Seymour Whyte Constructions Pty Ltd v Ostwald Bros Pty Ltd (in liq)
[2019] NSWCA 11
•12 February 2019
Court of Appeal
Supreme Court
New South Wales
- Summary available
- Amendment notes
Medium Neutral Citation: Seymour Whyte Constructions Pty Ltd v Ostwald Bros Pty Ltd (In liquidation) [2019] NSWCA 11 Hearing dates: 29 and 30 October 2018 Decision date: 12 February 2019 Before: Leeming JA at [1];
Payne JA at [44];
White JA at [45];
Sackville AJA at [46];
Emmett AJA at [262].Decision: 1. Direct the parties to file agreed short minutes of order within fourteen days giving effect to these reasons for judgment and dealing with the costs of the proceedings in this Court and the Equity Division.
2. To the extent that there is disagreement as to the proposed short minutes of order or costs, direct Seymour to file and serve its proposed short minutes of order (including on costs), together with written submissions in support (not to exceed five pages) within fourteen days.
3. Ostwald to file and serve its proposed short minutes of order (including on costs), together with written submissions in support (not exceeding five pages) within a further fourteen days.Catchwords: EQUITY – rectification of building contract – whether adjudication application under the Building and Construction Industry Security of Payment Act 1999 (NSW) (Security of Payment Act) made within time – answer depends on the date under the contract for the making of a progress payment – whether the primary Judge was correct to order rectification of the contract by changing the due date for payment – whether the evidence supported the finding that the parties had a common intention, at the time the contract was executed, that the date for payment should be otherwise than as recorded in the contract.
BUILDING AND CONSTRUCTION – adjudication application invalid because made out of time – whether the contractor entitled to institute summary proceedings under s 16(2)(a)(i) of the Security of Payment Act to recover unpaid portion of the scheduled amount as a debt – whether adjudication application, although a nullity, had a factual existence that had legal consequences – whether the invalid adjudication constituted an election between inconsistent statutory remedies so as to preclude summary proceedings to recover the debt.
BUILDING AND CONSTRUCTION - contractor in liquidation – whether the Security of Payment Act, as a matter of construction, is capable of operating for the benefit of a contractor which has gone into liquidation in insolvency – where Façade Treatment Engineering Pty Ltd (in liq) v Brookfield Multiplex Constructions Pty Ltd [2016] VSCA 247; (2016) 337 ALR 452 decides that equivalent Victorian legislation is not available to a contractor in liquidation – whether Victorian Court of Appeal decision is clearly wrong and should not be followed.Legislation Cited: Bankruptcy Act 1966 (Cth)
Corporations Act 2001 (Cth)
Judiciary Act 1903 (Cth)Corporations Regulations 2001 (Cth)
Building and Construction Industry Security of Payment Act 1999 (NSW)
Building and Construction Industry Security of Payment Act 2002 (Vic)
Building and Construction Industry Security of Payment Amendment Act 2002 (NSW)
Building and Construction Industry Security of Payment Amendment Act 2013 (NSW)
Interpretation Act 1987 (NSW)
Supreme Court Act 1970 (NSW)
Interpretation of Legislation Act 1984 (Vic)Cases Cited: Agricultural and Rural Finance Pty Ltd v Gardiner (2008) 238 CLR 570; [2008] HCA 57
Alqudsi v Commonwealth of Australia (2015) 91 NSWLR 92; [2015] NSWCA 351
Arnold v Britton [2015] AC 1619; [2015] UKSC 36
Australian Gypsum Ltd v Hume Steel Ltd (1930) 45 CLR 54; [1930] HCA 38
Bell Group NV (in liq) v Western Australia (2016) 260 CLR 500; [2016] HCA 21
Brodyn Pty Ltd v Dasein Constructions Pty Ltd [2004] NSWCA 1230
Cardinal Project Services Pty Ltd v Hanave Pty Ltd (2011) 81 NSWLR 716; [2011] NSWCA 399
Chartbrook Ltd v Persimmon Homes Ltd [2009] AC 1101; [2009] UKHL 38
Chase Oyster Bar Pty Ltd v Hamo Industries Pty Ltd (2010) 78 NSWLR 393; [2010] NSWCA 190
Cherry v Steele-Park (2017) 96 NSWLR 548; [2017] NSWCA 295
Duncan v New South Wales (2015) 255 CLR 388; [2015] HCA 13
Façade Treatment Engineering Pty Ltd (in liq) v Brookfield Multiplex Constructions Pty Ltd [2016] VSCA 247; (2016) 337 ALR 452
Falgat Constructions Pty Ltd v Equity Australia Corporation Ltd (2005) 62 NSWLR 385; [2005] NSWCA 49
Farah Constructions Pty Ltd v Say-Dee Pty Ltd (2007) 230 CLR 89; [2007] HCA 22
Fitzgerald v Masters (1956) 95 CLR 420; [1956] HCA 53
Fowler v Fowler (1859) 4 De G&J 250; 45 ER 97
Fox Entertainment Precinct Pty Ltd v Centennial Park and Moore Park Trust [2004] NSWSC 214; (2004) 11 BPR 21,629
Franklins Pty Ltd v Metcash Trading Ltd (2009) 76 NSWLR 603; [2009] NSWCA 407
Gammage v The Queen (1969) 122 CLR 444; [1969] HCA 68
GJ Coles & Co Ltd v Retail Trade Industrial Tribunal (1986) 7 NSWLR 503
Greenaways Australia Pty Ltd v CBC Management Pty Ltd [2004] NSWSC 1186
Grosvenor Constructions (NSW) Pty Ltd (in administration) v Musico [2004] NSWSC 344
Gye v McIntyre (1991) 171 CLR 609; [1991] HCA 60
Harris v Smith [2008] NSWSC 545
Hiley v Peoples Prudential Assurance Co Ltd (1938) 60 CLR 468; [1938] HCA 40
J Cummins Pty Ltd v F & D Bonaccorso [2015] NSWCA 200
JLF Bakeries Pty Ltd (in liq) v Baker’s Delight Holdings Ltd [2007] NSWSC 894; 64 ASCR 633
Kell & Rigby Pty Ltd v Guardian International Properties Pty Ltd [2007] NSWSC 554
Knight v Victoria (2017) 261 CLR 306; [2017] HCA 29
Kuru v State of New South Wales (2008) 236 CLR 1; [2008] HCA 26
Lambert v Weichelt (1954) 28 ALJ 282
Lavender v Director of Fisheries Compliance, Department of Industry Skills and Regional Development [2018] NSWCA 174
Lazarus v Independent Commission Against Corruption (2017) 94 NSWLR 36; [2017] NSWCA 37
Leung v Minister for Immigration and Multicultural Affairs (1997) 79 FCR 400; [1997] FCA 1313
Mainteck Services Pty Ltd v Stein Heurtey SA (2014) 89 NSWLR 633; [2014] NSWCA 184
Maralinga Pty Ltd v Major Enterprises Pty Ltd (1973) 128 CLR 336; [1973] HCA 23
Marley v Rawlings [2015] AC 129; [2014] UKSC 2
McHugh Holdings Pty Ltd v Newtown Colonial Hotel Pty Ltd (2008) 73 NSWLR 53; [2008] NSWSC 542
Minister for Immigration and Ethnic Affairs v Bhardwaj (2002) 209 CLR 597; [2002] HCA 11
Miwa Pty Ltd v Siantan Properties Pte Ltd [2011] NSWCA 297
Mobis Parts Australia Pty Ltd v XL Insurance Company SE [2018] NSWCA 342
National Australia Bank Ltd v Clowes [2013] NSWCA 179; 8 BFRA 600
New South Wales v Kable (2013) 252 CLR 118; [2013] HCA 26
Newey v Westpac Banking Corporation [2014] NSWCA 319
Paul Michael Pty Ltd v Urban Traders Pty Ltd [2010] NSWSC 1246
Pelechowski v The Registrar, Court of Appeal (1999) 198 CLR 435; [1999] HCA 19
Petelin v Cullen (1975) 132 CLR 355
Pink Floyd Music Ltd v EMI Records Ltd [2010] EWCA Civ 1429
Plaintiff S297/2013 v Minister for Immigration and Border Protection (2015) 255 CLR 231; [2015] HCA 3
Probuild Constructions (Aust) Pty Ltd v Shade Systems Pty Ltd [2018] HCA 4; (2018) 351 ALR 225
Pukallus v Cameron (1982) 180 CLR 447; [1982] HCA 63
Quasar Constructions NSW Pty Ltd v Demtech Pty Ltd [2004] NSWSC 116; 20 BCL 276
RJ Neller Building Pty Ltd v Ainsworth [2009] 1 Qd R 390
Rojo Building Pty Ltd v Jillcris Pty Ltd [2007] NSWSC 880
Romaldi Constructions Pty Ltd v Adelaide Interiors Linings Pty Ltd (No 2) [2013] SASCFC 124
Ryledar Pty Ltd v Euphoric Pty Ltd (2007) 69 NSWLR 603; [2007] NSWCA 65
Samm Property Holdings Pty Ltd v Shaye Properties Pty Ltd, [2017] NSWCA 132; 345 ALR 633
Sargent v ASL Developments Ltd (1974) 131 CLR 634 at 641; [1974] HCA 40
Seymour Whyte Constructions Pty Ltd v Ostwald Bros Pty Ltd (in liq) [2018] NSWSC 412
Seymour Whyte Constructions Pty Ltd v Ostwald Bros Pty Ltd (in liquidation) [2018] NSWCA 139
Seymour Whyte Constructions Pty Ltd v Ostwald Bros Pty Ltd (in liq) (No 2) unrep, 20 April 2018
Shellbridge Pty Ltd v Rider Hunt Sydney Pty Ltd [2005] NSWSC 1152
Silvia v Brodyn Pty Ltd [2007] NSWCA 55
Simic v New South Wales Land and Housing Corporation (2016) 260 CLR 85; [2016] HCA 47
Southern Han Breakfast Point Pty Ltd (in liq) v Lewence Construction Pty Ltd (2016) 260 CLR 340; [2016] HCA 52
Sparks v Hobson; Gray v Hobson [2018] NSWCA 29; 361 ALR 115
Sportsbet Pty Ltd v New South Wales (2012) 249 CLR 298; [2012] HCA 13
State of New South Wales v Kable (2013) 252 CLR 118; [2013] HCA 26
Toll (FGCT) Pty Ltd v Alphapharm Pty Ltd (2004) 219 CLR 165; [2004] HCA 52
United Telecasters Sydney Ltd v Hardy (1991) 23 NSWLR 323
Veolia Water Solutions v Kruger Engineering (No 3) [2007] NSWSC 459
Warren v Coombes (1979) 142 CLR 531; [1979] HCA 9
Wilson v Wilson (1854) 5 HL Cas 40; 10 ER 811
Wyllie v Tarrison Pty Ltd [2007] NSWCA 184Texts Cited: D Hodge QC, Rectification: The Modern Law and Practice Governing Claims for Rectification for Mistake (2nd ed, Sweet & Maxwell, 2016)
F Dawson, “Interpretation and Rectification of Written Agreements in the Commercial Court” (2015) 131 LQR 344
MGR Gronow and S Maiden, McPherson’s Law of Company Liquidation, 5th ed Thomson Reuters
P Davies, “Rectification versus Interpretation: The Nature and Scope of the Equitable Jurisdiction” [2016] CLJ 62
Review of Security of Payment Laws (December 2017)Category: Principal judgment Parties: Seymour Whyte Constructions Pty Ltd (Appellant)
Ostwald Bros Pty Ltd (In liquidation) (First Respondent)
Doron Rivlin (Second Respondent)
Adjudicate Today Pty Limited (Third Respondent)Representation: Counsel:
Solicitors:
Mr M Christie SC / Mr D Hume (Appellant)
Mr S Robertson / Mr AW Smith (First Respondent)
Submitting appearance (Second and Third Respondents)
K&L Gates (Appellant)
King & Wood Mallesons (First Respondent)
Dentons Australia (Second and Third Respondents)
File Number(s): 2018/136405 Decision under appeal
- Court or tribunal:
- Supreme Court of New South Wales
- Jurisdiction:
- Equity – Technology and Construction List
- Citation:
- [2018] NSWSC 412
- Date of Decision:
- 05 April 2018
- Before:
- Stevenson J
- File Number(s):
- 2017/348623
HEADNOTE
[This headnote is not to be read as part of the decision]
These proceedings arose out of a claim for progress payments under a Works Contract between the appellant (Seymour) as Contractor and the first respondent (Ostwald) as Subcontractor. Ostwald agreed on specified terms to perform road works on the Pacific Highway. The head contractor was the New South Wales Roads and Maritime Services.
Ostwald served a progress payment claim on Seymour for $6,351,066.08 pursuant to s 13(1) of the Building and Construction Security of Payment Act 1999 (NSW) (Security of Payment Act). Seymour responded by providing a payment schedule pursuant to s 14 of the Security of Payment Act, stating that it proposed to pay $2,505,237.58 as a progress payment (Scheduled Amount).
Ostwald then purported to make an adjudication application under s 17(2)(a)(ii) of the Security of Payment Act (Adjudication Application). An Adjudication subsequently determined that the amount due to Ostwald was $5,074,218.27 (Adjudication Amount).
Seymour commenced proceedings in the Equity Division claiming that the Adjudication Determination was invalid because Ostwald made the Adjudication Application outside the time limit specified by the Security of Payment Act. Ostwald filed a cross-claim seeking rectification of the Works Contract to alter the dates on which Seymour was required to make progress payments. It was common ground that if the claim for rectification succeeded, Ostwald’s Adjudication Application was made within the time prescribed by the Security of Payment Act, but if the Works Contract was not rectified the Adjudication Application had been made out of time and the Adjudication Determination was invalid.
In the alternative Ostwald claimed the unpaid Scheduled Amount of $2,505,237.58 as a statutory debt pursuant to s 16(2)(a)(i) of the Security of Payment Act.
After the proceedings commenced the creditors of Ostwald resolved pursuant to s 439C(c) of the Corporations Act, that it should be wound up.
The primary Judge held that:
(i) rectification should be ordered and therefore the Adjudication Determination was valid;
(ii) if, contrary to (i), the Adjudication Determination was invalid Ostwald could seek recovery of the Scheduled Amount in summary proceedings as a debt due to it pursuant to s 16(2)(a)(i) of the Security of Payment Act;
(iii) the Security of Payment Act continued to apply notwithstanding that the winding up of Ostwald had commenced;
(iv) but the Court had no option except to stay any judgment obtained by Ostwald following the Adjudication Determination until the parties’ rights were determined in the liquidation by an account of their mutual dealings pursuant to s 553C of the Corporations Act 2001 (Cth).
On the appeal, the issues were:
(i) whether the primary Judge erred in rectifying the Works Contract so as to alter the due date for payment (with the consequence that Ostwald’s Adjudication Application was made within time);
(ii) if yes to (i), whether Ostwald was precluded from suing to recover the unpaid amount pursuant to s 16(2)(a)(i) of the Security of Payment Act, Ostwald having purported to make an Adjudication Application under s 16(2)(a)(ii), albeit out of time;
(iii) if no to (ii), was the Act as a matter of construction incapable of applying to a builder or subcontractor which had gone into liquidation in insolvency, as was held by the Victorian Court of Appeal in Façade Treatment Engineering Pty Ltd (in liq) v Brookfield Multiplex Constructions Pty Ltd [2016] VSCA 247; 337 ALR 452.
The Court, allowing the appeal, held (per Sackville AJA, Leeming, Payne, White JJA and Emmett AJA agreeing):
(i) The primary Judge erred in finding that the common intention of the parties on the date of execution of the Works Contract was that Seymour should have 30 days from the end of the relevant month in which to pay Ostwald, rather than an earlier date specified in the Works Contract. The Adjudication Application was therefore served out of time and the Adjudication Determination was invalid.
Simic v New South Wales Land and Housing Corporation (2016) 260 CLR 85; [2016] HCA 47 applied.
(ii) The Adjudication Determination being invalid, Ostwald was entitled to seek recovery of the Scheduled Amount pursuant to s 16(2)(a)(i) of the Security of Payment Act. Although the Act provided alternative remedies for a claimant, the making of an invalid Adjudication Application did not preclude Ostwald from pursuing the summary statutory alternative available to it.
New South Wales v Kable (2013) 252 CLR 118; [2013] HCA 26 at [52] (Gageler J) followed.
(iii) An entitlement to a progress payment under s 8(1) of the Security of Payment Act does not depend on the claimant actually continuing to perform work under a contract. Accordingly, notwithstanding the winding up of Ostwald, the Security of Payment Act continued to apply to its claim and it was entitled to pursue its claim for the Scheduled Amount to judgment.
Façade Treatment Engineering Pty Ltd (in liq) v Brookfield Multiplex Constructions Pty Ltd [2016] VSCA 247; (2016) 337 ALR 452 not followed.
Judgment
-
LEEMING JA: I agree with Sackville AJA’s reasons and proposed orders. What follows is by way of elaboration rather than qualification, expanding on the questions of principle arising under the Building and Construction Industry Security of Payment Act 1999 (NSW) in this capably argued appeal and cross-appeal. I shall use the same abbreviations and assume familiarity with the matters contained in his Honour’s judgment.
-
The dispositive issues, as refined during the hearing, were:
did the primary judge err in rectifying the Contract so as to alter the due date for payment (with the consequence that Ostwald’s Adjudication Application was made within time)?
if yes to (1), then was Ostwald precluded from suing to recover the unpaid amount pursuant to s 16(2)(a)(i), Ostwald having purported to make an adjudication application under s 16(2)(a)(ii), albeit out of time?
if no to (2), then was the Act as a matter of construction incapable of applying to a builder or subcontractor which had gone into liquidation in insolvency, as had been held in Façade Treatment Engineering Pty Ltd (in liq) v Brookfield Multiplex Constructions Pty Ltd [2016] VSCA 247; 337 ALR 452?
Should the Contract have been rectified?
-
As Sackville AJA explains, there were internal inconsistencies in the contractual documentation, including in two bespoke provisions directed to the time for payment. Special Condition 9.1 required payment within 15 business days, while Item 21 of the Particulars required (because of the way its boxes had been filled out) payment within 30 days of the end of the month of claim. Although the Contract gave priority to the Special Conditions, there is some force in the proposition that the something had gone awry in Special Condition 9.1 and Item 21.
-
Before the primary judge, Ostwald had contended both for rectification in equity, and also as a matter of construction, but with the emphasis heavily on the former. His Honour ordered rectification in equity, and did not address the submissions on construction.
-
Sometimes it is clear on the face of a written contract that something has gone wrong with the language. In such cases, two quite different approaches may, in principle, be available as a matter of Australian law. It is vital to distinguish between the doctrines at common law and in equity.
Rectification by construction
-
At common law, if the error is clear, and it is also clear what a reasonable person would have understood the parties to have meant, then the mistake may be corrected as a matter of construction. This is old law. Lord St Leonards said in Wilson v Wilson (1854) 5 HL Cas 40 at 66-67; 10 ER 811 at 822:
“Now it is a great mistake if it is supposed that even a Court of Law cannot correct a mistake, or error, on the face of an instrument: there is no magic in words. If you find a clear mistake, and it admits of no other construction, a Court of Law, as well as a Court of Equity, without impugning any doctrine about correcting those things which can only be shown by parol evidence to be mistakes - without, I say, going into those cases at all, both Courts of Law and of Equity may correct an obvious mistake on the face of an instrument without the slightest difficulty.”
-
Examples may be found in linguistic errors, such as “inconsistent” being read as “consistent” in Fitzgerald v Masters (1956) 95 CLR 420; [1956] HCA 53, or conceptual errors, such as “lessor” being read as “lessee” in McHugh Holdings Pty Ltd v Newtown Colonial Hotel Pty Ltd (2008) 73 NSWLR 53; [2008] NSWSC 542. The language of a contract is not read like a computer program, such that any slip is fatal.
-
Two conditions are necessary in order to correct the contractual language in this manner: (a) that the literal meaning of the contractual words is an absurdity and (b) that it is self-evident what the objective intention is to be taken to have been: see Mainteck Services Pty Ltd v Stein Heurtey SA (2014) 89 NSWLR 633; [2014] NSWCA 184 at [117]-[119], approving National Australia Bank Ltd v Clowes [2013] NSWCA 179; 8 BFRA 600, where it was stated at [34]:
“Where both those elements are present ... ordinary processes of contractual construction displace an absurd literal meaning by a meaningful legal meaning.”
-
Likewise, in the United Kingdom, the court must be satisfied both as to the mistake and the nature of the correction: Pink Floyd Music Ltd v EMI Records Ltd [2010] EWCA Civ 1429 at [21] (Lord Neuberger); Arnold v Britton [2015] AC 1619; [2015] UKSC 36 at [78] (Lord Hodge).
-
The court must be satisfied of those matters to a high level of conviction. To use the language of Dixon CJ and Fullagar J in Fitzgerald v Masters at 426-427, it must be “clearly necessary in order to avoid absurdity or inconsistency”. As this Court said in Miwa Pty Ltd v Siantan Properties Pte Ltd [2011] NSWCA 297 at [18], the test of absurdity is not easily satisfied. Any question of absurdity or inconsistency must be identified according to established principles, by reference to the text of the agreement as understood in its factual and legal context: Wyllie v TarrisonPty Ltd [2007] NSWCA 184 at [46]; Newey v Westpac Banking Corporation [2014] NSWCA 319 at [85]. Courts which are asked to delete, insert or rewrite part of a contract because of what is said to be an obvious error should bear steadily in mind that imperfections and infelicities and ambiguities in contractual language commonly reflect the give and take of negotiations, or the parties’ appreciation that some obscurities are incapable of resolution. As Lord Hoffmann explained, the court does “not readily accept that people have made mistakes in formal documents”: Chartbrook Ltd v Persimmon Homes Ltd [2009] AC 1101; [2009] UKHL 38 at [23].
-
Although something had arguably gone wrong in the drafting of Special Condition 9.1 and Item 21 of the Particulars, it by no means followed that, as a matter of construction, the Contract could be construed so that Ostwald’s Adjudication Application was made within time.
Rectification in equity
-
In Australia, a contract may be rectified in equity where it is shown that there was at the time the document was executed, a common intention which, through a common mistake, was not reflected in the document: Maralinga Pty Ltd v Major Enterprises Pty Ltd (1973) 128 CLR 336 at 346 and 350-351; [1973] HCA 23; Simic v New South Wales Land and Housing Corporation (2016) 260 CLR 85; [2016] HCA 47 at [46] and [103]. Recent authorities from the United Kingdom must be read with care, because the doctrine has diverged, although not relevantly for the purposes of this appeal.
-
Equity insists on a high standard of proof. This is regularly expressed by a requirement of “clear and convincing proof” or “convincing proof”. Campbell JA considered this in detail in Franklins Pty Ltd v Metcash Trading Ltd (2009) 76 NSWLR 603; [2009] NSWCA 407 at [451]-[461]; see further the decisions collected in Newey v Westpac Banking Corporation [2014] NSWCA 319 at [170] and J Cummins Pty Ltd v F & D Bonaccorso [2015] NSWCA 200 at [7], and also Mobis Parts Australia Pty Ltd v XL Insurance Company SE [2018] NSWCA 342 at [11]. In Simic, Kiefel J, with whom French CJ agreed in this respect, said at [41] that the common intention must be “proved to a high standard” and cited Lord Chelmsford's statement in Fowler v Fowler (1859) 4 De G & J 250 at 265; 45 ER 97 at 103 that a person seeking to rectify a deed must establish the alleged intention “in the clearest and most satisfactory manner”. It has been explained that the insistence on a high standard of proof reflected a centuries old concern on the part of Chancery lest the integrity of written agreements be undermined. Equity recognised that it would not enforce an agreement where the defendant admitted the mistake, and to that exception were added cases where the mistake was proven by clear and convincing evidence equal to an admission: F Dawson, “Interpretation and Rectification of Written Agreements in the Commercial Court” (2015) 131 LQR 344 at 347. Rectification, no differently from non est factum and other principles which detract from the objective theory of contractual interpretation “must necessarily be kept within narrow limits”: Petelin v Cullen (1975) 132 CLR 355 at 359; [1975] HCA 24. If unchecked they would cause “serious mischief”: Toll (FGCT) Pty Ltd v Alphapharm Pty Ltd (2004) 219 CLR 165; [2004] HCA 52 at [46]-[47].
