SUPREME COURT OF THE AUSTRALIAN CAPITAL TERRITORY
Case Title: | St Hilliers Property Pty Limited v ACT Projects Pty Ltd and Simon Wilson | |
Citation: | [2017] ACTSC 177 | |
Hearing Dates: | 11 March 2016, 19 April 2016 and 26 May 2016, submissions received 31 May 2017. | |
DecisionDate: | Thursday 20 July 2017 | |
Before: | Walmsley AJ | |
Decision: | See [235]–[244] | |
Catchwords: | CONTRACTS – CONSTRUCTION AND INTERPRETATION OF CONTRACTS – Building, Engineering And Related Contracts – Remuneration – statutory regulation of entitlement to and recovery of progress payments – Building and Construction Industry (Security of Payment) Act 2009 (ACT) – payment claims – whether a payment claim had been served too late – whether a ‘reference date’ was a necessary prerequisite to its service, and was absent at the time of service – whether an adjudicator had delegated the preparation of his adjudication by having someone else prepare it ADMINISTRATIVE LAW – JUDICIAL REVIEW – Application For Leave To Appeal From Adjudication Decision Under The Building and Construction Industry (Security of Payment) Act 2009 (ACT) – Whether an adjudicator’s finding of waiver had been an error at law | |
Legislation Cited: | Building and Construction Industry (Security of Payment) Act 2009 (ACT) | |
Cases Cited: | Agricultural and Rural Finance Pty Ltd v Gardiner [2008] HCA 57; (2008) 238 CLR 570 Chase Oyster Bar Pty Ltd v Hamo Industries Pty Ltd [2010] NSWCA 190; 78 NSWLR 393 Dilosa v Latec Finance Pty Ltd (1968) 84 WN (NSW) Pt 1 557 Fernando v Medical Complaints Tribunal [2007] TASSC 44; 16 TAS R 237 Fulton Hogan Construction Pty Ltd v Brady Marine and Civil Pty Ltd [2015] ACTSC 384 Laing O’Rourke v H and M [2010] NSWSC 818 Minister for Aboriginal Affairs v Peko-Wallsend Ltd (1985) 162 CLR 24 Minister for Local Government v South Sydney City Council [2002] NSWCA 288; 55 NSWLR 381 O’Reilly v The Commissioners of the State Bank of Victoria (1982) 153 CLR 1 Pines Living Pty Limited v John O’Brien & Walton Construction Pty Limited [2013] ACTSC 156 R v Wallis (1949) 78 CLR 529 at 550 Southern Han Breakfast Point Pty Ltd v Lewence Construction Pty Ltd & Ors [2016] HCA 52; 91 ALJR 233 | |
Parties: | St Hilliers Property Pty Ltd (Appellant) ACT Projects Pty Ltd (First Respondent) Simon Wilson (Second Respondent) | |
Representation: | Counsel Mr D T Miller SC and Mr M Sheldon (Appellant) Mr J T Moffett (First Respondent) Mr M Orlov (Second Respondent) | |
| Solicitors Collin Biggers & Paisley (Appellant) Bradley Allen Love (First Respondent) CCS Legal Pty Ltd (Second Respondent) | ||
File Numbers: | SCA 59 of 2016 SC 363 of 2016 | |
Walmsley AJ:
Background to the Act
This litigation arises under the Building and Construction Industry (Security of Payment) Act 2009 (ACT) (the Act).
The Act provides a simple mechanism for…
Keep reading for free
Create a free CaseChat account to read St Hilliers Property Pty Limited v ACT Projects Pty Ltd and... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2017] ACTSC 177
- Decision Date
CaseChat Overview and Summary
The court examined whether the payment claim was served outside the statutory time frame and whether the absence of a 'reference date' at the time of service rendered the claim invalid. Additionally, it considered if the adjudicator had delegated the preparation of his adjudication decision, potentially undermining the validity of the decision. The court also assessed whether the adjudicator's finding of waiver constituted an error of law, which would affect the outcome of the adjudication.
The court found that the payment claim was not served too late, as the absence of a 'reference date' did not preclude its validity. Furthermore, it concluded that the adjudicator had not improperly delegated the preparation of the adjudication decision. Regarding the adjudicator's finding of waiver, the court determined that it was not an error of law. Consequently, the adjudicator's decision was upheld.
The court made several orders, including dismissing the application for leave to appeal the adjudicator's decision, and affirming the adjudicator's findings regarding the payment claim and waiver. The orders specified the timelines and conditions under which the progress payments were to be made, and provided for costs associated with the proceedings.
Orders
Orders of the court
See [235]–[244]
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi