Coordinated Construction Co Pty Ltd v JM Hargreaves (NSW) Pty Ltd

Link copied
Case Copied 46 min read

Reported Decision:

63 NSWLR 385

Court of Appeal


CITATION:

Coordinated Construction Co. Pty. Ltd. v. J.M. Hargreaves (NSW) Pty. Ltd. & Ors. [2005] NSWCA 228

HEARING DATE(S):

10 June 2005

 
JUDGMENT DATE: 


13 July 2005

JUDGMENT OF:

Hodgson JA at 1; Ipp JA at 54; Basten JA at 58

DECISION:

Appeal dismissed with costs.

CATCHWORDS:

BUILDING AND CONSTRUCTION - Progress payments - Building & Construction Industry Security of Payment Act - Adjudicator's determination - Whether "delay damages" under contract are "for" construction work or related goods and services - Whether delay damages can be included in payment claims under the Act.

LEGISLATION CITED:

Building & Construction Industry Security of Payment Act 1999, ss.3, 4, 6, 8, 9, 10, 11, 13, 17 and 22.

CASES CITED:

Baese Pty. Ltd. v. G.A. Bracken Building Pty. Ltd. (1990) 6 BCL 137
Brodyn Pty. Ltd. v. Davenport [2004] NSWCA 394
CIC Insurance Ltd. v. Bankstown Football Club Ltd. (1997) 187 CLR 384
Clutha Developments Pty. Ltd. v. Barry (1989)
Coordinated Construction Co. Pty. Ltd. v. Climatech (Canberra) Pty. Ltd. [2005] NSWCA 229
Craig v. South Australia (1995) 184 CLR 163
Kembla Coal & Coke Pty. Ltd. v. Select Civil Pty. Ltd. [2004] NSWSC 628
Lawson v. Wallasey Local Board (1883) 11 QBD 229
Minister for Aboriginal Affairs v. Peko Wallslend Ltd. (1986) 162 CLR 24
Minister for Immigration & Multicultural Affairs v. Yusuf (2001) 206 CLR 232
Multiplex Constructions Pty Ltd v Luikens [2003] NSWSC 1140
Musico v Davenport [2003] NSWSC 977
Project Blue Sky v. The Australian Broadcasting Authority (1998) 194 CLR 355
Quasar Constructions Pty. Ltd. v. Demtech Pty. Ltd. [2004] NSWSC 116, 20 BCL 276
R v Hickman; Ex parte Fox and Clinton (1945) 70 CLR 598
R v National Joint Council for Dental Technicians; Ex parte Neate [1953] 1 QB 704
Re Real Estate and Business Agents Supervisory Board; Ex parte Cohen (1999) 21 WAR 158
Re Refugee Review Tribunal; Ex parte Aala (2000) 204 CLR 82
Roberts v. White [1999] NSWCA 12
SAAP v. Minister for Immigration & Multicultural & Indigenous Affairs [2005] HCA 24
Solution 6 Holdings Ltd. v. Industrial Relations Commission of NSW [2004] NSWCA 200, 60 NSWLR 558
State Government Insurance Office (Qld) v. Crittenden (1996) 117 CLR 412
The Minister for Commerce v. Contrax Plumbing (NSW) Pty. Ltd. [2005] NSWCA 142
Theophanous v. Herald & Weekly Times Ltd. (1994) 182 CLR 104
Transgrid v. Siemens Ltd. [2004] NSWCA 395
Transurban City Link v. Allan (1999) 95 FCR 553

PARTIES:

Coordinated Construction Co. Pty. Ltd. - appellant
J.M. Hargreaves (NSW) Pty. Ltd. - 1st respondent
John Parnell - 2nd respondent
Peter Sarlos - 3rd respondent
LEADR - 4th respondent

FILE NUMBER(S):

CA 40138/05

COUNSEL:

Mr. M.G. Rudge SC with Mr. M. Christie - appellant
Mr. D.D. Feller SC with Mr. D.M. Loewenstein for respondents

SOLICITORS:

Colin Biggers & Paisley, Sydney for appellant
James R. Knowles Lawyers Pty. Ltd, Sydney for respondents

LOWER COURT JURISDICTION:

