Goyder Wind Farm 1 Pty Ltd v Ge Renewable Energy Australia Pty Ltd

Link copied
Case Copied 71 min read

SUPREME COURT OF SOUTH AUSTRALIA

(Civil: Judicial Review)

GOYDER WIND FARM 1 PTY LTD v GE RENEWABLE ENERGY AUSTRALIA PTY LTD & ORS

[2024] SASC 108

Judgment of the Honourable Justice Stein  

CONTRACTS - BUILDING, ENGINEERING AND RELATED CONTRACTS - REMUNERATION - STATUTORY REGULATION OF ENTITLEMENT TO AND RECOVERY OF PROGRESS PAYMENTS - ADJUDICATION OF PAYMENT CLAIMS

CONTRACTS - GENERAL CONTRACTUAL PRINCIPLES - CONSTRUCTION AND INTERPRETATION OF CONTRACTS

STATUTES - ACTS OF PARLIAMENT - INTERPRETATION - GENERAL APPROACHES TO INTERPRETATION - TO GIVE OPERATION AND EFFECT TO ACT

ADMINISTRATIVE LAW - PREROGATIVE WRITS AND ORDERS - CERTIORARI - GROUNDS FOR CERTIORARI TO QUASH - EXCESS OR WANT OF JURISDICTION - PARTICULAR INSTANCES OF JURISDICTIONAL ERROR

PROCEDURE - STATE AND TERRITORY COURTS: JURISDICTION, POWERS AND GENERALLY - INHERENT AND GENERAL STATUTORY POWERS - TO PREVENT ABUSE OF PROCESS - ATTEMPTS TO RELITIGATE

ESTOPPEL - ESTOPPEL BY JUDGMENT - ISSUE ESTOPPEL - GENERAL PRINCIPLES

ESTOPPEL - ESTOPPEL BY JUDGMENT - ANSHUN ESTOPPEL - GENERALLY

Goyder Wind Farm 1 Pty Ltd, the applicant (“Goyder”), entered into contracts with GE Renewable Energy Australia Pty Ltd and Elecnor Australia Pty Ltd, the first and second respondents (“GE‑Elecnor”), for the construction of a windfarm. 

GE-Elecnor has issued at different times three separate claims for progress payments relating to claimed entitlement to delay costs arising from a claimed an extension of time pursuant to the contract.  Two of the claims have proceeded to adjudication determination pursuant to Building and Construction Industry Security of Payment Act 2009 (SA) (“the Act”). The third claim is currently enjoined from proceeding by interim orders made at the commencement of these proceedings.

Goyder applied for review of the second determination by the adjudicator and sought an order quashing that second determination in addition to orders preventing GE-Elecnor taking steps to enforce the determination and from taking steps to progress a third claim to adjudication.

Goyder submitted the adjudicator had erred in the second determination on the basis he failed to apply s 22(4) of the Act and wrongfully permitted GE-Elecnor to re-agitate the claim for delay costs.

GE-Elecnor submitted the various delay cost claims were different and there had been no impermissible re-agitation of claims as between the first and second determination and the third payment claim.

Held (dismissing the application insofar as it relates to the second adjudication determination):

1.The delay claims did not constitute a singular claim for construction work which would have been carried out in the extension of time period.

2.Section 22(4) of the Act did not apply. If it had applied, s 22(4) of the Act is not a matter of jurisdiction.

3.The prolongation and procurement premium delay cost claims did not overlap and it was not an abuse of the processes of the Act to claim those amounts in separate payment claims.

Held (allowing the application insofar as it relates to the thickening costs claim aspect of the third adjudication claim):

4.The thickening costs claim aspect of the claim is precluded by the legislation as an…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Goyder Wind Farm 1 Pty Ltd v Ge Renewable Energy Australia P... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details

Case
[2024] SASC 108
Decision Date

CaseChat Overview and Summary

Goyder Wind Farm 1 Pty Ltd (Goyder) commenced proceedings in the Supreme Court of South Australia against GE Renewable Energy Australia Pty Ltd (GE-Elecnor) seeking relief in relation to an adjudication determination and an injunction preventing GE-Elecnor from proceeding with an application for a further adjudication. Goyder argued that the adjudicator’s Second Adjudication Determination was flawed and should be set aside. It further contended that the Third Adjudication Application which sought a determination in relation to thickening costs should be enjoined from proceeding. GE-Elecnor argued that the Second Adjudication Determination was valid and should not be set aside. It contended that Goyder had not established any basis upon which to enjoin the Third Adjudication Application from proceeding. The court was required to determine whether the Second Adjudication Determination was flawed and should be set aside. It was also required to determine whether the Third Adjudication Application should be enjoined from proceeding. The court considered the arguments of both parties and examined the relevant provisions of the contract and the applicable legislation. The court held that the Second Adjudication Determination was not flawed and should not be set aside. It found that the adjudicator had not made a jurisdictional error and that GE-Elecnor had not re-agitated its claim in a manner that amounted to an abuse of process. The court also held that the Third Adjudication Application should not be enjoined from proceeding. It found that the invalid part of the Third Payment Claim could be severed and that the adjudicator had jurisdiction to address the thickening costs claim. The court declined to grant relief in relation to the Second Adjudication Determination but made orders in relation to the thickening costs claim aspect of the Third Adjudication Application. The injunctive orders made in relation to the Second Adjudication Determination should be lifted.

