CITATION: Property & Equity Developments v Parnell [2004] NSWSC 1035 HEARING DATE(S): 2 November 2004 JUDGMENT DATE:
12 November 2004JURISDICTION:
EquityJUDGMENT OF: Campbell J DECISION: Payment claim valid CATCHWORDS: BUILDING, ENGINEERING AND RELATED CONTRACTS - remuneration - Building and Construction Industry Security of Payment Act 1999 - when payment claim may be served - time when "the construction work to which the claim relates was last carried out", within meaning of section 13(4)(b) LEGISLATION CITED: Building and Construction Industry Security of Payment Act 1999 CASES CITED: Estate Property Holdings Pty Limited v Barclay Mowlem Construction Limited [2004] NSWCA 393 PARTIES :
Property & Equity Developments Pty Ltd - Plaintiff
John Parnell - First Defendant
Bowdens Group Australia Pty Ltd - Second DefendantFILE NUMBER(S): SC 4275/04 COUNSEL: D M Loewenstein - Plaintiff
Submitting appearance - First Defendant
C Harris - Second DefendantSOLICITORS: R J Thomas - Plaintiff
Submitting appearance - First Defendant
Matthews Folbigg Pty Ltd - Second Defendant
IN THE SUPREME COURT
OF NEW SOUTH WALES
EQUITY DIVISION
EQUITY LIST
CAMPBELL J
12 NOVEMBER 2004
4275/04 PROPERTY & EQUITY DEVELOPMENTS PTY LTD v JOHN PARNELL & ANOR
JUDGMENT
1 HIS HONOUR: The plaintiff asks the Court to quash an adjudication determination which the first defendant made on 18 July 2004 under the Building and Construction Industry Security of Payment Act 1999 (“the BACISOP Act”). The plaintiff also asks that the second defendant be prevented from taking any steps to enforce that adjudication determination.
The Events Leading to this Litigation
2 The second defendant is a development consultant whose field of work includes providing design and engineering services concerning systems for controlling stormwater and floodwater. It was engaged by the plaintiff to carry out work of that type concerning a proposed home unit development at 140-148 Beattie Street, Balmain.
3 The second defendant submitted various invoices to the plaintiff for work done concerning that project. Amongst them were invoices dated 1 April 2003, 1 May 2003, 27 August 2003, and 11 December 2003. The plaintiff paid part only of the invoice dated 1 April 2003, and did not pay the remaining three invoices at all.
4 On 1 June 2004 the second defendant served on the plaintiff a document purporting to be a payment claim under the BACISOP Act. It identified the project as “provision of survey and engineering services for 140-148 Beattie Street Balmain” and claimed an amount of $128,467.02. It identified that amount as made up of the unpaid portion of the invoice dated 1 April 2003, of the invoices dated 1 May 2003, 27 August 2003 and 11 December 2003, and interest at the rate of 60% per annum on the unpaid part of each invoice, calculated from the date when the second defendant asserted that invoice had become due.
5 On 17 June 2004 the second defendant served on the plaintiff a notice under section 17(2) of the BACISOP Act.
6 On 8 July 2004 the first defendant, Mr Parnell,…
Continue reading Property and Equity Developments v Parnell
Sign in free to access the full text
- AGLC
- Property and Equity Developments v Parnell [2004] NSWSC 1035
- Case
- [2004] NSWSC 1035
- Decision Date
CaseChat Overview and Summary
The court was required to determine the precise moment when the construction work in question was considered complete, in order to ascertain whether the payment claim was served within the required timeframe. The key issue was whether the work was completed when the final physical activity was performed or when the work was deemed complete in accordance with the contract terms. Additionally, the court had to consider whether the payment claim was served within the statutory period from the last day of the relevant work.
The court examined the relevant provisions of the Act and the contract between the parties. It found that the construction work was completed when it was reasonably considered finished, in line with the contract terms, rather than the final physical activity. The court held that the payment claim was served within the statutory period, as it was submitted within the required timeframe from the date the work was considered complete under the contract. Consequently, the court ruled in favour of the subcontractor, determining that the payment claim was valid and that the principal contractor was obligated to make the payment.
The court ordered the principal contractor to pay the subcontractor the amount claimed, along with interest and costs as per the provisions of the Act. This decision underscores the importance of adhering to the statutory timelines and contractual obligations when serving payment claims in the building and construction industry.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.