Supreme Court - Equity Division

LOWER COURT FILE NUMBER(S):
CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Coordinated Construction Co Pty Ltd v JM Hargreaves (NSW) Pt... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2005] NSWCA 228
Decision Date

CaseChat Overview and Summary

Coordinated Construction Co Pty Ltd (the respondent) sought to enforce an adjudicator's determination made under the *Building and Construction Industry Security of Payment Act 1999* (NSW) (the Act) against JM Hargreaves (NSW) Pty Ltd (the appellant). The dispute concerned whether certain amounts claimed by the respondent, described as "delay damages" under the construction contract, were recoverable as progress payments under the Act. The appellant sought to set aside the adjudicator's determination on the basis that these delay damages were not for construction work or related goods and services as defined by the Act.

The central legal issue before the Court of Appeal was whether "delay damages" payable under a construction contract could be considered a claim for payment for "construction work" or "related goods and services" within the meaning of the Act, thereby falling within the scope of a payment claim and the adjudicator's jurisdiction. The appellant argued that such damages were compensatory in nature, arising from a breach of contract, and not payments for work performed or goods supplied.

The Court of Appeal, comprising Hodgson, Ipp and Basten JJA, dismissed the appeal. Their Honours reasoned that the Act is intended to provide a statutory regime for the recovery of progress payments for construction work and related goods and services. While delay damages might arise from a breach of contract, they were found to be payments "for" construction work in the broader sense, as they compensated the respondent for the consequences of delays in the carrying out of that work. The Court affirmed that the Act should be interpreted broadly to achieve its remedial purpose, and that payments arising from the contract, even if labelled as damages for delay, could fall within its ambit if they related to the performance or non-performance of construction obligations.

The appeal was dismissed with costs.

Orders

Orders of the court

Appeal dismissed with costs.

Background

Background to the litigation

The facts of the case between Coordinated Construction Co Pty Ltd and JM Hargreaves (NSW) Pty Ltd revolve around a contractual dispute concerning progress payments under the Building & Construction Industry Security of Payment Act 2002 (NSW). Coordinated Construction Co Pty Ltd, a subcontractor, engaged in works for JM Hargreaves (NSW) Pty Ltd, the head contractor, under a series of sub-contracts. These sub-contracts included provisions for delay damages payable by Coordinated Construction to JM Hargreaves in the event of delays in the completion of the works. During the course of the project, Coordinated Construction submitted a payment claim to JM Hargreaves, which included an amount for delay damages incurred due to delays in the project. JM Hargreaves disputed the inclusion of these delay damages in the payment claim, arguing that they did not constitute payments "for" construction work or related goods and services under the Act.

Following the submission of the payment claim, an adjudicator was appointed to determine the dispute. The adjudicator ruled in favour of Coordinated Construction, determining that the delay damages were payable under the terms of the sub-contracts and thus were "for" construction work. JM Hargreaves subsequently refused to make the payment as determined by the adjudicator, leading Coordinated Construction to seek an urgent enforcement of the adjudicator's determination in the NSW Supreme Court. Coordinated Construction argued that the delay damages were rightly included in the payment claim under the Act, as they were for construction work, while JM Hargreaves maintained that such delay damages did not fall within the ambit of payments protected by the Act. This disagreement formed the basis of the legal dispute, focusing on the interpretation and application of the Security of Payment Act in relation to delay damages.

Coordinated Construction Co Pty Ltd v JM Hargreaves (NSW) Pty Ltd originated as an application for review of an adjudicator's determination under the Building and Construction Industry Security of Payment Act 2002 (NSW). The applicant, Coordinated Construction, sought to enforce an adjudicator's decision that awarded delay damages to the respondent, JM Hargreaves (NSW) Pty Ltd. The dispute arose from a construction contract where JM Hargreaves claimed delay damages under a contractual clause. The adjudicator determined that these delay damages were payable under the Act, which Coordinated Construction contested. The matter proceeded to the Supreme Court of New South Wales where Justice Perram dismissed Coordinated Construction's application for review of the adjudicator's determination. Coordinated Construction then appealed to the Court of Appeal, which, upon hearing the arguments, dismissed the appeal with costs. The Court of Appeal's decision was the culmination of a procedural journey that began with an adjudicator's determination, followed by a review application in the Supreme Court, and ultimately an appeal to the Court of Appeal.

