EnerMech Pty Ltd v Acciona Infrastructure Projects Australia Pty Ltd

Link copied
Case Copied 54 min read

Court of Appeal


Supreme Court


New South Wales

  • Summary available
  • Amendment notes
Medium Neutral Citation: EnerMech Pty Ltd v Acciona Infrastructure Projects Australia Pty Ltd [2024] NSWCA 162
Hearing dates: 6 May 2024
Date of orders: 10 July 2024
Decision date: 10 July 2024
Before: Meagher JA at [1];
Basten AJA at [2];
Griffiths AJA at [89]
Decision:

(1)   Allow the appeal from the judgment in the Equity Division given on 14 December 2023.

(2)   Set aside orders 1, 2 and 5 entered on 15 December 2023 and in their place order that:

(a)   the amended summons dated 24 October 2023 be dismissed;

(b)   the plaintiffs pay the costs of the first defendant of the summons;

(c)   the first defendant pay the plaintiffs’ costs of the cross-summons.

(3)   Order that the first to third respondents pay the appellant an amount of $10,160,109.77, together with interest at 9.1% per annum from 7 July 2023 to the date of payment.

(4)   Order that the first to third respondents pay the appellant’s costs in this Court.

Catchwords:

BUILDING AND CONSTRUCTION – payment claim – validity – claim for payment due under construction contract – whether claim must be “for construction work” – purpose of claim to recover an amount obtained by respondents through recourse to bank guarantees provided by claimant – defence asserted in payment schedule – whether issue to be determined by adjudicator or Court

Legislation Cited:

Building and Construction Industry Security of Payment Act 1999 (NSW), ss 3, 4, 7, 8, 9, 10, 12, 13, 14, 15, 16, 20, 22, 25, 27, 34

Supreme Court Act 1970 (NSW), s 69

Cases Cited:

Brodyn Pty Ltd t/as Time Cost and Quality v Davenport & Anor (2004) 61 NSWLR 421; [2004] NSWCA 394

BSA Advanced Property Solutions (Fire) Pty Ltd v Ventia Australia Pty Ltd (2022) 108 NSWLR 350; [2022] NSWCA 82

Ceerose Pty Ltd v A-Civil Aust Pty Ltd (2023) 112 NSWLR 225; [2023] NSWCA 215

Chase Oyster Bar Pty Ltd v Hamo Industries Pty Ltd (2010) 78 NSWLR 393; [2010] NSWCA 190

Coordinated Construction Co Pty Ltd v J M Hargreaves (NSW) Pty Ltd (2005) 63 NSWLR 385; [2005] NSWCA 228

Grocon (Belgrave St) Developer Pty Ltd vConstruction Profile Pty Ltd [2020] NSWSC 409

Illawarra Retirement Trust v Denham Constructions Pty Ltd [2015] NSWSC 823

Nepean Engineering Pty Ltd v Total Process Services Pty Ltd (in liq) (2005) 64 NSWLR 462; [2005] NSWCA 409

Probuild Constructions (Aust) Pty Ltd v ShadeSystems Pty Ltd (2018) 264 CLR 1; [2018] HCA 4

Quasar Constructions NSW Pty Ltd v Demtech Pty Ltd (2004) 20 BCL 276; [2004] NSWSC 116

Sopov v Kane Constructions Pty Ltd (No 2) (2009) 24 VR 510; [2009] VSCA 141

Southern Han Breakfast Point Pty Ltd (in liq) v Lewence Construction Pty Ltd (2016) 260 CLR 340; [2016] HCA 52

Witron Australia Pty Ltd v Turnkey Innovative Engineering Pty Ltd [2023] NSWCA 305

Category:Principal judgment
Parties: EnerMech Pty…
CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read EnerMech Pty Ltd v Acciona Infrastructure Projects Australia... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Find similar cases

Other decisions on the same topics. Each opens in a new tab.

Details

Case
[2024] NSWCA 162
Decision Date

CaseChat Overview and Summary

EnerMech Pty Ltd (the claimant) sought payment from Acciona Infrastructure Projects Australia Pty Ltd (the respondent) under a construction contract. The dispute concerned a payment claim made by EnerMech, which Acciona argued was invalid. Acciona had recourse to bank guarantees provided by EnerMech, and EnerMech's payment claim sought to recover the amount obtained by Acciona through these guarantees. Acciona asserted a defence in its payment schedule, raising the question of whether the validity of the payment claim and the underlying dispute were matters for an adjudicator under the relevant legislation or for the court. The matter came before the Court of Appeal of New South Wales.

The primary legal issues before the Court of Appeal were: (1) whether EnerMech's payment claim was a valid claim for payment "for construction work" as required by the *Building and Construction Industry Security of Payment Act 1999* (NSW) (the Act); and (2) whether the court or an adjudicator had the jurisdiction to determine the validity of the claim and the dispute concerning the recourse to the bank guarantees.

The Court of Appeal allowed EnerMech's appeal, setting aside the previous orders of the Equity Division. The Court reasoned that the payment claim, although seeking to recover an amount obtained by recourse to bank guarantees, was nonetheless a claim for an amount due under the construction contract. The Court held that the Act was intended to provide a rapid mechanism for securing cash flow in the construction industry, and that the nature of the claim, as being for an amount due under the contract, was sufficient to engage the Act. The Court found that the question of whether the amount claimed was actually due was a matter for an adjudicator, not a preliminary jurisdictional question for the court.

Consequently, the Court of Appeal ordered that EnerMech's amended summons be dismissed, with specific orders regarding the costs of the summons and cross-summons. Crucially, the Court ordered that the respondents pay EnerMech the sum of $10,160,109.77, plus interest, and pay EnerMech's costs in the Court of Appeal.

Orders

Orders of the court

(1) Allow the appeal from the judgment in the Equity Division given on 14 December 2023.

(2) Set aside orders 1, 2 and 5 entered on 15 December 2023 and in their place order that:

(a) the amended summons dated 24 October 2023 be dismissed;

(b) the plaintiffs pay the costs of the first defendant of the summons;

(c) the first defendant pay the plaintiffs’ costs of the cross-summons.

(3) Order that the first to third respondents pay the appellant an amount of $10,160,109.77, together with interest at 9.1% per annum from 7 July 2023 to the date of payment.

(4) Order that the first to third respondents pay the appellant’s costs in this Court.

Background

Background to the litigation

Decision

Reasons for decision

Ratio Decidendi

Legal principle established