Court of Appeal
Supreme Court
New South Wales
- Amendment notes
Medium Neutral Citation: Cockram Construction Ltd v Fulton Hogan Construction Pty Ltd [2018] NSWCA 107 Hearing dates: 10 May 2018 Date of orders: 10 May 2018 Decision date: 21 May 2018 Before: Basten JA at [1];
Meagher JA at [19];
Barrett AJA at [42]Decision: 1. Allow the appeal.
2. Set aside orders 1, 2 and 4 made on 7 March 2018.
3. Dismiss the summons filed 26 February 2018 with costs.
4. Order the first respondent to pay the appellant’s costs of the appeal.Catchwords: BUILDING AND CONSTRUCTION – adjudication of payment claim – review of adjudicator’s decision –content of the reasons to be included in determination – where adjudicator concluded that contractual condition precedent to extension of time was not legitimate or workable because it depended on something happening under another contract – whether the determination failed to include the reasons for the determination – whether the adjudicator departed from the statutory function by so concluding Legislation Cited: Building and Construction Industry Security of Payment Act 1999 (NSW), ss 12, 22 Cases Cited: Azriel v NSW Land & Housing Corporation (2006) 67 NSWLR 256; [2006] NSWCA 372
Coordinated Construction Co Pty Ltd v JM Hargreaves (NSW) Pty Ltd (2005) 63 NSWLR 385; [2005] NSWCA 228
Minister for Aboriginal Affairs v Peko-Wallsend Ltd (1986) 162 CLR 24; [1986] HCA 40
Minister for Immigration and Ethnic Affairs v Wu Shan Liang (1996) 185 CLR 259; [1996] HCA 6
Probuild Constructions (Aust) Pty Ltd v Shade Systems Pty Ltd [2018] HCA 4; 92 ALJR 248
Re Minister for Immigration and Multicultural and Indigenous Affairs; Ex parte Palme (2003) 216 CLR 212; [2003] HCA 56
Shade Systems Pty Ltd v Probuild Constructions (Aust) Pty Ltd (No 2) [2016] NSWCA 379; 344 ALR 355
Weal v Bathurst City Council [2000] NSWCA 88; (2000) 11 LGERA 181Category: Principal judgment Parties: Cockram Construction Ltd (Appellant)
Fulton Hogan Construction Pty Ltd (First Respondent)
Rosemarie Risgalla (Second Respondent)Representation: Counsel:
Solicitors:
M Christie SC, D Hume (Appellant)
S Robertson, PF Santucci (First Respondent)
Vincent Young (Appellant)
Maddocks (First Respondent)
File Number(s): 2018/81325 Decision under appeal
- Court or tribunal:
- Supreme Court
- Jurisdiction:
- Equity
- Citation:
- [2018] NSWSC 264
- Date of Decision:
- 07 March 2018
- Before:
- Ball J
- File Number(s):
- 2018/63885
Headnote
[This headnote is not to be read as part of the decision]
The appellant (subcontractor) issued a payment claim to the first respondent (head contractor) within the Building and Construction Industry Security of Payment Act 1999 (NSW). In response, the head contractor issued a payment schedule claiming contractual set off for amounts due as liquidated damages for delay. The subcontractor then applied for adjudication under the Act, claiming various extensions of time in answer to any set off. In so doing, it denied that the head contractor could rely on a clause providing that the subcontractor was entitled to an extension only if, amongst other things, the head contractor…
Keep reading for free
Create a free CaseChat account to read Cockram Construction Ltd v Fulton Hogan Construction Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2018] NSWCA 107
- Decision Date
CaseChat Overview and Summary
The primary legal issues before the Court of Appeal were whether the adjudicator's determination failed to include adequate reasons for its decision, and whether the adjudicator had departed from its statutory function by concluding that the contractual condition precedent was not legitimate or workable. The appellant argued that the adjudicator's reasons were insufficient and that the adjudicator had impermissibly ventured into determining the validity of the underlying contract rather than merely assessing the payment claim.
The Court of Appeal allowed the appeal, finding that the adjudicator's determination did not adequately set out the reasons for its conclusion regarding the contractual condition precedent. The Court held that while an adjudicator is empowered to consider the substance of a claim, including whether conditions precedent have been met, the reasons provided must clearly articulate the basis for such findings. The Court determined that the adjudicator had not departed from its statutory function but had failed to provide a sufficiently detailed explanation for its reasoning. Consequently, the Court set aside the primary judge's orders and dismissed the summons filed by the appellant, ordering the respondent to pay the appellant's costs of the appeal.
Orders
Orders of the court
1. Allow the appeal.
2. Set aside orders 1, 2 and 4 made on 7 March 2018.
3. Dismiss the summons filed 26 February 2018 with costs.
4. Order the first respondent to pay the appellant’s costs of the appeal.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.