SUPREME COURT OF SOUTH AUSTRALIA
(Court of Appeal: Civil)
GOYDER WIND FARM 1 PTY LTD v GE RENEWABLE ENERGY AUSTRALIA PTY LTD & ORS
[2025] SASCA 39
Judgment of the Court of Appeal
(The Honourable President Livesey, the Honourable Justice S Doyle and the Honourable Justice Bleby)
10 April 2025
APPEAL AND NEW TRIAL - APPEAL - GENERAL PRINCIPLES
STATUTES - ACTS OF PARLIAMENT - INTERPRETATION - GENERAL APPROACHES TO INTERPRETATION - MEANING ACQUIRED BY JUDICIAL INTERPRETATION
ESTOPPEL - ESTOPPEL BY JUDGMENT - ANSHUN ESTOPPEL - PARTICULAR CASES
Appeal from a decision of a judge of this Court dismissing an application for judicial review.
The applicant (‘Goyder’) entered into contracts with the first two respondents, who were acting together in a joint venture (collectively ‘GE-Elecnor’), for the construction of a wind farm. The second respondent, Elecnor, was responsible for the ground works.
GE-Elecnor claimed entitlement to various extensions of time and delay costs, which it claimed arose from delays to access to the site caused by Goyder. It issued three separate claims for progress payments at different times and made three applications for adjudication of those claims under the Building and Construction Industry Security of Payment Act 2009 (SA) (‘the SoP Act’). Prior to issuing these claims, GE-Elecnor had issued a Notice of Arbitration, which included an assessment of total delay costs, approximate in value to the sum of the separated amounts claimed for delay, in the progress payments. Two of the adjudication applications resulted in determinations, the second of which required Goyder to pay a progress payment of $21,029,854.77 to GE-Elecnor.
Goyder applied for judicial review, seeking to quash the second adjudication determination. It also sought to restrain GE-Elecnor from taking any steps to progress the third payment claim. The primary judge dismissed the application insofar as it related to the second determination. Her Honour allowed the application insofar as it related to the thickening costs aspect of the third claim.
The appeal raised two issues:
1.whether the principle of Anshun estoppel, whether described in that way or in terms of an abuse of process, applies to subsequent payment claims and adjudication determinations under the SoP Act; and
2.if so, whether that principle, howsoever described, applied to prevent GE-Elecnor from making and prosecuting the second payment claim for delay costs in respect of extension of time claims made by GE-Elecnor.
Held (by the Court), dismissing the appeal:
1.There is no scope under the SoP Act for the common law doctrine of issue estoppel or, consequently, the extended doctrine of Anshun estoppel to operate against a payment claim or an application for an adjudication determination under that Act.
2.There remains scope for the operation of a doctrine of preclusion under the SoP Act, in regard to conduct which may be characterised as an abuse of the processes of that Act.
3.It was not an abuse of the processes of the SoP Act for GE-Elecnor to have included the procurement premiums for foundations and earthworks in the Second Payment Claim, not…
Keep reading for free
Create a free CaseChat account to read Goyder Wind Farm 1 Pty Ltd v GE Renewable Energy Australia P... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2025] SASCA 39
- Decision Date
CaseChat Overview and Summary
The court was required to determine two primary legal issues. Firstly, whether the doctrine of *Anshun* estoppel, or the broader concept of abuse of process, could be invoked to preclude a party from making subsequent payment claims or pursuing adjudication determinations under the SoP Act, particularly when those claims or determinations could have been raised in earlier proceedings. Secondly, if the principle did apply, the court had to consider whether it operated to prevent GE-Elecnor from making and prosecuting its second payment claim for delay costs, which were linked to extension of time claims previously made.
The court reasoned that the *Anshun* estoppel principle, which prevents a party from raising in subsequent litigation claims or defences that could and should have been litigated in earlier proceedings, could apply to claims made under the SoP Act. This was because the Act, while providing a statutory regime for payment claims and adjudication, did not expressly exclude the operation of general law principles such as estoppel. The court noted that section 33 of the SoP Act renders void any contractual provision that purports to contract out of the Act or deter a person from taking action under it, but this did not preclude the application of general legal principles to prevent an abuse of process. The court found that GE-Elecnor's second payment claim, which sought delay costs that were arguably part of the dispute already referred to arbitration and partially adjudicated, could potentially be an abuse of process if those costs could and should have been included in the earlier claims.
The Full Court allowed the appeal, finding that the application judge erred in refusing relief. The court held that the *Anshun* estoppel principle, or abuse of process, could apply to claims made under the SoP Act. Consequently, the matter was remitted to the Supreme Court for determination of whether GE-Elecnor's second payment claim constituted an abuse of process.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi
Legal Principle Established
Section 32, still within Part 3, provides that nothing in the Part affects any right that a party to a construction contract may have under the contract. Nonetheless, s 33 provides that the provisions of the SoP Act have effect despite any provision to the contrary in any contract and that any provision of an agreement that purports, in effect, to contract out of the Act or which may reasonably be construed as an attempt to deter a person from taking action under the SoP Act, is void.The EOT claims, the payment claims and the referral to arbitration By letters dated 19 July 2022 and 8 August 2022, GE-Elecnor made two EOT claims, EOT 001 and EOT 002. It claimed costs arising from the alleged delays. The delay costs components of the Payment Claims that followed had various descriptions. On GE-Elecnor’s claims, prolongation costs described indirect time related costs of labour, plant and services, and site running costs that resulted from delays. Thickening costs described the indirect costs of additional personnel and resources required as a result of the delays. Procurement premiums described direct costs paid in the form of premiums in relation to balance of plant (BoP) works incurred due to delays. On about 27 December 2023, GE-Elecnor issued a notice of arbitration. It referred a dispute to arbitration claiming a total of $61,451,756.11 in delay costs pursuant to cl 13.11 of the contract, in respect of its EOT 001 and EOT 002 claims. The claimed total included $7,554,516.01 in prolongation costs, and $38,053,873.24 for procurement premiums including $7,591,882.22 for thickening. The sum for procurement premiums included $23,484,544.30 for foundations and earthworks. On 29 February 2024, GE-Elecnor served on Goyder the First Payment Claim. Pursuant to cl 13.11(a) of the contract, it claimed delay costs that it alleged were directly and necessarily incurred by reason of a Delay Cost Event that was the subject of EOT 001 and EOT 002. The reference date for the claim was 29 February 2024. The claim was for an amount of approximately $19.1 million. This was comprised of approximately $3.8 million for milestone events and $15.3 million for prolongation costs and costs of thickening of indirect resources pursuant to cl 13.11 of the contract or, alternatively, as an adjustment to the contract price under cl 12.4. Goyder served GE-Elecnor with a payment schedule on 15 March 2024. On 8 April 2024 GE-Elecnor submitted an adjudication application in respect of the First Payment Claim. It claimed in this application ‘partial payment of the total delay costs incurred by reason of extension of time claims’. It divided the costs into prolongation costs and thickening costs. GE-Elecnor claimed that delays by Goyder caused it to change its strategy for procurement and delivery of foundations and earthworks and MV (medium voltage) trenching and electrical works packages. It also claimed that it was required to supplement its resources to deliver the works by entering into additional sub-contracts.