-
It has been said, of the position in the United Kingdom, that there has been an “explosion” of claims for rectification in equity, and that it is attributable to the increasing complexity of commercial and other written contracts, the tendency for successive drafts to be composed using a “cut and paste” style of word-processing, their increasing length and complexity, and the richness of accessible electronic records of negotiations: see D Neuberger, foreword to D Hodge QC, Rectification: The Modern Law and Practice Governing Claims for Rectification for Mistake (2nd ed, Sweet & Maxwell, 2016), p ix. This may also be, in part, a consequence of the changes introduced by what was said, obiter, in Chartbrook at [48]-[67]. But that does not reflect the law in Australia: Simic at [19], [48]-[49].
-
The doctrines at law and in equity remain conceptually distinct, as French CJ noted in Simic at [18] and [20], and as Kiefel J stated at [48], doubting a suggestion in Chartbrook that consistency of approach was warranted between rectification and construction. Conceptually, there is a world of difference. The requirements of ex facie absurdity or inconsistency and clarity as to what the parties must be taken to have intended ensure that rectification by construction remains an aspect of determining the objectively manifested legal meaning of contractual words, and accommodates the truth that sometimes, even in a formal legal document, the parties will make mistakes which are nonetheless readily identified and corrected. On the other hand, rectification in equity turns on the discrepancy between the written instrument and a separately proven contrary common intention, which was intended to have been incorporated into the instrument, such that it is unconscientious for a party to insist on performance in accordance with the written instrument. Rectification in equity is a departure – albeit one which is narrowly circumscribed by the insistence on cogent proof – from the objective theory of contract.
-
Any assimilation of the two doctrines would also confront very large obstacles in terms of their practical operation. Without being exhaustive, the following differences may be noted.
First, a court may not have jurisdiction to make an order for rectification in equity (cf Cherry v Steele-Park (2017) 96 NSWLR 548; [2017] NSWCA 295 at [139]).
Secondly, and very commonly, evidence (for example, as to the parties’ subjective intentions) may be admissible in equity but not at common law: see Cherry v Steele-Park at [57]-[58].
Thirdly, different defences may be available to a claim for equitable rectification. For example, rectification will not be decreed if to do so would prejudice the rights of a bona fide third party: see the decisions noted by Brereton J (as his Honour then was) in Harris v Smith [2008] NSWSC 545 at [49]). A right to rectification in equity is a classic example of a “mere equity” which may be defeated by a later equitable interest acquired without notice of it.
Fourthly, equitable rectification may in an appropriate case be ordered on terms, as noted in Marley v Rawlings [2015] AC 129; [2014] UKSC 2 at [40].
-
Enough has been said to establish that, as Lord Neuberger said in Marley v Rawlings at [40], the question is “by no means simply an academic issue of categorisation”; see further P Davies, “Rectification versus Interpretation: The Nature and Scope of the Equitable Jurisdiction” [2016] CLJ 62.
-
In the present case, the parties’ submissions were confined to rectification in equity. It was made clear during the hearing that if Ostwald sought to rely upon construction, a notice of contention would be required (transcript, 29 October 2018, pp 63-64). None was put forward, even after an adjournment.
-
As Sackville AJA explains, in the absence of any evidence from the officers of Ostwald who executed the contract on its behalf, and of evidence explaining how Special Condition 9.1 came to be incorporated, some time after the exchange of written drafting proposals, and including changes not otherwise explained in the evidence, the high standard of proof for rectification in equity was not made out.
Was Ostwald precluded from suing for the statutory debt?
-
Subsection 16(2) of the Act provides that, in circumstances which it was accepted obtained, that the claimant:
“(a) may:
(i) recover the unpaid portion of the scheduled amount from the respondent, as a debt due to the claimant, in any court of competent jurisdiction, or
(ii) make an adjudication application under section 17 (1) (a) (ii) in relation to the payment claim, and
(b) may serve notice on the respondent of the claimant’s intention to suspend carrying out construction work (or to suspend supplying related goods and services) under the construction contract.”
-
Again, as Sackville AJA explains, it was accepted that s 16(2)(a)(i) and (ii) provided a claimant with two mutually exclusive alternatives where there had been a failure to pay a scheduled amount. The issue was whether Ostwald, having purported to apply for adjudication but having done so invalidly, because it was outside the time limits applicable to s 16(2)(a)(ii), was capable of enforcing the debt pursuant to s 16(2)(a)(i). Did Ostwald’s out of time purported exercise of one of the statutory alternatives preclude it from exercising the other?
-
Seymour Whyte submitted that Ostwald was prevented from enforcing the debt pursuant to s 16(2)(a)(i), either as a matter of statutory construction, or else as a matter of election at common law.
-
In many areas of law, it can be difficult to identify whether the answer to an issue is one of “common law” or of statutory construction. One reason for this was explained by Windeyer J in Gammage v The Queen (1969) 122 CLR 444 at 462; [1969] HCA 68. Referring to the law of homicide, he said that “[i]ts growth, elaboration and development over centuries has been the result of the work of Parliament as well as of courts and of the great and authoritative writers.” The same may be said of much private law (consider the law of partnership, or marine insurance, or contributory negligence, or any other area where statute has intervened and the intervention has itself become subject to a body of judge-made law). But there is another reason why Windeyer J’s statement that “it is misleading to speak glibly of the common law in order to compare and contrast it with a statute” is presently applicable. The rights conferred by the Act are not of any great antiquity, but they are intimately connected with the parties’ rights at common law, based, primarily, on their contract. Because the Act is framed with a close regard to modifying extant rights, liabilities, powers and privileges under a construction contract, it can be quite unclear whether the source of a particular entitlement is statute or contractual. Often, it is both. For example, while every payment claim and every payment schedule is, in a sense, a creature of the Act, their content and timing are determined by the terms of the parties’ contract.
-
Although grounds 2(a) and (b) of Seymour Whyte’s appeal distinguished between common law and statutory sources of its claimed entitlement to prevent Ostwald suing on the statutory debt, and to my mind identifying that source is far from straightforward, it is clear that Ostwald was not prevented from enforcing the s 16(2)(a)(i) debt.
No election at common law
-
Election at common law only applies if there are inconsistent legal rights. “[I]t is this concurrent existence of inconsistent sets of rights which explains the doctrine; because they are inconsistent neither one may be enjoyed without the extinction of the other and that extinction confers upon the elector the benefit of enjoying the other, a benefit denied to him so long as both remained in existence”: Sargent v ASL Developments Ltd (1974) 131 CLR 634 at 641; [1974] HCA 40 (Stephen J, with whom McTiernan ACJ agreed). The same point was made in Agricultural and Rural Finance Pty Ltd v Gardiner (2008) 238 CLR 570; [2008] HCA 57 at [58]:
“The doctrine of election is long established at common law. As Jordan CJ pointed out in O’Connor v SP Bray Ltd, ‘[s]ince the days of the Year Books it has been recognised that you cannot have the egg and the halfpenny too’. If, then, something happens which gives rise to the existence of two alternative rights, and one of those rights is satisfied, the other is no longer available” [citation omitted].
-
It is accepted that the out of time adjudication application was invalid; it must follow that there was no inconsistency such as to give rise to an occasion for election at common law.
No election as a matter of construction
-
Seymour Whyte's submissions as a matter of construction must also be rejected. Seymour Whyte submitted that “s 16(2)(a)(ii) is engaged by the making of an adjudication application in fact, even if that adjudication application is vitiated by jurisdictional error”, thereby precluding the recovery of the statutory debt.
-
Seymour Whyte relied on Gageler J’s analysis in State of New South Wales v Kable (2013) 252 CLR 118; [2013] HCA 26 at [52]. Speaking of a purported but invalid law, and a thing done in the purported but invalid exercise of a power conferred by law, Gageler J said that both remained “at all times a thing in fact”. He continued:
“The thing is, as is sometimes said, a ‘nullity’ in the sense that it lacks the legal force it purports to have. But the thing is not a nullity in the sense that it has no existence at all or that it is incapable of having legal consequences. The factual existence of the thing might be the foundation of rights or duties that arise by force of another, valid, law” [citation omitted].
-
The fact that a decision is beyond jurisdiction, and may be said to be a “nullity”, is not determinative of its status for the purposes of further legal analysis. The law of contempt supplies an example. An inferior court’s order beyond jurisdiction is a nullity, in the sense that the failure to obey it cannot be a contempt: United Telecasters Sydney Ltd v Hardy (1991) 23 NSWLR 323 at 335; Pelechowski v The Registrar, Court of Appeal (1999) 198 CLR 435; [1999] HCA 19 at [27]-[28], [55] and [71]. However, an order beyond jurisdiction may also be the subject of proceedings seeking judicial review in the Supreme Court’s supervisory jurisdiction, or indeed an appeal (consider for example an appeal from the District Court upheld on the basis of a denial of procedural fairness).
-
But the question is one of construction. Seymour Whyte’s submission is that Ostwald made an adjudication application in fact, albeit out of time, such that it was invalid to engage the suite of rights under Division 2 of Part 3 of the Act, but was sufficient to preclude the alternative right under s 16(2)(a)(i). There is no reason to construe the statute in so capricious a manner. Why would not only the substantive rights under Division 2 of Part 3 be unavailable because the application was lodged out of time, but also the alternative rights under s 16(2)(a)(i) be precluded as well? Seymour Whyte submits that, as happened here, a claimant might persevere with taking steps down both alternative paths. But that is no reason to reach the construction for which Seymour Whyte contends, which denies to the claimant both alternatives.
-
The reality of the situation is that there may be, as here, a dispute as to which of the two alternative rights enjoyed by a claimant is available. In the present case, I would infer that both sides had reasonably arguable positions as to whether the Adjudication Application had been lodged in time. The position would only become clear following the determination of a court, which would not occur within the very tight timeframes required under the statutory regime. There is no reason to construe the Act, which after all is beneficial legislation providing additional valuable (albeit interim) rights to claimants, so that both alternative rights are lost in the event that a claimant turns out to be wrong in its view as to the availability of one of them.
Did the Act apply once a liquidator was appointed?
-
The primary judge considered that the decision of the Victorian Court of Appeal in Façade Treatment Engineering Pty Ltd (in liq) v Brookfield Multiplex Constructions Pty Ltd was clearly wrong, principally since it had failed to have regard to the definition of “claimant”. The Victorian Court of Appeal had accepted Multiplex’s submission that the Act did “not apply once a person seeking payment had been placed into liquidation”: at [58]; see also at [89]-[90] and [191].
-
When the appeal was heard in this Court, Seymour Whyte accepted that aspects of Façade were wrong. As Sackville AJA has explained, Seymour Whyte was correct to take that course. Seymour Whyte also adopted a narrower approach. Accepting that companies may be wound up for a variety of reasons aside from insolvency, including on the just and equitable ground in the case of, say, a deadlocked board and membership, it contended that the Act only ceased to apply when a company was being wound up in insolvency. Even so, once it is appreciated that a liquidator is empowered to, and may wish, to continue to trade, so as to sell (or at least, to investigate whether it might be possible to sell) the company’s business as a going concern, it is clear that the central premise in Façade – that the making of a winding up order ipso facto meant that the company ceased to trade – is incorrect.
-
I respectfully agree with Sackville AJA that the reasoning in Façade as to construction is plainly wrong and should not be followed.
The consequences of rejecting the reasoning as to construction in Façade
-
The Victorian Court of Appeal reached its conclusion as a matter of construction (see at [90]), noting expressly that it was “strictly unnecessary for us to consider the issue of constitutional inconsistency” (at [91]). However, the Court then took the further step of addressing, elaborately, the argument advanced under s 109 of the Constitution, concluding that it “also provides independent additional support for the narrow construction we have adopted”: at [189].
-
In this Court, although full submissions based on s 109 were advanced, ground 3(b) was abandoned in oral submissions in reply. That occurred after Ostwald explained, by reference to fresh evidence, why the constitutional point could not be run for the first time on appeal. Seymour Whyte accepted that a floating charge granted by Ostwald had crystallised prior to the commencement of its winding up, and that Ostwald had insufficient assets to satisfy its secured creditors and priority creditors, such that no issue under s 553C of the Corporations Act 2001 (Cth) could arise.
-
It is well settled that the High Court will not unnecessarily determine a constitutional question: Lambert v Weichelt (1954) 28 ALJ 282 at 283. That has been followed on numerous occasions by the High Court, including by all seven members of the High Court in Duncan v New South Wales (2015) 255 CLR 388; [2015] HCA 13 at [52] and Knight v Victoria (2017) 261 CLR 306; [2017] HCA 29 at [32]-[33].