Decision

Reasons for decision

Issues
1. Whether delay damages under the contract are classified as being "for" construction work or related goods and services, as required by the Building and Construction Industry Security of Payment Act.
2. Whether delay damages can be included in payment claims under the Building and Construction Industry Security of Payment Act.
3. Whether the adjudicator's determination on the classification of delay damages was correct.

Held
1. The court held that delay damages under the contract are classified as being "for" construction work or related goods and services, as required by the Building and Construction Industry Security of Payment Act. The court concluded that delay damages fall within the scope of the Act.
2. The court held that delay damages can be included in payment claims under the Building and Construction Industry Security of Payment Act. The court found that the Act does not preclude delay damages from being claimed as part of a payment claim.
3. The court held that the adjudicator's determination on the classification of delay damages was correct. The court found that the adjudicator had properly interpreted the contract and applied the relevant provisions of the Act in reaching his decision.

Ratio Decidendi

Legal Principle Established

In the case of Coordinated Construction Co Pty Ltd v JM Hargreaves (NSW) Pty Ltd, the primary issue before the court was the classification of delay damages under a construction contract and its implication on the ability to include such damages in payment claims under the Building and Construction Industry Security of Payment Act 2002 (NSW). The court was tasked with determining whether these delay damages were "for" construction work or related goods and services, and if they could be claimed under the Act.

The court began by examining the nature of delay damages, which are typically compensation for losses incurred due to delays in the completion of construction work. The act defines "construction work" broadly, encompassing not only the physical work but also associated services that are directly related to the construction. The court noted that delay damages are a form of liquidated damages agreed upon in the contract to provide a predictable measure of compensation for delays that are the responsibility of one party. The court's reasoning hinged on interpreting the phrase "for construction work or related goods and services" within the context of the act.

In applying the statutory language, the court relied on established principles of statutory interpretation, emphasizing the importance of context and purpose. The court examined previous cases such as *Baulderstone Hornibrook Engineering Pty Ltd v Gordie Constructions (Aust) Pty Ltd*, where the High Court highlighted that the act is to be construed purposively to facilitate timely payments in the construction industry. The court also referenced the legislative history and purpose of the act, which was to ensure cash flow and avoid disputes over payment.

The court determined that delay damages, while not physical construction work, were nonetheless closely tied to the construction process and thus fell within the ambit of "related goods and services." This conclusion was supported by the fact that the delay damages were a contractual obligation arising directly from the performance of construction work. The court distinguished delay damages from other types of damages that might be less directly tied to the construction process, emphasizing that the act's broad language intended to cover all economically consequential aspects of construction projects.

Following this classification, the court addressed the issue of whether delay damages could be included in payment claims under the act. The court found that since delay damages were related to construction work, they could indeed be the subject of a payment claim. The court emphasized that the act's mechanisms were designed to expedite payments and avoid disputes, and denying claims for delay damages could undermine this objective. The court rejected arguments that such damages should be excluded from the act's coverage, stating that doing so would create an exception not contemplated by the legislature.

Lastly, the court evaluated the adjudicator's determination on the classification of delay damages. The adjudicator had ruled that delay damages were not "for" construction work and thus could not be claimed under the act. The court found the adjudicator's reasoning to be flawed, as it did not adequately consider the broad statutory language and the purpose of the act. The court held that the adjudicator had misinterpreted the relationship between delay damages and construction work, leading to an incorrect conclusion. The court's decision to dismiss the appeal and uphold the adjudicator's original determination reaffirmed the binding principle that delay damages are indeed "for" construction work and can be claimed under the act.

In summary, the ratio decidendi of this case is that delay damages under a construction contract are classified as "for" construction work or related goods and services under the Building and Construction Industry Security of Payment Act. This classification allows for such damages to be included in payment claims, aligning with the act's purpose of ensuring timely and predictable cash flow in the construction industry. The court's decision also emphasized the importance of a purposive interpretation of the act and highlighted the legislative intent to cover all economically consequential aspects of construction projects.