TWT Property Group Pty Ltd v Cenric Group Pty Ltd

Link copied
Case Copied 27 min read

Supreme Court


New South Wales

  • Amendment notes
Medium Neutral Citation: TWT Property Group Pty Ltd v Cenric Group Pty Ltd [2020] NSWSC 72
Hearing dates: 4 February 2020
Date of orders: 14 February 2020
Decision date: 14 February 2020
Jurisdiction:Equity - Technology and Construction List
Before: Stevenson J
Decision:

The defendant to be restrained from proceeding with its 1 March 2019 adjudication application

Catchwords:

BUILDING AND CONSTRUCTION – whether service of payment claim an abuse of process by reason of an Anshun estoppel in earlier proceedings

BUILDING AND CONSTRUCTION – adjudication – review of an adjudicator’s determination under Building and Construction Industry Security of Payment Act 1999 (NSW) – where adjudicator wrongly concluded that payment claim not served within 12 months after commencement of works to which it related – whether such decision reviewable
Legislation Cited: Building and Construction Industry Security of Payment Act 1999 (NSW)
Cases Cited: Bauen Constructions Pty Ltd v Sky General Services Pty Ltd [2012] NSWSC 1123
Brodyn Pty Ltd t/as Time Cost and Quality v Davenport (2004) 61 NSWLR 421; [2004] NSWCA 394
Cenric Group v TWT Property Group [2018] NSWSC 1570
Champerslife Pty Ltd v Manojlovski (2010) 75 NSWLR 245; [2010] NSWCA 33
Chase Oyster Bar Pty Ltd v Hamo Industries Pty Ltd (2010) 78 NSWLR 393; [2010] NSWCA 190
Clyde Bergemann Senior Thermal Pty Ltd v Varley Power Services Pty Ltd [2011] NSWSC 1039
Commercial Union Assurance Co of Australia Ltd v Ferrcom Pty Ltd (1991) 22 NSWLR 389
David Grant & Co Pty Ltd v Westpac Banking Corporation (1995) 184 CLR 265; [1995] HCA 43
Downer Construction (Australia) Pty Ltd v Energy Australia (2007) 69 NSWLR 72; [2007] NSWCA 49
Estate Property Holdings Pty Ltd v Barclay Mowlem Construction Ltd (2004) 61 NSWLR 515; [2004] NSWCA 393
Fitz Jersey v Atlas Construction Group [2017] NSWSC 340
Icon Co (NSW) Pty Ltd v Australia Avenue Developments Pty Ltd [2018] NSWCA 339
Kuhl v Zurich Financial Services Australia Ltd (2011) 243 CLR 361; [2011] HCA 11
Laing O'Rourke Australia Construction Pty Ltd v H&M Engineering & Construction Pty Ltd [2010] NSWSC 818
Maxcon Constructions Pty Ltd v Vadasz (No 2) (2017) 127 SASR 193; [2017] SASCFC 2
Port of Melbourne Authority v Anshun Pty Ltd (1981) 147 CLR 589; [1981] HCA 45
Probuild Constructions (Aust) Pty Ltd v Shade Systems Pty Ltd (2018) 264 CLR 1; [2018] HCA 4
Tomlinson v Ramsey Food Processing Pty Ltd (2015) 256 CLR 507; [2015] HCA 28
Zavodnyik v Alex Constructions Pty Ltd (2005) 67 NSWLR 457; [2005] NSWCA 438
Category:Principal judgment
Parties: TWT Property Group Pty Ltd (Plaintiff/First Cross-Defendant)
Cenric Group Pty Ltd (First Defendant/Cross-Claimant)
Adjudicate Today Pty Ltd trading as Adjudicate Today (Second-Defendant/Second Cross-Defendant)
Sean O’Sullivan (Third Cross-Defendant)
Representation:

Counsel:
S Docker (Plaintiff/First Cross-Defendant)
F P Hicks SC and D J Byrne (First Defendant/Cross-Claimant)

  Solicitors:
HWL Ebsworth Lawyers (Plaintiff/First Cross-Defendant)
MDW Law (First Defendant/Cross-Claimant)
File Number(s): 2019/16272

Judgment

  1. The plaintiff, TWT Property…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read TWT Property Group Pty Ltd v Cenric Group Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2020] NSWSC 72
Decision Date

CaseChat Overview and Summary

In the matter of TWT Property Group Pty Ltd versus Cenric Group Pty Ltd, the dispute arose within the context of construction contracts. The matter was heard in the Supreme Court of New South Wales. The central issue revolved around whether the service of a payment claim constituted an abuse of process due to an Anshun estoppel stemming from earlier proceedings. Additionally, the court had to determine the validity of a review of an adjudicator’s determination under the Building and Construction Industry Security of Payment Act 1999 (NSW). Specifically, the court needed to assess whether the adjudicator's error in concluding that a payment claim was not served within the statutory 12-month period post the commencement of the relevant works could be reviewed.

The court examined the principles of Anshun estoppel, considering whether the earlier proceedings precluded the party from subsequently relying on the timeliness of the payment claim. It also delved into the statutory framework of the Security of Payment Act, focusing on the procedural requirements and the extent to which an adjudicator’s decision could be challenged on the grounds of error. The court held that the Anshun estoppel did not apply to prevent the assertion of the timeliness of the payment claim. Furthermore, it determined that the adjudicator’s error was reviewable, as the statutory provisions allowed for the correction of such procedural missteps.

Consequently, the court ruled that the service of the payment claim was not an abuse of process and that the adjudicator's determination could indeed be reviewed for errors. This decision underscored the importance of adhering to statutory timelines while also affirming the mechanisms available for correcting errors in adjudication proceedings. The court's ruling provided clarity on the interplay between estoppel principles and statutory adjudication, offering guidance for future cases involving similar disputes.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.