-
In many cases, the same approach will apply in this Court: see for example Lazarus v Independent Commission Against Corruption (2017) 94 NSWLR 36; [2017] NSWCA 37 at [71]-[72] and Lavender v Director of Fisheries Compliance, Department of Industry Skills and Regional Development [2018] NSWCA 174 at [68] and [76]. However, telling against declining to resolve constitutional points is the general proposition that intermediate courts of appeal should consider all grounds of appeal, in part because of the possibility of a further appeal: Kuru v State of New South Wales (2008) 236 CLR 1; [2008] HCA 26 at [12]. Further, it may also be desirable for an intermediate court of appeal to go further than is necessary, bearing in mind the effect of the reasoning which remains. Even if the appeal be allowed on a non-constitutional ground, other trial courts will not be free to disregard the reasoning at first instance: see Sparks v Hobson; Gray v Hobson [2018] NSWCA 29; 361 ALR 115 at [35]-[40]. Thus a more nuanced approach may be required: see for example Alqudsi v Commonwealth of Australia (2015) 91 NSWLR 92; [2015] NSWCA 351 at [124]-[125].
-
The present case is different again. Ground 3(b) has been abandoned. In that unusual circumstance, I do not think it is right to express a view, one way or the other, as to the correctness of the constitutional aspect of the reasoning in Façade. But the point was fully argued in this Court, and will doubtless recur. For the purposes of New South Wales courts, it is appropriate to state that the constitutional analysis in Façade is inapplicable to the Building and Construction Industry Security of Payment Act 1999 (NSW). The Victorian Court of Appeal considered that the “roll back” provisions in ss 5E, 5F and 5G of the Corporations Act 2001 (Cth) had no application: at [187]. In accordance with Ostwald’s persuasive submission, a different analysis obtains in New South Wales.
-
The New South Wales Act commenced in March 2000, prior to the commencement of the Corporations Act 2001 (Cth) (in July 2001), both of which preceded the commencement of the Victorian Act on 31 January 2003. The difference in timing matters. Speaking generally, much of the New South Wales Act, including the key provisions relating to the right to adjudication and the enforcement of an adjudicator’s determination, are not materially altered from the form they took in July 2001 (although it is true that an adjudicator’s determination could not at that time be filed as a judgment). It follows that the provisions of the New South Wales Act are apt to be “pre-commencement (commenced) provisions” within the meaning of s 5G(12) of the Corporations Act, and that any analysis of the interaction between the Corporations Act and the New South Wales Act must have regard to s 5G.
-
Although the “roll back” provisions are complex, their general force is to the effect that where State legislation co-existed with the Corporations Law prior to July 2001, then broadly speaking State legislation should continue to operate after the commencement of the Corporations Act 2001 (Cth).
-
It follows from the foregoing that the reasoning of Young CJ in Eq in Brodyn Pty Ltd v Dasein Constructions Pty Ltd [2004] NSWSC 1230 at [82]-[84] concerning s 109, on which the Victorian Court of Appeal relied, is likewise materially incomplete. It may be noted that (a) Young CJ in Eq’s reasoning was distinguished by McDougall J in Veolia Water Solutions v Kruger Engineering [No 3] [2007] NSWSC 459 at [11]-[26], (b) that there was an appeal: Silvia v Brodyn Pty Ltd [2007] NSWCA 55 in which Hodgson JA, with whom Ipp and Basten JJA agreed, while dismissing the appeal, expressed a different view as to the operation of s 553C of the Corporations Act at [46].
-
Thus, in a New South Wales case where the point arises, it will be necessary to examine the operation of s 5G upon the impugned provisions of the Act.
-
PAYNE JA: I have had the privilege of reading the decision of Sackville AJA in draft. I agree with his Honour’s reasons and the orders he proposes. I also agree with the additional observations of Leeming JA.
-
WHITE JA: I agree with Sackville AJA. I also agree with the additional observations of Leeming JA.
-
SACKVILLE AJA: These proceedings arise out of a claim for progress payments under a Works Subcontract (No CW01) dated 6 September 2016 (Contract) between the appellant (Seymour) as Contractor and the first respondent (Ostwald) as Subcontractor. Ostwald, now in liquidation, agreed on terms specified in the Contract to perform certain road works on the Pacific Highway near Grafton. The head contractor was New South Wales Roads and Maritime Services (RMS).
The proceedings
-
Ostwald served a progress payment claim on Seymour for $6,351,066.08 pursuant to s 13(1) of the Building and Construction Industry Security of Payment Act 1999 (NSW) (Security of Payment Act). [1]
1. Relevant provisions of the Security of Payment Act are set out at [71]-[91] below.
-
Seymour responded by providing a payment schedule pursuant to s 14 of the Security of Payments Act, stating that it proposed to pay $2,505,237.58 by way of progress payments (Scheduled Amount). Ostwald then made what it said was an adjudication application under s 17(2)(a)(ii) of the Security of Payment Act (Adjudication Application). The Adjudicator subsequently issued an adjudication determination pursuant to s 22 of the Security of Payment Act (Adjudication Determination) which determined that the amount due by Seymour to Ostwald was $5,074,218.27 (Adjudicated Amount). Seymour has paid neither the Scheduled Amount nor the Adjudicated Amount.
-
Seymour commenced proceedings in the Equity Division claiming that the Adjudication Determination was invalid on the ground that Ostwald made the Adjudication Application outside the time limit specified in the Security of Payment Act. Seymour joined the Adjudicator as the second defendant and the person appointed as nominating authority under the Security of Payment Act as the third defendant. Both filed submitting appearances.
-
Seymour required leave pursuant to s 440D(1)(b) of the Corporations Act 2001 (Cth) (Corporations Act) to commence the proceedings as the directors of Ostwald had previously resolved to appoint administrators. Ball J granted Seymour leave on condition that Seymour not enforce any orders made in its favour without leave. His Honour noted that Seymour gave the usual undertaking as to damages and also undertook to pay the Adjudicated Amount into court.
-
Ostwald filed a cross-claim seeking rectification of the Contract to alter the dates on which Seymour had to make progress payments. It was common ground that if the claim for rectification succeeded, Ostwald’s Adjudication Application was made within the time prescribed by the Security of Payment Act, but if the Contract was not rectified the adjudication application had been made out of time and the Adjudication Determination was invalid. In the alternative Ostwald claimed the unpaid Scheduled Amount of $2,505,237.58 as a statutory debt pursuant to s 16(2)(a)(i) of the Security of Payment Act.
-
After the proceedings commenced the creditors of Ostwald resolved pursuant to s 439C(c) of the Corporations Act, that it should be wound up.
-
The primary Judge (Stevenson J) held that:[2]
1. this was a clear case where rectification of the Contract should be ordered;
2. the Adjudication Application was therefore made within time and the Adjudication Determination was valid;
3. even if, contrary to the second holding, the Adjudication Determination was invalid, Ostwald was entitled to seek recovery of the unpaid Scheduled Amount as a debt due to it pursuant to s 16(2)(a)(i) of the Security of Payment Act;
4. the Security of Payment Act on its proper construction continued to apply notwithstanding that the winding up of Ostwald had commenced;
5. but the Court had no option except to stay any judgment obtained by Ostwald following the Adjudication Determination until the parties’ rights were finally determined in the liquidation by an account of their mutual dealings as required by s 553C of the Corporations Act.
2. Seymour Whyte Constructions Pty Ltd v Ostwald Bros Pty Ltd (in liq) [2018] NSWSC 412 (Primary Judgment).
-
The primary Judge also refused a late application by Seymour to amend its Technology and Construction List Statement (List Statement). Seymour wished to contend that certain provisions of the Security of Payment Act are inconsistent with s 553C of the Corporations Act and are therefore invalid to the extent of the inconsistency by virtue of s 109 of the Constitution. [3] His Honour declined to entertain the argument.
3. Section 109 of the Constitution provides that when a State law is inconsistent with a law of the Commonwealth, the latter shall prevail, and the former, to the extent of the inconsistency, be invalid.
-
Following a separate hearing and judgment on costs [4] the primary Judge made the following orders and notation (original numbers retained):
4. Seymour Whyte Constructions Pty Ltd v Ostwald Bros Pty Ltd (in liq) (No 2) unrep, 20 April 2018.
“5. Order that the ‘Works Subcontract’ (Subcontract Number: CW01) in which [Ostwald] is described as the ‘Subcontractor’ and [Seymour] is described as the ‘Contractor’ (‘Subcontract’) is rectified by deleting clause 9.1 [5] of the ‘GC 21 Special Conditions – All Subcontracts’ forming part of the Subcontract.
6. Order that a copy of order 5 of these orders be endorsed on the Subcontract.
7. Order that any judgment obtained by [Ostwald] arising from filing of an adjudication certificate in relation to the adjudication determination dated 6 November 2017 be stayed until further order in these proceedings or in the proceedings in which any judgment is obtained with a view that, unless otherwise ordered, the stay will remain in effect until an account is taken of the kind contemplated by s 553C of the Corporations Act 2001 (Cth) as between [Ostwald] and [Seymour] in respect of their mutual dealings.
8. Order that the Further Amended Summons is otherwise dismissed.
9. Order that the moneys paid into Court by [Seymour] on 17 November 2017 (plus interest accrued thereon) are to be repaid to [Seymour] by electronic transfer to the following account:
…
10. Subject to the other specific orders as to costs made in these proceedings … order that [Seymour] pay 75% of [Ostwald’s] costs of these proceedings (including the cross-claim).
THE COURT NOTES THAT [Seymour] undertakes to lodge a proof of debt in the winding up of [Ostwald] within 28 days and, if [Seymour] does not lodge such a proof of debt, the stay granted in order 7 will cease and this undertaking will expire.”
The Court was informed that Seymour lodged a proof of debt within the 28 day period. The proof of debt was not in the appeal papers.
5. Clause 9.1 of the Special Conditions to the Contract specified the time within which amounts due to Ostwald were to be paid: see [94] below.
-
Since the primary Judge concluded that the Adjudication Determination was valid and that Ostwald could file an adjudication certificate as a judgment for debt pursuant to s 25(1) of the Security of Payment Act, his Honour did not make orders on Ostwald’s cross-claim for the unpaid Scheduled Amount as a statutory debt.
-
Seymour’s notice of appeal contains the following grounds:
“1. The primary judge erred in holding that:
(a) the parties had a common intention at the time of executing the contract that Seymour … had 30 days from the end of the month in which Ostwald … served a payment claim to make payment; and
(b) the contract between Seymour … and Ostwald … should be rectified to reflect that common intention.
2. The primary judge erred in failing to hold that:
(a) Ostwald … could not pursue rights under s 16(2)(a)(i) of the Act in circumstances where it had in fact made an adjudication application under s 17(1)(a)(ii) of the Act in relation to its payment claim;
(b) Ostwald … could not pursue rights under s 16(2)(a)(i) of the Act in circumstances where it had elected to make an adjudication application and to pursue that application to a determination.
3. The primary judge erred in failing to hold that Part 3 of the Act or, in the alternative, ss 24(1), 25(1) and/or 25(4) is not or are not available to a company in liquidation:
(a) as a matter of construction of the Act; or
(b) by reason of s 109 of the Constitution.”
-
It can be seen that:
Ground 1 challenges the first and second holdings (set out at [53] above);
Ground 2 challenges the third holding;
Ground 3 challenges the fourth holding; and also seeks to rely on the constitutional argument notwithstanding that the primary Judge refused Seymour leave to amend in order to advance the argument at the trial.
-
Ostwald filed with leave an amended notice of cross-appeal. Ground 1 challenges the decision of the primary Judge to stay any judgment obtained by Ostwald as the result of filing an adjudication certificate. Ostwald says that his Honour should have held that Seymour had neither pleaded nor proved that it was entitled to the benefit of a set-off of the kind contemplated by s 553C of the Corporations Act.
-
Ground 2 of the amended cross-appeal is enlivened only if this Court sets aside the order for rectification of the Contract and concludes that the Adjudication Application was “void”. In that case Ostwald contends that the primary Judge should have ordered that Seymour pay $2,505,237.58 plus interest, since his Honour correctly held that it was open to Ostwald to seek recovery of the unpaid Scheduled Amount in curial proceedings brought pursuant to s 16(2)(a)(ii) of the Security of Payment Act.
-
Seymour filed a notice of contention in respect of the cross-appeal. It contends that the primary Judge:
“in the exercise of discretion in the interests of justice, [should] have stayed any judgment arising from the filing of any adjudication certificate until an account is taken, pursuant to s 553C of the Corporations Act 2001 (Cth), of the amounts due from Ostwald to Seymour … in respect of their mutual dealings under the contract.”
