by a claim dated 1 July 2015 (the “Payment Claim”). The Payment Claim was served as Progress Claim No 19 in the course of the Project. The amount of the Payment Claim was $4,460,815.06 (including GST).
Plenty Road seeks relief by way of certiorari on the ground of jurisdictional error which it says is…
Keep reading for free
Create a free CaseChat account to read SSC Plenty Road Pty Ltd v Construction Engineering (Aust) Pt... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2015] VSC 631
- Decision Date
CaseChat Overview and Summary
The court found that the contractual provision requiring mediation was not a “method of resolving disputes” under the Act, as it did not provide a process for resolving disputes about payment claims. The court also found that the adjudicator’s valuation was flawed, as it did not consider all the evidence before them. However, the court held that the adjudicator’s decision was not so flawed as to be quashed, and that the terms of the construction contract were not inconsistent with the Act. The court emphasised that the adjudicator’s valuation task was to consider the evidence and make a determination as to whether payment was due, and that the adjudicator had performed this task. The court held that the standard of reasons required from an adjudicator was towards the lower end of the scale, and that a robust approach should be taken to the review of an adjudicator’s decision.
The court also held that the adjudicator’s decision should be quashed in part, as it had not considered all the evidence before them. The court found that the adjudicator had failed to consider a specific document that was relevant to the valuation of the work performed. The court held that this error amounted to a jurisdictional error, as it meant that the adjudicator had not considered all the evidence before them. The court also found that the adjudicator’s decision was flawed in that it had not considered the impact of a contractual term that required the parties to negotiate in good faith. The court held that this term was inconsistent with the Act, and that the adjudicator should have considered its impact on the valuation of the work performed. The court ordered that the adjudicator’s decision be quashed in part, and that the matter be remitted to the adjudicator for reconsideration.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.