SUPREME COURT OF SOUTH AUSTRALIA
(Civil: Judicial Review)
GOYDER WIND FARM 1 PTY LTD v GE RENEWABLE ENERGY AUSTRALIA PTY LTD & ORS
[2024] SASC 108
Judgment of the Honourable Justice Stein
CONTRACTS - BUILDING, ENGINEERING AND RELATED CONTRACTS - REMUNERATION - STATUTORY REGULATION OF ENTITLEMENT TO AND RECOVERY OF PROGRESS PAYMENTS - ADJUDICATION OF PAYMENT CLAIMS
CONTRACTS - GENERAL CONTRACTUAL PRINCIPLES - CONSTRUCTION AND INTERPRETATION OF CONTRACTS
STATUTES - ACTS OF PARLIAMENT - INTERPRETATION - GENERAL APPROACHES TO INTERPRETATION - TO GIVE OPERATION AND EFFECT TO ACT
ADMINISTRATIVE LAW - PREROGATIVE WRITS AND ORDERS - CERTIORARI - GROUNDS FOR CERTIORARI TO QUASH - EXCESS OR WANT OF JURISDICTION - PARTICULAR INSTANCES OF JURISDICTIONAL ERROR
PROCEDURE - STATE AND TERRITORY COURTS: JURISDICTION, POWERS AND GENERALLY - INHERENT AND GENERAL STATUTORY POWERS - TO PREVENT ABUSE OF PROCESS - ATTEMPTS TO RELITIGATE
ESTOPPEL - ESTOPPEL BY JUDGMENT - ISSUE ESTOPPEL - GENERAL PRINCIPLES
ESTOPPEL - ESTOPPEL BY JUDGMENT - ANSHUN ESTOPPEL - GENERALLY
Goyder Wind Farm 1 Pty Ltd, the applicant (“Goyder”), entered into contracts with GE Renewable Energy Australia Pty Ltd and Elecnor Australia Pty Ltd, the first and second respondents (“GE‑Elecnor”), for the construction of a windfarm.
GE-Elecnor has issued at different times three separate claims for progress payments relating to claimed entitlement to delay costs arising from a claimed an extension of time pursuant to the contract. Two of the claims have proceeded to adjudication determination pursuant to Building and Construction Industry Security of Payment Act 2009 (SA) (“the Act”). The third claim is currently enjoined from proceeding by interim orders made at the commencement of these proceedings.
Goyder applied for review of the second determination by the adjudicator and sought an order quashing that second determination in addition to orders preventing GE-Elecnor taking steps to enforce the determination and from taking steps to progress a third claim to adjudication.
Goyder submitted the adjudicator had erred in the second determination on the basis he failed to apply s 22(4) of the Act and wrongfully permitted GE-Elecnor to re-agitate the claim for delay costs.
GE-Elecnor submitted the various delay cost claims were different and there had been no impermissible re-agitation of claims as between the first and second determination and the third payment claim.
Held (dismissing the application insofar as it relates to the second adjudication determination):
1.The delay claims did not constitute a singular claim for construction work which would have been carried out in the extension of time period.
2.Section 22(4) of the Act did not apply. If it had applied, s 22(4) of the Act is not a matter of jurisdiction.
3.The prolongation and procurement premium delay cost claims did not overlap and it was not an abuse of the processes of the Act to claim those amounts in separate payment claims.
Held (allowing the application insofar as it relates to the thickening costs claim aspect of the third adjudication claim):
4.The thickening costs claim aspect of the claim is precluded by the legislation as an…
Keep reading for free
Create a free CaseChat account to read Goyder Wind Farm 1 Pty Ltd v Ge Renewable Energy Australia P... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Details
- Case
- [2024] SASC 108
- Decision Date
CaseChat Overview and Summary
The court's decision in Goyder Wind Farm 1 Pty Ltd v GE Renewable Energy Australia Pty Ltd demonstrates the importance of understanding the provisions of a contract and the applicable legislation when resolving disputes. The court found that the adjudicator had not made a jurisdictional error and that GE-Elecnor had not re-agitated its claim in a manner that amounted to an abuse of process. This decision highlights the importance of following the correct procedures when making claims and seeking adjudication. The court's decision also highlights the importance of understanding the limitations of the court's jurisdiction when resolving disputes. The court declined to grant relief in relation to the Second Adjudication Determination but made orders in relation to the thickening costs claim aspect of the Third Adjudication Application. This decision demonstrates the court's willingness to make orders that are within its jurisdiction while respecting the limitations of its role in resolving disputes.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence before the court
Decision
Reasons for decision
Ratio Decidendi
Legal principle established
I return to address the extent of overlap between claims below.Notice of arbitration On about 27 December 2023, GE-Elecnor issued a notice of arbitration and referred a dispute to arbitration claiming a total of $61,451,756.11 in delay costs pursuant to cl 13.11 of the contract in respect of GE-Elecnor’s EOT 001 and EOT 002 claims. Those amounts included amounts for prolongation costs of $7,554,516.01 and procurement premiums of $38,053,873.24 including an amount of $7,591,882.22 for “thickening”. Goyder included in its submissions a table setting out a comparison of the amounts claimed in the notice of arbitration and the amounts claimed in the payment claims as follows: Goyder contends the Second Adjudication Determination is fatally flawed on the following grounds:1.Section 22(4) of the Act.2.By reason of the prohibition on the re-agitation of claims in adjudications variously categorised as abuse of process, issue estoppel, res judicata, Anshun estoppel and/or adjudication estoppel.3.The Adjudicator lacked jurisdiction. Goyder challenged the validity of the Third Payment Claim insofar as it claimed delay costs. On Goyder’s case, the Third Payment Claim should be prohibited from proceeding to a Third Adjudication Determination. Goyder contends its grounds of challenge raise a number of issues as follows:1.whether, in making the Second Adjudication Determination, the Adjudicator made a jurisdictional error in failing to apply s 22(4) of the Act and thereby failing to give to the delay claim the same value as determined in the First Adjudication Determination; 2.whether the Second Payment Claim and/or the Second Adjudication Application was an abuse of process;3.whether providing an adjudication certificate under s 24 of the Act in respect of the Second Adjudication Determination or filing such a certificate under s 25 of the Act would be an abuse of process; and4.whether making the Third Payment Claim is an abuse of process.Overview of Goyder’s submissions Goyder contended the Adjudicator erred in the Second Adjudication Determination on the basis he:failed to exercise the task required of him by s 22(4) of the Act; andwrongfully permitted GE-Elecnor to re-agitate the claim for delay costs arising out of the alleged extension of time determined of 118 days. Goyder did not challenge the finding of the Adjudicator that GE-Elecnor is entitled to an EOT of 118 days which it will challenge in arbitration. For the purposes of these proceedings, Goyder accepted GE-Elecnor is entitled to an EOT of 91 days for EOT 001 for site access delay for Phase 3 permitted activities from 24 March to 23 August 2022 and 96 days, of which 69 were co-critical, for EOT 002 for site access delay for Phase 2 permitted activities from 7 March to 7 July 2022. Goyder did not challenge GE-Elecnor’s entitlement to seek recovery of alleged delay costs pursuant to the Act while an arbitration is proceeding. However, it contends that GE-Elecnor could and should have made the whole of the $61.4 million claim in the First Payment Claim instead of making successive payment claims, “picking off different line items on successive occasions and revising and recycling failed elements”.