Estate Property Holdings Pty Ltd v Barclay Mowlem Construction Ltd

Link copied
Case Copied 12 min read

Reported Decision:

61 NSWLR 515

Court of Appeal


CITATION: Estate Property Holdings Pty. Limited v. Barclay Mowlem Construction Limited [2004] NSWCA 393
HEARING DATE(S): 13 October 2004
JUDGMENT DATE:
3 November 2004
JUDGMENT OF: Mason P at 1; Giles JA at 2; Hodgson JA at 3
DECISION: Appeal dismissed with costs.
CATCHWORDS: BUILDING AND CONSTRUCTION - Progress payments - Building and Construction Industry Security of Payment Act - Progress claim - Meaning of "construction work to which the claim relates" - Whether it is the work required by the contract, the work for which payment is claimed, or each item of work for which payment is claimed
LEGISLATION CITED: Building and Construction Industry Security of Payment Act 1999 (NSW) ss.8, 13-15, 20
CASES CITED: Leighton Contractors Pty. Limited v. Campbelltown Catholic Club Limited [2003] NSWSC 1103

PARTIES :

Estate Property Holdings Pty. Limited - appellant
Barclay Mowlem Construction Limited - respondent
FILE NUMBER(S): CA 40600/04
COUNSEL: Mr. B. Coles QC with Mr. M. Ashhurst for appellant
Mr. M. Rudge SC with D. Meltz for respondent
SOLICITORS: Church & Grace, Sydney for appellant
Baker & McKenzie, Sydney for respondent
LOWER COURTJURISDICTION: Supreme Court - Equity Division
LOWER COURT FILE NUMBER(S): ED55042/04
LOWER COURT
JUDICIAL OFFICER :
Einstein J



                          CA 40600/04
                          ED 55042/04

                          MASON P
                          GILES JA
                          HODGSON JA

                          Wednesday 3 November 2004
ESTATE PROPERTY HOLDINGS PTY. LIMITED V. BARCLAY MOWLEM CONSTRUCTION LIMITED

HEADNOTE



      FACTS
      On 15 November 2002, Barclay entered into a design and construction contract with Estate for the construction by Barclay of four residential towers in Gosford.

      On 28 May 2004, Barclay served on Estate a document purporting to be a payment claim under s.13 of the Building & Construction Industry Security of Payment Act 1999 (the Act). The payment claim included, inter alia, a $1,606,561.50 claim for piling work, out of the total claim of $4,900,497.34. The piling work had been completed more than twelve months before service of the payment claim, raising the issue of whether s.13(4)(b) had been complied with.

      The primary judge noted three possible interpretations of s.13(4)(b): first, as requiring only that some work under the construction contract had been performed in the twelve month period; second, as requiring that some work for which payment was claimed in the payment claim had been performed in the twelve month period; and third, as requiring, in respect of each item for which payment was claimed, that some work had been performed in the twelve month period.

      The primary judge accepted the first of the three interpretations, consistent with his previous decision in Leighton Contractors Pty. Limited v. Campbelltown Catholic Club Limited [2003] NSWSC 1103.

      On appeal, the primary issue was whether the payment claim had been served in accordance with s.13(4) of the Act.

      (1) The second of the three interpretations of s.13(4)(b) is correct. Section 13(2)(a) requires that a payment claim identify the construction work for which payment is claimed in the claim, not merely the construction work as a whole that is being…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Estate Property Holdings Pty Ltd v Barclay Mowlem Constructi... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2004] NSWCA 393
Decision Date

CaseChat Overview and Summary

Estate Property Holdings Pty Ltd (the respondent) sought to recover progress payments from Barclay Mowlem Construction Ltd (the appellant) under the *Building and Construction Industry Security of Payment Act 2002* (NSW). The dispute concerned the interpretation of "construction work to which the claim relates" within the Act, specifically in relation to a progress claim made by the respondent. The matter came before the Court of Appeal of New South Wales.

The central legal issue before the Court of Appeal was to determine the correct interpretation of the phrase "construction work to which the claim relates" as used in the *Building and Construction Industry Security of Payment Act 2002* (NSW). This involved considering whether this phrase referred to the work required by the contract generally, the specific work for which payment was claimed, or each individual item of work for which payment was sought.

The Court of Appeal held that the phrase "construction work to which the claim relates" refers to the work for which payment is claimed. The Court reasoned that the purpose of the Act is to facilitate cash flow within the building and construction industry by providing a statutory mechanism for progress payments. To achieve this, a progress claim must clearly identify the work for which payment is sought, allowing the respondent to assess the claim and the claimant to understand what work has been valued. The Court dismissed the appeal, upholding the decision of the lower court. The appellant was ordered to pay the respondent's costs.

Orders

Orders of the court

Appeal dismissed with costs.

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established