-
Seymour has filed a notice of contention in respect of the cross-appeal seeking to support the stay granted by the primary Judge on an alternative basis. Seymour contends that the primary Judge, in the exercise of discretion and in the interests of justice, should have stayed any judgment arising from the filing of an adjudication certificate until the account required by s 553C of the Corporations Act is taken.
-
On 22 June 2018, Seymour was granted leave nunc pro tunc pursuant to s 500(2) of the Corporations Act to commence its appeal against the decision of the primary Judge. [6]
6. Seymour Whyte Constructions Pty Ltd v Ostwald Bros Pty Ltd (in liquidation) [2018] NSWCA 139. The Court assumed, without deciding, that leave was necessary.
-
Seymour gave notice of a constitutional issue to the Attorneys-General of the Commonwealth, States and Territories as required by s 78B of the Judiciary Act 1903 (Cth). None sought to intervene in the proceedings.
Narrowing of issues
-
There were numerous twists and turns in the course of argument. Much time was devoted to the constitutional contention and, consequently, to the interaction between the provisions of the Security of Payment Act and s 553C of the Corporations Act. Ostwald’s oral submissions included a close analysis of the complex provisions of Part 1.1A of the Corporations Act, which deals with the interaction between Corporations legislation and State and Territory laws (matters overlooked in Seymour’s submissions).
-
In the course of argument Mr Robertson, who appeared with Mr Smith for Ostwald, tendered without objection a Mortgage Debenture dated 9 June 2006 between Ostwald and Australia and New Zealand Banking Group Ltd (ANZ). Other material in the appeal books indicated that ANZ’s charge had crystallised on 15 August 2017, by virtue of the service of a garnishee notice by the Australian Taxation Office on Seymour. This was before 25 August 2017, the date (as the parties agreed) that the winding up of Ostwald is taken to have commenced. [7] There was also material in the appeal books suggesting that Ostwald had insufficient assets to satisfy ANZ’s security interest and priority creditors. This raised a question as to whether there was mutuality in the relevant sense for the purposes of s 553C(1) of the Corporations Act between Seymour and Ostwald.
7. Being the date on which the administration of Ostwald began: Corporations Act, ss 513B(b), 513C; see [110] below
-
By reason of these and other matters Mr Christie informed the Court that Seymour did not propose to rely on any argument based on s 553C of the Corporations Act and did not press the constitutional contention.
-
After some discussion, Mr Robertson gave an undertaking to the Court on behalf of Ostwald that it would:
“not take steps for the enforcement of judgments pursuant to the Adjudicator’s determination or any judgment which this Court may make or sought in the amended cross-appeal without first giving 14 days notice to [Seymour].”
The Court noted that Seymour gave the usual undertaking as to damages.
-
Ostwald’s undertaking may provide Seymour with the opportunity, if so advised, to seek orders restraining enforcement of any judgment obtained by Ostwald for the unpaid Adjudication Amount or other relief. That may require Seymour to put on evidence establishing that it at least has an arguable claim against Ostwald based on its rights under the Contract preserved by the Security of Payment Act. [8]
8. Security of Payment Act, s 32(1), (2), (3); Grosvenor Constructions (NSW) Pty Ltd (in administration) v Musico [2004] NSWSC 344 at [27]-[32] (Einstein J); Veolia Water Solutions v Kruger Engineering (No 3) [2007] NSWSC 459 (Veolia) at [72]-[92] (McDougall J).
-
Mr Christie pressed Ground 3(a) of the notice of appeal, which contends that Part 3 of the Security of Payment Act, on its proper construction, is not available to a company in liquidation. If this contention is accepted it would prevent Ostwald relying on the Adjudication Determination (if valid) and would also prevent Ostwald from pursuing the alternative route of curial proceedings to recover the unpaid portion of the Scheduled Amount as a debt.
Legislation
Security of Payment Act
-
The Security of Payment Act was enacted in 1999 and has been adopted with variations in other Australian jurisdictions (although not all). [9] The legislation has given rise to numerous questions of construction and many authorities have explained the legislative scheme. [10] It is necessary to repeat the exercise for the purposes of this appeal.
9. Probuild Constructions (Aust) Pty Ltd v Shade Systems Pty Ltd (Probuild Constructions) [2018] HCA 4; (2018) 351 ALR 225 at [3] (Kiefel CJ, Bell, Keane, Nettle and Gordon JJ). The New South Wales Legislation has been amended on several occasions, notably by the Building and Construction Industry Security of Payment Amendment Act 2002 (NSW) and the Building and Construction Industry Security of Payment Amendment Act 2013 (NSW). The legislation in force in the various Australian jurisdictions has recently been examined in the Review of Security of Payment Laws (December 2017) (Murray Report).
10. See, for example, Probuild Constructions at [4]-[18]; Southern Han Breakfast Point Pty Ltd (in liq) v Lewence Construction Pty Ltd (Southern Han) (2016) 260 CLR 340; [2016] HCA 52 at [3]-[19] per curiam.
-
The High Court has on two occasions quoted the explanation of the original design of the Security of Payment Act given by the responsible Minister when introducing amending legislation in 2002: [11]
“The Act was designed to ensure prompt payment and, for that purpose, the Act set up a unique form of adjudication of disputes over the amount due for payment. Parliament intended that a progress payment, on account, should be made promptly and that any disputes over the amount finally due should be decided separately. The final determination could be by a court or by an agreed alternative dispute resolution procedure. But meanwhile the claimant’s entitlement, if in dispute, would be decided on an interim basis by an adjudicator, and that interim entitlement would be paid.”
The Minister went on to say that cash flow was the “lifeblood of the construction industry” and that the Government was:
“determined that, pending final determination of all disputes, contractors and subcontractors should be able to obtain a prompt interim payment on account, as always intended under the Act.”
11. New South Wales, Legislative Assembly, Parl Deb, 12 November 2002 at 6542. (Hon Morris Iemma MLA), quoted in Southern Han at [4] and Probuild Constructions at [39].
-
Section 3(1) of the Security of Payment Act states that the object of the legislation is:
“to ensure that any person who undertakes to carry out construction work … under a construction contract is entitled to receive and is able to recover, progress payments in relation to the carrying out of that work…”
The means by which the Act ensures that a person is entitled to receive a progress payment “is by granting a statutory entitlement to such a payment regardless of whether the relevant contract makes provision for progress payments” (s 3(2)).
-
Section 3(3) provides as follows:
“The means by which this Act ensures that a person is able to recover a progress payment is by establishing a procedure that involves:
(a) the making of a payment claim by the person claiming payment, and
(b) the provision of a payment schedule by the person by whom the payment is payable, and
(c) the referral of any disputed claim to an adjudicator for determination, and
(d) the payment of the progress payment so determined.”
-
Section 4(1) defines “progress payment” to mean:
“a payment to which a person is entitled under section 8, and includes (without affecting any such entitlement):
(a) the final payment for construction work carried out … under a construction contract, or
(b) a single or one-off payment for carrying out construction work … under a construction contract, or
(c) a payment that is based on an event or date (known in the building and construction industry as a ‘milestone payment’).”
-
Section 5(1) defines “construction work” to mean any of various activities identified in the provision, such as the construction, alteration or extension, demolition of buildings or structures.
-
Part 2 of the Security of Payment Act creates “Rights to progress payments”. Section 8 provides as follows:
“(1) On and from each reference date under a construction contract, a person:
(a) who has undertaken to carry out construction work under the contract, or
(b) …
is entitled to a progress payment.
(2) In this section, reference date, in relation to a construction contract, means:
(a) a date determined by or in accordance with the terms of the contract as the date on which a claim for a progress payment may be made in relation to work carried out or undertaken to be carried out (or related goods and services supplied or undertaken to be supplied) under the contract, or
(b) …”
-
In the circumstances of the present case the amount of a progress payment to which a person is entitled in respect of a continuation contract is to be the amount calculated in accordance with the terms of the contract (s 9(a)).
-
Section 11(1) provides that, subject to s 11 and any other law, a progress payment is to be made in accordance with the applicable terms of the contract. “Due date” in relation to a progress payment is defined in s 4(1) to mean the due date for the progress payment as referred to in s 11.
-
The procedure referred to in s 3(3) of the Security of Payment Act is set out in Part 3 (“Procedure for recovering progress payments”). Section 13(1) provides that:
“A person referred to in section 8(1) who is or who claims to be entitled to a progress payment (the claimant) may serve a payment claim on the person who, under the construction contract concerned, is or may be liable to make the payment.”
The payment claim must indicate, among other things, “the amount of the progress payment that the claimant claims to be due (the claimed amount)” (s 13(2)(b)). A payment claim may be served (relevantly) only within the period determined in accordance with the contract (s 13(4)(a)). Service by a claimant on the respondent of a payment claim for a claimed amount is therefore the trigger for the procedure set out in Part 3. [12]
12. Southern Han at [14].
-
Section 14 deals with the payment schedule as follows:
“(1) A person on whom a payment claim is served (the respondent) may reply to the claim by providing a payment schedule to the claimant.
(2) A payment schedule:
(a) must identify the payment claim to which it relates, and
(b) must indicate the amount of the payment (if any) that the respondent proposes to make (the scheduled amount).
(3) If the scheduled amount is less than the claimed amount, the schedule must indicate why the scheduled amount is less and (if it is less because the respondent is withholding payment for any reason) the respondent’s reasons for withholding payment.
(4) If:
(a) a claimant serves a payment claim on a respondent, and
(b) the respondent does not provide a payment schedule to the claimant:
(i) within the time required by the relevant construction contract, or
(ii) within 10 business days after the payment claim is served,
whichever time expires earlier,
the respondent becomes liable to pay the claimed amount to the claimant on the due date for the progress payment to which the payment claim relates.”
-
Section 15 deals with the case where a respondent does not provide a payment schedule and fails to pay the claimed amount on or before the due date. In the present case Seymour provided a payment schedule in response to Ostwald’s payment claim. Thus s 15 does not apply.
-
Section 16 prescribes the consequences where a respondent provides a payment schedule but does not pay the scheduled amount. Section 16 provides as follows:
“(1) This section applies if:
(a) a claimant serves a payment claim on a respondent, and
(b) the respondent provides a payment schedule to the claimant:
(i) within the time required by the relevant construction contract, or
(ii) within 10 business days after the payment claim is served,
whichever time expires earlier, and
(c) the payment schedule indicates a scheduled amount that the respondent proposes to pay to the claimant, and
(d) the respondent fails to pay the whole or any part of the scheduled amount to the claimant on or before the due date for the progress payment to which the payment claim relates.
(2) In those circumstances, the claimant:
(a) may:
(i) recover the unpaid portion of the scheduled amount from the respondent, as a debt due to the claimant, in any court of competent jurisdiction, or
(ii) make an adjudication application under section 17 (1) (a) (ii) in relation to the payment claim, and
(b) may serve notice on the respondent of the claimant’s intention to suspend carrying out construction work (or to suspend supplying related goods and services) under the construction contract.
…
(4) If the claimant commences proceedings under subsection (2) (a) (i) to recover the unpaid portion of the scheduled amount from the respondent as a debt:
(a) judgment in favour of the claimant is not to be given unless the court is satisfied of the existence of the circumstances referred to in subsection (1), and
(b) the respondent is not, in those proceedings, entitled:
(i) to bring any cross-claim against the claimant, or
(ii) to raise any defence in relation to matters arising under the construction contract.”
-
Division 2 of Part 3 is headed “Adjudication of disputes”. Section 17 relevantly provides as follows:
“(1) A claimant may apply for adjudication of a payment claim (an adjudication application) if:
(a) the respondent provides a payment schedule under Division 1 but:
(i) …, or
(ii) the respondent fails to pay the whole or any part of the scheduled amount to the claimant by the due date for payment of the amount, or
(b) …
(3) An adjudication application:
(a) must be in writing, and
…
(d) in the case of an application under subsection (1) (a) (ii)—must be made within 20 business days after the due date for payment
…”
The expression “adjudication application” is defined in s 4(1) to mean “an application referred to in section 17”.
-
The adjudication is to determine the amount of the progress payment (if any) to be made by the respondent to the claimant (the adjudicated amount), the date on which the adjudicated amount became or becomes payable and the rate of interest payable (s 22(1)).
-
Section 23(2) provides that if an adjudicator determines that a respondent is required to pay an adjudicated amount, the respondent must pay that amount to the claimant on or before the relevant date. The “relevant date” is five business days after the adjudicator’s determination is served on the respondent, unless the adjudicator determines a later date (s 23(1)).