The court's decision in Goyder Wind Farm 1 Pty Ltd v GE Renewable Energy Australia Pty Ltd demonstrates the importance of understanding the provisions of a contract and the applicable legislation when resolving disputes. The court found that the adjudicator had not made a jurisdictional error and that GE-Elecnor had not re-agitated its claim in a manner that amounted to an abuse of process. This decision highlights the importance of following the correct procedures when making claims and seeking adjudication. The court's decision also highlights the importance of understanding the limitations of the court's jurisdiction when resolving disputes. The court declined to grant relief in relation to the Second Adjudication Determination but made orders in relation to the thickening costs claim aspect of the Third Adjudication Application. This decision demonstrates the court's willingness to make orders that are within its jurisdiction while respecting the limitations of its role in resolving disputes.

Orders

Orders of the court

Background

Background to the litigation

For the reasons that follow I have determined to refuse the application insofar as it relates to the adjudication determination made on 17 July 2024 but to make orders in relation to aspects of the application for adjudication which is presently enjoined from proceeding. BackgroundThe contract In 2021, Goyder and GE-Elecnor entered into engineering, procurement and construction contracts for the construction of a wind farm (the “contract”). The project was divided into Stage 1A and Stage 1B with Stage 1A relating to 38 wind turbines. In the contract, delay costs are defined as “costs payable to GE-Elecnor for delay and disruption determined in accordance with cl 13.11”. Clause 13.3 of the contract provides for GE-Elecnor’s entitlement to, and process for, seeking extensions of time (“EOT”). If GE-Elecnor considers it has been or is likely to be delayed, it must give written notice of the delay. If a delay event continues for a period longer than contemplated in the EOT claim, GE‑Elecnor may amend the EOT claim by submitting a revised claim.[1] [1] Contract, cl 13.3(c). Under cl 13.11(a) of the contract, where GE-Elecnor has been granted an extension of time under cl 13.3 for delays of the kind defined as a Delay Cost Event, Goyder must pay to GE-Elecnor delay costs being “such extra costs as are directly and necessarily incurred by [GE-Elecnor] in connection with the extension by reason of the Delay Cost Event”. Delay costs are valued in accordance with schedule 5 to the contract. Pursuant to clause 20.1 of the contract, in each calendar month, if GE-Elecnor considers there has been a completion of a milestone event or that other amounts are payable to GE-Elecnor under the contract, GE-Elecnor is to submit to the Principal’s Representative (as defined in the contract) a claim for payment. Clause 20 sets out the matters which must be addressed in a payment claim. It includes calculation of milestone amounts and any other amounts payable to GE-Elecnor in accordance with the contract. GE-Elecnor may only submit one payment claim per calendar month. The contract provides for a payment schedule to be issued to GE-Elecnor certifying, among other things, the milestone amount attributable to a certified completed milestone event and any other amounts payable to GE-Elecnor in accordance with the contract.[2] The amount to be certified in a payment schedule is able to be adjusted by, among other things, any correction to amounts previously certified in a previous payment certificate.[3] [2] Contract, cl 20.3.[3] Contract, cl 20.4(b). Pursuant to the contract, any payment certificate or payment of monies under cl 20.6 is only a payment on account.[4] [4] Contract, cl 20.8. A failure to include in a payment certificate any amount which Goyder is entitled to retain, deduct, withhold or set off does not prejudice Goyder’s right to subsequently exercise such rights to retain, deduct, withhold or set off any amount.[5] [5] Contract, cl 20.8(b).

