Supreme Court
New South Wales
- Amendment notes
Medium Neutral Citation: CPB Contractors Pty Limited v Heyday5 Pty Limited [2020] NSWSC 1625 Hearing dates: 2 November 2020 Decision date: 16 November 2020 Jurisdiction: Equity - Technology and Construction List Before: Hammerschlag J Decision: Summons dismissed
Catchwords: BUILDING AND CONSTRUCTION – Building and Construction Industry Security of Payment Act 1999 (NSW) ss 22(2), (3), (5) – An adjudication determination upheld a claim for a variation of a building contract consisting of a direction by a head contractor to a sub-contractor to provide spotters for mobile elevated work platforms – Challenge to the determination on the grounds that it discloses no evident or intelligible justification for upholding the claim and that the adjudicator denied the plaintiffs procedural fairness because he found them on bases not the subject of submission duly made – HELD – Challenges not made out – Importance of recognising that adjudicators’ determinations are not judgments of a court, that the procedural behaviour of adjudicators and determinations should not be examined with an overcritical or pedantic eye but should be viewed with common sense and without undue legality and should not be scrutinised with a fine-tooth comb approach.
Legislation Cited: Building and Construction Industry Security of Payment Act 1999 (NSW)
Cases Cited: Cockram Construction Ltd v Fulton Hogan Construction Pty Ltd [2018] NSWCA 107
Colin Joss & Co Pty Ltd v Cube Furniture Pty Ltd [2015] NSWSC 735
Minister for Immigration and Ethnic Affairs v Wu Shan Liang (1996) 185 CLR 259
Perform (NSW) Pty Ltd v Mev-Aus Pty Ltd [2009] NSWCA 157
Re Minister for Immigration and Multicultural Affairs; Ex parte Lam (2003) 214 CLR 1
Category: Principal judgment Parties: CPB Contractors Pty Limited - First Plaintiff
Dragados Australia Pty Ltd - Second Plaintiff
Samsung C&T Corporation - Third Plaintiff
Heyday5 Pty Limited - First Defendant
David Francis - Second Defendant
Resolution Institute - Third DefendantRepresentation: Counsel:
Solicitors:
M Christie SC with D Hume - Plaintiffs
FP Hicks SC with A Cameron - First Defendant
MinterEllison - Plaintiffs
Kreisson - First Defendant
File Number(s): 2020/260298
Judgment
INTRODUCTION
-
HIS HONOUR: This is a challenge to an adjudication determination (the Determination) made by the second defendant (the Adjudicator) in favour of the first defendant (Heyday) against the plaintiffs (together CDSJV), for $13,153,289.098 (excluding GST) on 30 August 2020 under the provisions of the Building and Construction Industry Security of Payment Act 1999 (NSW) (the Act).
-
CDSJV is a joint venture which had the head contract for the WestConnex project, which includes the construction of roads, a tunnel, and other physical works.
-
On 9 July 2018 under a written works contract (the Contract), CDSJV retained Heyday (defined as the Contractor in the Contract) to do electrical installation works on the project.
-
The work to be done under the Contract required use of mobile elevated work platforms (MEWPs).
-
$7,120,922 of the total adjudicated amount was determined by the Adjudicator to be owing to Heyday…
Keep reading for free
Create a free CaseChat account to read CPB Contractors Pty Limited v Heyday5 Pty Limited and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2020] NSWSC 1625
- Decision Date
CaseChat Overview and Summary
The primary legal issues before the court were whether the adjudication determination disclosed no evident or intelligible justification for upholding the claim, and whether the adjudicator denied CPB procedural fairness by finding them on bases not the subject of submission duly made. The court had to consider the appropriate standard of review for an adjudication determination, and whether the determination should be examined with an overcritical or pedantic eye, or viewed with common sense and without undue legality.
The court held that the challenges to the adjudication determination were not made out. It recognised that adjudicators' determinations are not judgments of a court, and that the procedural behaviour of adjudicators and determinations should not be examined with an overcritical or pedantic eye but should be viewed with common sense and without undue legality. The court found that the determination was not so unreasonable as to justify setting it aside, and that there was an evident or intelligible justification for upholding the claim. The court also held that the adjudicator did not deny CPB procedural fairness, as the submissions made by CPB were sufficient to put Heyday5 on notice of the arguments that CPB intended to raise.
The court upheld the adjudication determination and ordered CPB to pay the sub-contractor the amount determined by the adjudicator, plus interest and costs.
Background
Background to the litigation
The matter came before the court as an application to set aside the adjudication determination under section 22(2) of the Building and Construction Industry Security of Payment Act 1999 (NSW). The application was heard by a judge of the Supreme Court of New South Wales. Heyday5 argued that the adjudicator's determination was flawed and should be set aside. The primary issue was whether the adjudicator's determination disclosed an evident or intelligible justification for upholding the claim and whether procedural fairness was observed. The court examined the adjudicator's determination, the submissions made, and the arguments presented by both parties.
Decision
Reasons for decision
1. Did the adjudicator's determination disclose an evident or intelligible justification for upholding the claim for the cost of providing spotters for mobile elevated work platforms?
2. Was Heyday5 denied procedural fairness by the adjudicator finding them on bases not the subject of submission duly made?
Held
1. The court concluded that the adjudicator's determination disclosed an evident or intelligible justification for upholding the claim for the cost of providing spotters for mobile elevated work platforms. The appeal against the adjudicator's determination was dismissed.
2. The court determined that Heyday5 was not denied procedural fairness by the adjudicator finding them on bases not the subject of submission duly made. The application was dismissed.
Ratio Decidendi
Legal Principle Established
The court examined the adjudicator's determination and found that it contained an intelligible justification for the claim, despite the absence of explicit reasoning. The court emphasised that adjudicators' determinations are not to be scrutinised with the same rigour as court judgments, and should be viewed with common sense and without undue legality. The court recognised the practical nature of adjudication processes and held that procedural fairness was not compromised by the adjudicator's approach. The ratio decidendi of this case is that adjudicators' determinations should not be examined with an overcritical or pedantic eye and should be viewed with common sense and without undue legality. This decision aligns with the overarching principle that adjudication is a practical and speedy process, not a mini-trial. The court also highlighted the importance of not scrutinising adjudicators' determinations with a fine-tooth comb approach. The decision did not depart from prior authority but reinforced the existing approach to reviewing adjudicators' determinations.