-
Section 24 prescribes the consequences of the respondent not repaying the adjudicated amount:
“(1) If the respondent fails to pay the whole or any part of the adjudicated amount to the claimant in accordance with section 23, the claimant may:
(a) request the authorised nominating authority to whom the adjudication application was made to provide an adjudication certificate under this section, and
(b) serve notice on the respondent of the claimant’s intention to suspend carrying out construction work … under the construction contract.”
-
Section 25 provides as follows:
“(1) An adjudication certificate may be filed as a judgment for a debt in any court of competent jurisdiction and is enforceable accordingly.
(2) An adjudication certificate cannot be filed under this section unless it is accompanied by an affidavit by the claimant stating that the whole or any part of the adjudicated amount has not been paid at the time the certificate is filed.
(3) If the affidavit indicates that part of the adjudicated amount has been paid, the judgment is for the unpaid part of that amount only.
(4) If the respondent commences proceedings to have the judgment set aside, the respondent:
(a) is not, in those proceedings, entitled:
(i) to bring any cross-claim against the claimant, or
(ii) to raise any defence in relation to matters arising under the construction contract, or
(iii) to challenge the adjudicator’s determination, and
(b) is required to pay into the court as security the unpaid portion of the adjudicated amount pending the final determination of those proceedings.”
-
Section 27(1) states that a claimant may suspend the carrying out of construction work under a construction contract if at least two business days have passed since the claimant has given notice of intention to do so, for example pursuant to s 24(1)(b).
-
Section 32 preserves rights under the construction contract:
“(1) Subject to section 34, nothing in this Part affects any right that a party to a construction contract:
(a) may have under the contract, or
(b) may have under Part 2 in respect of the contract, or
(c) may have apart from this Act in respect of anything done or omitted to be done under the contract.
(2) Nothing done under or for the purposes of this Part affects any civil proceedings arising under a construction contract, whether under this Part or otherwise, except as provided by subsection (3).
(3) In any proceedings before a court or tribunal in relation to any matter arising under a construction contract, the court or tribunal:
(a) must allow for any amount paid to a party to the contract under or for the purposes of this Part in any order or award it makes in those proceedings, and
(b) may make such orders as it considers appropriate for the restitution of any amount so paid, and such other orders as it considers appropriate, having regard to its decision in those proceedings.”
-
Section 34 states that the provisions of the Act have effect despite any provision to the contrary in any contract.
Corporations Act
-
Section 553C of the Corporations Act provides as follows:
“(1) Subject to subsection (2), where there have been mutual credits, mutual debts or other mutual dealings between an insolvent company that is being wound up and a person who wants to have a debt or claim admitted against the company:
(a) an account is to be taken of what is due from the one party to the other in respect of those mutual dealings; and
(b) the sum due from the one party is to be set off against any sum due from the other party; and
(c) only the balance of the account is admissible to proof against the company, or is payable to the company, as the case may be.
(2) A person is not entitled under this section to claim the benefit of a set‑off if, at the time of giving credit to the company, or at the time of receiving credit from the company, the person had notice of the fact that the company was insolvent.”
The Contract
-
The Contract was executed on 6 September 2016. It consisted of a number of documents including:
the “Formal Instrument of Agreement”,
the “Special Conditions” and
the “Subcontract Conditions”.
Clause 1.2 of the Formal Instrument of Agreement stated that in the event of inconsistency the Special Conditions had “priority” over the Subcontract Conditions.
-
Clause 20.4 of the Subcontract Conditions provided that Ostwald was entitled to submit payment claims at the times stated in the Particulars. Special Condition 9.1 stated that:
“Clause 20.7 of the Subcontract Conditions is replaced with the following clause:
If the balance of the statement [after deducting the amount in clause 20.6(b) from the amount in clause 20.6(a)] is that an amount is payable to the Subcontractor then the Contractor must, within 15 Business Days after the Contractor receives the payment claim:
(i) pay the GST exclusive assessed amount;
(ii) upon the Subcontractor giving the Contractor a valid tax invoice, pay the relevant GST.”
Clause 20.6 required Seymour to issue within 10 Business Days after receiving a payment claim a statement of the amount Seymour considered was payable to Ostwald (cl 20.6(a)) and any amount Seymour considered was payable by Ostwald to Seymour (cl 20.6(b)).
-
Despite Special Condition 9.1, cl 20.7 of the printed Subcontract Conditions was not deleted or struck out from the executed Contract. This version of cl 20.7 provided as follows:
“20.7 If the balance of the statement [after deducting the amount In clause 20.6(b) from the amount in clause 20.6(a)] is that an amount is payable to the Subcontractor then the Contractor must, within the time stated in the Particulars after the Contractor receives the payment claim and upon the Subcontractor giving the Contractor a valid tax invoice:
(a) pay the GST exclusive assessed amount;
(b) pay the relevant GST.”
-
The definition clause of the Subcontract Conditions (cl 33) defined “Particulars” to mean the document in “Annexure A so described and contained within the Subcontract”. Annexure A was in chart form and comprised 25 Items. Items 21, 23 and 24 are reproduced below:
21.
Due date for payment
(clause 20.7)
☐ 30 daysafter the Contractor receives the payment claim.
or
☑ Within 30 days of the end of the month of claim.
Select whichever is applicable.
If nothing stated:
• If the head contract for the Project is the New South Wales Government GC21 (Edition 2) General Conditions of Contact (GC21): 15 Business Days;
• otherwise, 25 Business Days.
23.
Head Contract Conditions - GC21
Is the head contract for the Project the New South Wales Government GC21 (Edition 2) General Conditions of Contract (GC21)?
Yes ☑ No ☐
If YES, the GC21 Special Conditions - All Subcontracts in Annexure C will apply.
If YES, complete Items 24 and 25 of these Particulars.
24.
Head Contract Conditions - GC21
If the head contract for the Project is GC21:
Is the Subcontract valued at or above $100,000?
Yes ☑ No ☐
If YES, the GC21 Special Conditions - Specified Subcontracts in Annexure C will apply.
If YES, complete Item 25 of these Particulars.
-
It can be seen that the lower of the two boxes in Item 21 of the Particulars was ticked. Item 21 in that form, when read with the original cl 20.7 in the Subcontract Conditions, indicated that the due date for payment under the Contract was within 30 days of the end of the month in which Seymour received the payment claim. By contrast, cl 20.7, as substituted by Special Condition 9.1, required Seymour to pay “the balance of the statement” within 15 business days after Seymour received the payment claim.
-
If the lower box in Item 21 had not been ticked there would have been “nothing stated”. Since the head contract for the Project was the New South Wales Government GC 21 (confirmed by Items 23 and 24), subject to the operation of cl 20.7 as substituted by Special Condition 9.1, the time for payment would have been “15 Business Days”. It is not entirely clear whether that meant 15 business days after Seymour received the payment claim or 15 business days after the end of the month in which the payment claim was made. Evidence given by Mr Millar on behalf of Seymour, to which reference is made later,[13] suggests that the effect of not ticking the second box would have been to require payment within 15 business days of receipt of the payment claim.
13. See at [131] below.
-
As appears from the Particulars reproduced above, the “Yes” box in Item 23 was ticked. The consequence was that “All Subcontracts in Annexure C will apply”. Since Special Condition 9.1 formed part of Annexure C, the effect of ticking the box in Item 23 was to incorporate Special Condition 9.1 as a term of the Contract. As Mr Robertson acknowledged in argument in this Court, ticking the “Yes” box in Item 23 created an inconsistency with the ticked second box in Item 21.
Background facts
-
On 28 July 2017, Ostwald served a payment claim on Seymour pursuant to s 13(1) of the Security of Payment Act. As noted above, the claim sought payment of $6,351,066.08.
-
On 11 August 2017, in response to the payment claim, Seymour served a payment schedule pursuant to s 14(1) of the Security of Payment Act. Seymour stated in compliance with s 14(2)(b) that it proposed to pay Ostwald the Scheduled Amount ($2,505,237.58).
-
On Seymour’s case the date on which the progress payment became due and payable for the purposes of s 11 of the Security of Payment Act was 15 business days after Seymour received the payment claim, in accordance with cl 20.7 of the Subcontract Conditions (as substituted by Special Condition 9.1). The due date was therefore 18 August 2017.
-
On 24 August 2017, Seymour terminated the Contract. Clause 24 of the Contract allowed Seymour to do so without cause.
-
On the following day, 25 August 2017, the directors of Ostwald resolved to appoint administrators.
-
On Ostwald’s case the Contract was to be rectified by removing Special Condition 9.1. On this basis, the original cl 20.7 of the Subcontract Conditions gave effect to Item 21 of the Particulars. Item 21 required Seymour to pay Ostwald within 30 days of the end of the month in which it received Ostwald’s payment claim. Accordingly, on Ostwald’s case the due date for payment was 30 August 2017, being 30 days after the end of the month in which Seymour received the payment claim.
-
On 27 September 2017, Ostwald served the Adjudication Application on Seymour. On Seymour’s case the Adjudication Application was served too late, since the time specified by s 17(3)(d) of the Security of Payment Act for served expired on 15 September 2017, being 20 business days from the due date for payment (18 August 2017). On Ostwald’s case the Adjudication Application was served within time, as the last date for service was 27 September 2017, being 20 business day from the due date for payment (30 August 2017).
-
On 6 November 2017, the Adjudicator issued the Adjudication Determination for the Adjudicated Amount ($5,074,218.27).
-
Seymour commenced the Equity Division proceedings on 17 November 2017. On the same day Ball J granted Seymour leave to proceed against Ostwald. [14]
14. See at [50] above.
-
On 23 November 2017, the administrators of Ostwald reported to creditors that in their opinion Ostwald was insolvent and that no funds would be available to pay out unsecured creditors. The administrators recommended that Ostwald be placed in liquidation.
-
On 30 November 2017, the creditors of Ostwald resolved, pursuant to s 439C(c) of the Corporations Act, that Ostwald be wound up. The primary Judge accepted the agreed position of the parties that by reason of ss 513B(b) and 513C(b) of the Corporations Act the winding up of Ostwald is taken to have commenced on 25 August 2017, the date the administration commenced. [15] This is also common ground on the appeal.
15. Primary Judgment at [18].
-
On 11 December 2017, Ostwald filed its cross-claim in the Equity Division proceedings.
-
The hearing before the primary Judge took place on 8 and 13 March 2018 and the Primary Judgment was delivered on 5 April 2018. The separate hearing on costs took place on 18 April 2018 and the costs judgment was delivered on 21 April 2018. The orders made by the primary Judge were entered on 2 May 2018.
Rectification: Ground 1 of the appeal
-
Mr Christie SC, who appeared with Mr Hume for Seymour, placed Ground 3 of the notice of appeal at the forefront of his argument. It is, however, convenient to commence with Ground 1, which challenges the primary Judge’s conclusion that the Contract should be rectified by deleting Special Condition 1. It is common ground that unless the Contract is rectified, Ostwald’s Adjudication Application was served outside the time specified by s 17(3)(d) of the Security of Payment Act. In that event Ostwald accepts, on the authority of Chase Oyster Bar Pty Ltd v Hamo Industries Pty Ltd,[16] that compliance within the time limit specified in s 17(3)(d) of the Security of Payment Act is an essential condition for a valid adjudication application and that Ostwald’s Adjudication Application did not comply with that essential condition.
16. (2010) 78 NSWLR 393; [2010] NSWCA 190 (Chase Oyster Bar).
Primary Judgment
-
The primary Judge noted that Ostwald’s case was that cl 20.7 of the Subcontract Conditions was inserted into the Contract by Special Condition 9.1 as a result of the mutual mistake of the parties. Ostwald submitted that the terms of the Contract, as executed, did not reflect the parties’ common intention that Seymour should have 30 days from the end of the month following receipt of the payment claim to make the payment. [17]
17. Primary Judgment at [39].
(ii) a reference date under the construction contract has arisen.
-
The progress payment to which a person is entitled as and from the reference date is a payment for work done, or for work undertaken to be done where some element of advance payment has been agreed under the contract. [114] In short, a progress payment is an amount that a contract requires to be paid as part of the total price of construction work. [115]
114. Southern Han at [67] citing Quasar Constructions NSW Pty Ltd v Demtech Pty Ltd [2004] NSWSC 116; 20 BCL 276 at [34] (Barrett J).