Evidence

Evidence before the court

Decision

Reasons for decision

I reach this conclusion by reason of s 32 of the Act. That provision protects the contractual rights of parties. Relevantly in this case, that includes the right to arbitrate disputes which is provided for by the contract. The protections provided for by s 32 are broad. Section 32 provides that nothing done for the purposes of Part 3 affects any civil proceedings other than requiring a court or tribunal to allow for amounts paid to a party in making an order or award. It protects the rights a party may have under Part 2 (that is, the part providing for entitlements to claim progress payments) in respect of the contract. Consequently, use of the legislative provisions for recovering progress payments does not affect a party’s rights to claim entitlements in subsequent civil litigation. Equally, the existence of an entitlement to make claims in arbitration or litigation or the commencement of such does not preclude a party’s entitlement to claim progress payments under Part 2 of the Act. Conclusion For the reasons expressed above, I do not consider delay claims referable to EOT 001 and EOT 002 are properly characterised as a singular claim nor that the contract requires the inclusion of all components of such delay claim in one only progress payment claim. The failure to include all aspects of both in one payment claim is not relevantly an abuse of the processes of the Act. This is not a case in which GE-Elecnor has sought to proffer the prolongation and procurement premium claim on one basis and then re-agitate them on a different basis. It is also not a case in which GE-Elecnor sought to get a better outcome in the Second Adjudication Determination than it obtained in the First Adjudication Determination nor is it seeking to achieve a better outcome in the Third Adjudication Application insofar as it relates to procurement premium claims. Given my conclusions above, I dismiss the application and decline to grant relief insofar as the application related to the Second Adjudication Determination. The injunctive orders made in relation to the Second Adjudication Determination should be lifted. However, I accept that the Court has the power to grant orders in relation to the thickening costs claim aspect of the Third Adjudication Application based on the decisions to which I have referred above. I do not accept GE-Elecnor’s submission that any orders should await the outcome of the Third Adjudication Application for the same reason Hammerschlag J rejected such a contention in Cadence.[210] On the basis of decisions including Dualcorp[211] and Cadence,[212] the aspect of the payment claim relating to the thickening costs is invalid and consequently the adjudicator will lack jurisdiction to address it. [210] [2009] NSWSC 635 at [57]-[60].[211] [2009] NSWCA 69; (2009) 74 NSWLR 190[212] [2009] NSWSC 635. Goyder accepts the invalid part of the Third Payment Claim can be severed but submitted that any Third Adjudication Application is foredoomed because of Goyder’s claim for delay liquidated damages. During submissions, GE-Elecnor’s counsel accepted the quantum of liquidated damages determined in the Second Adjudication Determination. However, GE-Elecnor’s counsel did not expressly address Goyder’s submission concerning the impact of the liquidated damages claim in the context of any orders which may be made concerning the Third Adjudication Application. I am not in a position to form a view whether the Third Adjudication Application is foredoomed in its entirety such that I should make orders in relation to the Third Adjudication Application in its entirety. Consequently, I propose to make orders addressing only the aspect of the Third Payment Claim and Third Adjudication Application which relates to thickening costs claims. Orders

Ratio Decidendi

Legal principle established

I return to address the extent of overlap between claims below.Notice of arbitration On about 27 December 2023, GE-Elecnor issued a notice of arbitration and referred a dispute to arbitration claiming a total of $61,451,756.11 in delay costs pursuant to cl 13.11 of the contract in respect of GE-Elecnor’s EOT 001 and EOT 002 claims. Those amounts included amounts for prolongation costs of $7,554,516.01 and procurement premiums of $38,053,873.24 including an amount of $7,591,882.22 for “thickening”. Goyder included in its submissions a table setting out a comparison of the amounts claimed in the notice of arbitration and the amounts claimed in the payment claims as follows: Goyder contends the Second Adjudication Determination is fatally flawed on the following grounds:1.Section 22(4) of the Act.2.By reason of the prohibition on the re-agitation of claims in adjudications variously categorised as abuse of process, issue estoppel, res judicata, Anshun estoppel and/or adjudication estoppel.3.The Adjudicator lacked jurisdiction. Goyder challenged the validity of the Third Payment Claim insofar as it claimed delay costs. On Goyder’s case, the Third Payment Claim should be prohibited from proceeding to a Third Adjudication Determination. Goyder contends its grounds of challenge raise a number of issues as follows:1.whether, in making the Second Adjudication Determination, the Adjudicator made a jurisdictional error in failing to apply s 22(4) of the Act and thereby failing to give to the delay claim the same value as determined in the First Adjudication Determination; 2.whether the Second Payment Claim and/or the Second Adjudication Application was an abuse of process;3.whether providing an adjudication certificate under s 24 of the Act in respect of the Second Adjudication Determination or filing such a certificate under s 25 of the Act would be an abuse of process; and4.whether making the Third Payment Claim is an abuse of process.Overview of Goyder’s submissions Goyder contended the Adjudicator erred in the Second Adjudication Determination on the basis he:failed to exercise the task required of him by s 22(4) of the Act; andwrongfully permitted GE-Elecnor to re-agitate the claim for delay costs arising out of the alleged extension of time determined of 118 days. Goyder did not challenge the finding of the Adjudicator that GE-Elecnor is entitled to an EOT of 118 days which it will challenge in arbitration. For the purposes of these proceedings, Goyder accepted GE-Elecnor is entitled to an EOT of 91 days for EOT 001 for site access delay for Phase 3 permitted activities from 24 March to 23 August 2022 and 96 days, of which 69 were co-critical, for EOT 002 for site access delay for Phase 2 permitted activities from 7 March to 7 July 2022. Goyder did not challenge GE-Elecnor’s entitlement to seek recovery of alleged delay costs pursuant to the Act while an arbitration is proceeding. However, it contends that GE-Elecnor could and should have made the whole of the $61.4 million claim in the First Payment Claim instead of making successive payment claims, “picking off different line items on successive occasions and revising and recycling failed elements”.