Court of Appeal
Supreme Court
New South Wales
- Summary available
- Amendment notes
Medium Neutral Citation: EnerMech Pty Ltd v Acciona Infrastructure Projects Australia Pty Ltd [2024] NSWCA 162 Hearing dates: 6 May 2024 Date of orders: 10 July 2024 Decision date: 10 July 2024 Before: Meagher JA at [1];
Basten AJA at [2];
Griffiths AJA at [89]Decision: (1) Allow the appeal from the judgment in the Equity Division given on 14 December 2023.
(2) Set aside orders 1, 2 and 5 entered on 15 December 2023 and in their place order that:
(a) the amended summons dated 24 October 2023 be dismissed;
(b) the plaintiffs pay the costs of the first defendant of the summons;
(c) the first defendant pay the plaintiffs’ costs of the cross-summons.
(3) Order that the first to third respondents pay the appellant an amount of $10,160,109.77, together with interest at 9.1% per annum from 7 July 2023 to the date of payment.
(4) Order that the first to third respondents pay the appellant’s costs in this Court.
Catchwords: BUILDING AND CONSTRUCTION – payment claim – validity – claim for payment due under construction contract – whether claim must be “for construction work” – purpose of claim to recover an amount obtained by respondents through recourse to bank guarantees provided by claimant – defence asserted in payment schedule – whether issue to be determined by adjudicator or Court
Legislation Cited: Building and Construction Industry Security of Payment Act 1999 (NSW), ss 3, 4, 7, 8, 9, 10, 12, 13, 14, 15, 16, 20, 22, 25, 27, 34
Supreme Court Act 1970 (NSW), s 69
Cases Cited: Brodyn Pty Ltd t/as Time Cost and Quality v Davenport & Anor (2004) 61 NSWLR 421; [2004] NSWCA 394
BSA Advanced Property Solutions (Fire) Pty Ltd v Ventia Australia Pty Ltd (2022) 108 NSWLR 350; [2022] NSWCA 82
Ceerose Pty Ltd v A-Civil Aust Pty Ltd (2023) 112 NSWLR 225; [2023] NSWCA 215
Chase Oyster Bar Pty Ltd v Hamo Industries Pty Ltd (2010) 78 NSWLR 393; [2010] NSWCA 190
Coordinated Construction Co Pty Ltd v J M Hargreaves (NSW) Pty Ltd (2005) 63 NSWLR 385; [2005] NSWCA 228
Grocon (Belgrave St) Developer Pty Ltd vConstruction Profile Pty Ltd [2020] NSWSC 409
Illawarra Retirement Trust v Denham Constructions Pty Ltd [2015] NSWSC 823
Nepean Engineering Pty Ltd v Total Process Services Pty Ltd (in liq) (2005) 64 NSWLR 462; [2005] NSWCA 409
Probuild Constructions (Aust) Pty Ltd v ShadeSystems Pty Ltd (2018) 264 CLR 1; [2018] HCA 4
Quasar Constructions NSW Pty Ltd v Demtech Pty Ltd (2004) 20 BCL 276; [2004] NSWSC 116
Sopov v Kane Constructions Pty Ltd (No 2) (2009) 24 VR 510; [2009] VSCA 141
Southern Han Breakfast Point Pty Ltd (in liq) v Lewence Construction Pty Ltd (2016) 260 CLR 340; [2016] HCA 52
Witron Australia Pty Ltd v Turnkey Innovative Engineering Pty Ltd [2023] NSWCA 305
Category: Principal judgment Parties: EnerMech Pty…
Keep reading for free
Create a free CaseChat account to read EnerMech Pty Ltd v Acciona Infrastructure Projects Australia... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Find similar cases
Other decisions on the same topics. Each opens in a new tab.
Details
- Case
- [2024] NSWCA 162
- Decision Date
CaseChat Overview and Summary
The primary legal issues before the Court of Appeal were: (1) whether EnerMech's payment claim was a valid claim for payment "for construction work" as required by the *Building and Construction Industry Security of Payment Act 1999* (NSW) (the Act); and (2) whether the court or an adjudicator had the jurisdiction to determine the validity of the claim and the dispute concerning the recourse to the bank guarantees.
The Court of Appeal allowed EnerMech's appeal, setting aside the previous orders of the Equity Division. The Court reasoned that the payment claim, although seeking to recover an amount obtained by recourse to bank guarantees, was nonetheless a claim for an amount due under the construction contract. The Court held that the Act was intended to provide a rapid mechanism for securing cash flow in the construction industry, and that the nature of the claim, as being for an amount due under the contract, was sufficient to engage the Act. The Court found that the question of whether the amount claimed was actually due was a matter for an adjudicator, not a preliminary jurisdictional question for the court.
Consequently, the Court of Appeal ordered that EnerMech's amended summons be dismissed, with specific orders regarding the costs of the summons and cross-summons. Crucially, the Court ordered that the respondents pay EnerMech the sum of $10,160,109.77, plus interest, and pay EnerMech's costs in the Court of Appeal.
Orders
Orders of the court
(1) Allow the appeal from the judgment in the Equity Division given on 14 December 2023.
(2) Set aside orders 1, 2 and 5 entered on 15 December 2023 and in their place order that:
(a) the amended summons dated 24 October 2023 be dismissed;
(b) the plaintiffs pay the costs of the first defendant of the summons;
(c) the first defendant pay the plaintiffs’ costs of the cross-summons.
(3) Order that the first to third respondents pay the appellant an amount of $10,160,109.77, together with interest at 9.1% per annum from 7 July 2023 to the date of payment.
(4) Order that the first to third respondents pay the appellant’s costs in this Court.
Background
Background to the litigation
Decision
Reasons for decision
Ratio Decidendi