115. Southern Han at [68] citing Co-Ordinated Construction Co Pty Ltd v JM Hargreaves (NSW) Pty Ltd (2005) 63 NSWLR 385; [2005] NSWCA 228 at [41] (Hodgson JA)
-
There is nothing in the language of s 8(1) to support an implication that the entitlement to a progress payment cannot arise unless the builder or subcontractor continues to carry out construction work under the contract. Section 8(1) refers to a person who “has undertaken to carry out construction work under the contract”. This is a reference to a contractual undertaking, not to the physical performance of work. The analysis of the High Court in Southern Han is entirely consistent with this construction of s 8(1).
-
The statutory entitlement to a progress payment does not arise until a reference date has arrived. That date is determined by the terms of the contract as that date on which a claim for a progress payment may be made in relation to work carried out or undertaken to be carried out under the contract. The reference date is:[116]
“a date set by contractual force as a date for making a contractual claim to be paid the whole or part of the contracted amount … [T]he date is … fixed by operation of one or more express provisions of the contract.”
A reference date can arise regardless of whether the claimant is actually continuing to carry out construction work under the contract on that particular date (although it may be necessary, in conformity with Southern Han, for the contract or at least the contractual entitlement to be paid, to remain in force).
116. Southern Han at [70].
-
There is also nothing in the language of s 13 of the Security of Payment Act which implies that a person can only serve a payment claim at a time when that person is actually carrying out construction work under the contract. As Southern Han expressly recognises, a claim may be made even after a contract has expired, for example, in relation to a final payment.
-
Two further points should be noted. First, the text of the Security of Payment Act distinguishes between work undertaken to be carried out and work carried out. Section 8(2), for example, refers to “work carried out or undertaken to be carried out”. [117] The reference in s 8(1) to a “person … who has undertaken to carry out construction work” contrasts with the reference in s 15(2)(b) and s 16(2)(b) to a claimant serving notice of intention to suspend “carrying out construction work”. [118] This suggests that if Parliament intended s 8(1) to be subject to a requirement that the claimant actually carry out construction work on the reference date it would have said so.
117. See also ss 9(b), 10(1) where the same expression is used.
118. See also ss 11(3) and 27(1) where the same expression is used.
-
Secondly, ss 15(2)(b) and 16(2)(b) of the Security of Payment Act apply where a respondent fails to pay the claimed amount or the unpaid portion of the scheduled amount. Those provisions permit a claimant to serve a notice of the claimant’s intention to suspend carrying out construction work. The Court in Façade said that the provisions favoured the Court’s construction of s 9(1) of the Victorian Act (NSW s 8(1)) because they “[contemplate] a claimant who is still carrying out construction work”. [119]
119. Façade at [80].
-
It is true that ss 15(2)(b) and 16(2)(b) contemplate that some claimants will be carrying out construction work when the due date for a progress payment arrives and that those claimants may wish to take advantage of the statutory entitlement to suspend construction work. But that does not mean that the provisions contemplate that an entitlement to a progress payment under s 8(1) depends on the claimant actually performing construction work under the contract on the reference date. Nor does it mean that ss 15(2) and 16(2) only permit a claimant to invoke the statutory procedures if on the due date for payment the claimant is carrying out construction work under the Contract.
-
In my opinion Mr Christie was correct to accept that the Victorian Court of Appeal was in error in construing s 9(1) of the Victorian Act (NSW s 8(1)) as creating an entitlement to a progress payment only in a person who continues to carry out construction work under a construction work. With great respect, it follows that the Court was in error in adopting this construction of the provision as the basis for the conclusion that a “claimant” for the purposes of the equivalent to ss 15(2) and 16(2) of the Security of Payment Act must be a person who continues to carry out construction work under a contract. Mr Christie was also correct to accept that his concession removes the principal basis advanced by the Victorian Court of Appeal for its construction of the legislation.
Implications
-
Mr Christie’s attempt to support the decision if not the reasoning in Façade rested on implications to be derived from the “fundamental purpose” of the Security of Payment Act to ensure the financial survival of builders. It is a permissible approach to construction to draw implications from the text, structure and evident objectives of the legislation. Thus in Probuild Constructions, the High Court considered that the language, structure and purposes of the Security of Payment Act were not consistent with allowing an adjudication determination to be quashed for non-jurisdictional error, even though the legislative text did not explicitly preclude judicial review of such a determination. [120] In Southern Han the High Court identified an important limitation implicit in the overall design of the Security of Payment Act. [121]
120. Probuild Constructions at [48].
121. Southern Han at [66]. See at [226] above.
-
Three matters were identified by the Victorian Court of Appeal that might be said to support an implication to the effect advanced by Mr Christie. The first was that a company in liquidation cannot carry out construction work or supply goods and services under a contract. [122] Accordingly “cash flow problems cease to be a concern when a company enters liquidation”. [123]
122. Façade at [84]. See at [207] above.
123. Façade at [82].
-
This proposition overlooks the express power conferred on the liquidator of a company to:
“carry on the business of the company so far as is, in the opinion of the liquidator, required for the beneficial disposal or winding up of that business.”[124]
It may not be common for the liquidator of a builder or building subcontractor, in particular, to seek to carry on the business of the company by continuing to perform work under an existing construction contract. But the circumstances in which an insolvent company is placed in liquidation vary greatly. It is possible for a construction company in liquidation to need a progress payment for much the same cash flow reasons as a company “teetering on the edge of insolvency”.
124. Corporations Act, s 477(1)(a); MGR Gronow and S Maiden, McPherson’s Law of Company Liquidation, 5th ed Thomson Reuters, at [8.2060].
-
A liquidator may consider it expedient to carry on the company’s business with a view to disposing of it or winding it up in the most beneficial manner. To this end, the liquidator may make a payment claim on behalf of the company pursuant to an existing construction contract, perhaps in respect of work completed prior to the commencement of the liquidation. The liquidator may then seek to invoke the statutory procedures for quantifying and enforcing the claim. Receipt of the progress payment could be crucial to the liquidator’s endeavours to dispose of the business beneficially, for example by enabling the company to discharge its few remaining obligations under a construction contract, thereby entitling it to a substantial payment under the contract.
-
The second matter the Victorian Court of Appeal thought significant was that once a winding up order is made in respect of a building contractor:
“it is no longer a question of the risk of insolvency; insolvency is a certainty.”[125] (Emphasis in original.)
125. Façade at [86].
-
A company is insolvent for the purposes of the Corporations Act if it is unable to pay its debts as and when they fall due. [126] Even a company wound up on the ground of insolvency[127] may ultimately be found to have a surplus of assets over liabilities. It is therefore not necessarily inevitable that creditors of a company wound up on the ground of insolvency will suffer a shortfall in recovering the moneys due to them. If the Court of Appeal was implying that the creditors of a construction company wound up in insolvency can never ultimately recover the full amounts due to them, that proposition is not correct.
126. Corporations Act, s 95A.
127. Corporations Act, ss 459A, 459P.
-
Mr Christie did not fully adopt the reasoning of the Court of Appeal on these two matters. But he did submit that Parliament must have been aware of the practical difficulties that generally confront creditors in a winding up in insolvency. That, however, is a tenuous basis on which to imply limitations on statutory language not supported by the text of the legislation.
-
The third matter relied on in Façade and adopted by Mr Christie is the interim character of the statutory entitlement. As the High Court observed in Probuild Constructions,[128] the Security of Payment Act creates an entitlement that is determined informally, summarily and quickly and then summarily enforced without prejudice to the common law rights of the parties which are to be determined “in the normal manner”.
128. Probuild Constructions at [44], citing Falgat Constructions Pty Ltd v Equity Australia Corporation Ltd (2005) 62 NSWLR 385; [2005] NSWCA 49 at [22] (Handley JA, Santow JA and Pearlman AJA agreeing).
-
The principal provisions that define the nature of a claimant’s entitlement to a progress payment are the following:
Sections 15 and 16 permit the claimant to recover the unpaid portion of the claimed amount or the scheduled amount (as the case may be) as a debt in any court of competent jurisdiction. The respondent is not entitled in the proceedings to bring a cross-claim or raise a defence in relation to matters arising under the construction contract.
Section 24 enables the claimant to obtain an adjudication certificate if the respondent fails to pay the whole or any of the adjudicated amount by the “relevant date”. Section 25 provides for the adjudication certificate to be filed as a judgment for debt in a court. If the respondent commences proceedings to set aside the judgment, the respondent is not entitled in those proceedings to bring a cross-claim, raise any defence in relation to matters under the construction contract or challenge the adjudicator’s determination (except for jurisdictional error).
Section 32 provides that nothing in Part 3 affects the rights of the parties under the construction contract proceedings arising under the contract and nothing done under Pt 3 affects any civil proceedings. However, in any proceedings in relation to a matter arising under a construction contract, the court:
“(a) must allow for any amount paid to a party to the contract under or for the purposes of this Part in any order or award it makes in those proceedings, and
(b) may make such orders as it considers appropriate for the restitution of any amount so paid, and such other orders as it considers appropriate, having regard to its decision in those proceedings.”
-
The Court in Façade considered that these provisions envisage that a respondent will be able to claim back any amounts paid to the claimant pursuant to Pt 3 of the legislation. If the claimant is in liquidation the respondent will be unlikely to be able to claim back moneys paid in satisfaction of any judgment debt because the moneys will form part of the claimant’s pool of assets to be distributed to creditors. [129] Accordingly, the interim nature of the claimant’s entitlement supports a construction that denied a claimant the entitlement to lodge a payment claim against a company in the liquidation insolvency.
129. Façade at [81].
-
The assumption underlying this argument is that it is unfair to a respondent to permit a claimant company in liquidation to recover its “interim” statutory entitlement in full while relegating the respondent to the status of an unsecured creditor, notwithstanding that s 32 of the Security of Payment Act expressly preserves the parties’ contractual rights. Although there is some support in the authorities for this assumption, its validity is by no means beyond argument. The circumstances of the present case illustrate the point.
-
In response to Ostwald’s payment claim served on 28 July 2017, Seymour served a payment schedule stating that it proposed to pay the Scheduled Amount of $2,505,237.58. The due date for payment was 18 August 2017, prior to termination of the Contract and appointment of the administrators to Ostwald. Had Seymour paid the Scheduled Amount on the due date as was its statutory obligation, its only remedy against Ostwald, once it went into liquidation, was to lodge a proof of debt as an unsecured creditor. In that situation, depending on the assets available for distribution, the “interim” payment could well have effectively become final.
-
Seymour’s contention is that it would be unfair if it had to satisfy a judgment obtained by the liquidator for Ostwald pursuant to s 16(a)(ii) of the Security of Payment Act when any claim by Seymour against Ostwald would simply be as an unsecured creditor.
-
Seymour is only in a position to advance this contention because it refused to pay the Scheduled Amount, despite stating that it proposed to do so. It is difficult to see how rewarding a head contractor for delaying a progress payment it has stated that it intends to make promotes the objectives of the Security of Payment Act.
-
If, however, enforcement of a judgment for a progress payment would unfairly prevent a respondent from effectively asserting its contractual rights against the claimant, s 553C(1) of the Corporations Act provides a mechanism that, within its field of operation, alleviates the unfairness. The High Court stated the rationale for the set-off provision in the context of bankruptcy[130] in Gye v McIntyre: [131]
“the object of set-off in bankruptcy is, in the words of Parke B. in Forster v. Wilson [132] , ‘to do substantial justice between the parties, where a debt is really due from the bankrupt to the debtor to his estate’. Where there are genuine mutual debts, credits or other dealings, it would be unjust if the trustee in bankruptcy could insist upon having 100 cents in the dollar upon the whole of the debt owed to the bankrupt but at the same time insist that the bankrupt’s debtor must be satisfied with a dividend of some few cents in the dollar on the whole of the debt owed by the bankrupt to him. It was to prevent such injustice that the ‘mutual credits’ and ‘mutual debts’, and later ‘mutual dealings’, provisions were introduced into bankruptcy legislation … To the extent necessary to achieve that legislative purpose of ‘substantial justice’ to the parties, it is established by authority that a provision such as s. 86 of the Act should be given ‘the widest possible scope’.” (Most citations omitted.)
130. Section 86 of the Bankruptcy Act 1966 (Cth) is the equivalent provision in bankruptcy to s 533C of the Corporations Act.
131. (1991) 171 CLR 609; [1991] HCA 60 at 618-619 per curiam.
132. (1843) 12 M & W 191 at 204; 152 ER 1165 at 1171.
-
White J helpfully summarised the operation of s 553C(1) of the Corporations Act in JLF Bakeries Pty Ltd (in liq) v Baker’s Delight Holdings Ltd, as follows:[133]
133. [2007] NSWSC 894; 64 ASCR 633 at [17]-[18].
“[17] Where the requirements of the section are satisfied, set-off under s 553C operates automatically … There is authority that the relevant date for determining whether the sum due from one party is to be set off against any sum due from the other party in respect of mutual dealings is the ‘relevant date’ under s 553 for determining what claims are admissible to proof against the company … That is also the date at which the winding up is taken to have commenced: ss 513B(b) and 513C(b) …
[18] Debts in respect of mutual dealings which may be set off under s 553C(1) include not only debts which are then due, but debts which are contingent and which ultimately mature into pecuniary demands. In Hiley v Peoples Prudential Assurance Co Ltd (1938) 60 CLR 468 at 497; (1938) 40 ALR 469 at 498, Dixon J said:
It is enough that at the commencement of the winding up mutual dealings exist which involve rights and obligations whether absolute or contingent of such a nature that afterwards in the events that happen they mature or develop into pecuniary demands capable of set off. If the end contemplated by the transaction is a claim sounding in money so that, in the phrase employed in the cases, it is commensurable with the cross-demand, no more is required than that at the commencement of the winding up liabilities shall have been contracted by the company and the other party respectively from which cross money claims accrue during the course of the winding-up.
…
[19] The company will owe or be owed a contingent debt if, as a result of an existing obligation, the company will be liable to pay or be entitled to receive a sum of money on the occurrence of a future event which may happen, not which must happen: Community Development Pty Ltd v Engwirda Construction Co (1969) 120 CLR 455 at 459 …” (Some citations omitted.)
-
Sifris J in Grapecorp Management Pty Ltd (in liq) v Grape Exchange Management Euston Pty Ltd [134] observed that the effect of the authorities is that:
“[66] … a contingent right or liability will only exist where there is a vested or existing right or obligation out of which, on the happening of a contingency (an event which may or may not occur), there will arise a right to be paid or an obligation to pay, a sum of money, which sum of money may be liquidated or sounding only in damages. The contingency is usually performance of an obligation.
[67] The critical matter therefore is the existing or vested right or obligation as at the date of the winding-up. This well established concept introduces a sufficient state of certainty and recognises that commerce does not stop when a company goes into liquidation …
[68] The policy behind the legislation requires a notional account to be taken as at the commencement of the winding-up. However, account must be taken of activity continuing after such date so far as such activity – eventually sounding in money – is underpinned by pre-liquidation obligations. Post-liquidation debts (and credits) that are entirely fresh transactions are dealt with differently. … However, as the authorities establish, it is proper and just that activity undertaken post-liquidation pursuant to antecedent pre-existing obligations that remain on foot should be brought to account and set off in the manner contemplated.” (Citations omitted.)
134. [2012] VSC 112; 93 ACSR 1 at [66]-[68].
-
The authorities have recognised that s 25(4) of the Security of Payment Act, which applies in proceedings commenced by a respondent to set aside a judgment based on an adjudication determination, does not prevent a respondent seeking other relief such as a stay of the judgment pending a decision on a proof of debt or a cross-claim. [135] They have also recognised that there is nothing in the Security of Payment Act to prevent a set-off available under s 553C(1) operating to satisfy a judgment obtained by a claimant under Pt 3 of the Security of Payment Act, where the claimant is in liquidation. [136]
135. Greenaways Australia Pty Ltd v CBC Management Pty Ltd [2004] NSWSC 1186 at [11] (Barrett J); Shellbridge Pty Ltd v Rider Hunt Sydney Pty Ltd [2005] NSWSC 1152 at [37] (Barrett J); Veolia at [18], [31] (McDougall J).
136. Veolia at [24].
-
In the light of these principles, it has generally been accepted that a respondent which can establish that it has a seriously arguable claim arising out of the construction contract may be able to obtain a stay of execution of a judgment obtained under Pt 3 of the Security of Payment Act or equivalent relief (such as an order requiring a claimant to provide security). [137] Such relief ordinarily may be granted only if:
“the failure to do so would have the practical effect of making permanent that which … the legislature intended [by the Security of Payment Act] to be only interim.” [138]
137. Paul Michael Pty Ltd v Urban Traders Pty Ltd [2010] NSWSC 1246 (Paul Michael) at [5] (White J); Romaldi Constructions Pty Ltd v Adelaide Interiors Linings Pty Ltd (No 2) [2013] SASCFC 124 at [75]-[79] (Blue J, Sulan and Stanley JJ agreeing), compare Neller at [39]-[41].
138. Veolia at [75]; Paul Michael at [59]-[60].
-
Having regard to the course of argument in the present case, it is not necessary to analyse further the circumstances in which a stay or similar relief might be granted. It is enough to conclude that there are mechanisms available to eliminate or at least minimize the risk of injustice to a respondent seeking to enforce contractual rights against a claimant in liquidation which has the benefit of a judgment obtained under Pt 3 of the Security of Payment Act.
-
Accordingly, in my opinion the Security of Payment Act, as a matter of construction, is capable of operating for the benefit of a builder or sub-contractor which has gone into liquidation in insolvency. To the extent that the Victorian Court of Appeal decided to the contrary in Façade, I consider, with the greatest respect, that it was plainly wrong and should not be followed.
Conclusions
-
I have reached the following conclusions:
1. The primary Judge erred in making an order for rectification of the Contract.
2. The Adjudication Application was not made within the period specified in s 17(3)(d) of the Security of Payment Act and was therefore invalid.
3. Ostwald was entitled to institute proceedings against Seymour pursuant to s 16(2)(a)(i) of the Security of Payment Act seeking to recover the unpaid portion of the Scheduled Amount as a debt.
4. The fact that Ostwald’s liquidation was deemed to have commenced before it filed its cross-claim seeking judgment against Seymour does not prevent it pursuing that claim to judgment.
-
Ostwald’s cross-appeal challenged the primary Judge’s conclusion that he had no option but to stay any judgment obtained by Ostwald by filing the Adjudication Certificate. Since the Adjudication Certificate was invalid, Order 7 made by the primary Judge cannot stand. [139]
139. See at [55] above.
-
Since I have concluded that there is no impediment at present to Ostwald obtaining summary judgment against Seymour pursuant to s 16(2)(a)(i) of the Security of Payment Act, an issue would remain as to whether any judgment so obtained should be stayed. In view of the undertaking given to the Court on behalf of Ostwald, it would seem that there is no need to address the question of a stay.
-
The most convenient course is for the parties to agree on short minutes of order giving effect to these reasons for judgment. In the absence of agreement the parties should each file draft short minutes of order together with brief written submissions in support. In the absence of agreement as to costs, the parties’ written submissions should also address the question of costs in this Court and in the Equity Division proceedings. Any dispute will be resolved on the papers.
-
The orders I propose are:
1. Direct the parties to file agreed short minutes of order within fourteen days giving effect to these reasons for judgment and dealing with the costs of the proceedings in this Court and the Equity Division.
2. To the extent that there is disagreement as to the proposed short minutes of order or costs, direct Seymour to file and serve its proposed short minutes of order (including on costs), together with written submissions in support (not to exceed five pages) within fourteen days.
3. Ostwald to file and serve its proposed short minutes of order (including on costs), together with written submissions in support (not exceeding five pages) within a further fourteen days.
-
EMMETT AJA: A significant question in this appeal concerns the interaction between the Building and Construction Industry Security of Payment Act 1999 (NSW) (Security of Payment Act) and the Corporations Act 2001 (Cth) (the Corporations Act). The appeal also raises a question as to the meaning of the phrase “adjudication application” in s 16(2)(a)(ii) of the Security of Payment Act. Finally, there is a question as to whether a building contract between the appellant and respondent should be rectified.
-
By a works sub-contract dated 6 September 2000 (the Contract), the first respondent, Ostwald Bros Pty Ltd (in Liquidation) (Ostwald), as Sub-contractor, agreed with the appellant, Seymour White Constructions Pty Ltd (Seymour), as Contractor, to perform road works near Grafton, New South Wales. Ostwald served a progress payment claim on Seymour pursuant to s 13(1) of the Security of Payment Act. Seymour responded by providing a payment schedule stating the amount it proposed to pay, pursuant to s 14 of the Security of Payment Act (the Scheduled Amount). Ostwald then purported to make an adjudication application under s 17(2)(a)(ii) of the Security of Payment Act (the Adjudication Application). The Adjudicator then purportedly made an adjudication determination pursuant to s 22 of the Security of Payment Act (the Adjudication Determination), which determined an amount due by Seymour to Ostwald (the Adjudicated Amount). Ostwald has not been paid either the Adjudicated Amount or the Scheduled Amount.
-
Seymour thereafter commenced proceedings in the Technology and Construction List of the Equity Division claiming that the Adjudication Determination was invalid. The basis for that claim was that Ostwald made the Adjudication Application outside the time limit provided for in the Security of Payment Act. In the meantime, Ostwald went into liquidation and Seymour was granted leave under s 440D of the Corporations Act to continue the proceedings against Ostwald.
-
In addition, Ostwald filed a cross-claim seeking rectification of the Contract. If the claim for rectification were to be successful, Ostwald’s Adjudication Application was made within the time prescribed by the Security of Payment Act. However, if the Contract were not to be rectified, the Adjudication Application was made out of time and was therefore invalid. In the alternative, Ostwald sought payment of the Scheduled Amount as a statutory debt under the Security of Payment Act.
-
A judge of the Equity Division (the primary judge) concluded that rectification of the Contract should be ordered and that the Adjudication Application was therefore valid. The primary judge also concluded that, if the Adjudication Determination had been invalid, Ostwald was entitled to recover the Scheduled Amount as a debt due to it under the Security of Payment Act. His Honour also concluded that, on its proper construction, the Security of Payment Act continued to apply notwithstanding the commencement of the winding up of Ostwald. However, his Honour ordered that any judgment obtained by Ostwald be stayed until the rights of the parties were finally determined, in the winding up of Ostwald, by an account of their mutual dealings under s 553C of the Corporations Act.
-
Seymour appealed from the orders made by the primary judge. Ostwald filed a cross-appeal. In its appeal, Seymour contended that the primary judge erred in holding that the Contract should be rectified and erred further in holding that Ostwald could claim payment of the statutory debt in circumstances where it had elected to make an Adjudication Application and to pursue the Adjudication Application to a determination. Seymour also contended that his Honour erred in holding that provisions of the Security of Payment Act are available to a company in liquidation.
-
In its cross-appeal, Ostwald challenged his Honour’s decision to stay any judgment obtained by it pursuant to the filing of any Adjudication Certificate. In addition, Ostwald contended that, if the Adjudication Application was void, his Honour should have ordered Seymour to pay the Scheduled Amount plus interest. Seymour filed a Notice of Contention in respect of the cross-appeal seeking to support the stay until the taking of the account required by s 553C of the Corporations Act.
-
I have had the considerable advantage of reading in draft form the proposed reasons of Sackville AJA. I agree with his Honour that the primary judge erred in concluding that the evidence supported a finding that the common intention of the parties was not reflected in the terms of the Contract and in ordering rectification. Accordingly, Ostwald did not make the Adjudication Application within the time specified by the Security of Payment Act and the Adjudication Determination was invalid and liable to be set aside.
-
It follows from that last conclusion that Ostwald was entitled to seek recovery of the Scheduled Amount pursuant to its cross claims, subject to Seymour’s contentions in relation to the interplay between the Corporations Act and the Security of Payment Act. In that regard, the primary judge declined to follow a decision of the Victorian Court of Appeal. I agree with Sackville AJA that, on its proper construction, the Security of Payment Act is capable of operating for the benefit of a builder or sub-contractor notwithstanding that the builder or sub-contractor has gone into liquidation in insolvency. I agree with Sackville AJA, with the greatest respect, that the decision of the Victorian Court of Appeal in question was plainly wrong and should not be followed.
-
I agree with Sackville AJA that the stay order made by the primary judge cannot stand and there would be no impediment for Ostwald obtaining summary judgment against Seymour under the Security of Payment Act. I agree that the orders proposed by Sackville AJA are appropriate.
**********
Endnotes
Amendments
03 October 2019 - [9] and Cover sheet - deleted [2011] 1 WLR 770 from citation of Pink Floyd Music Ltd v EMI Records Ltd [2010] EWCA Civ 1429
[10] and Cover sheet - replaced Miwa Pty Ltd v Siantan Properties Pty Ltd [2011] NSWCA 297 with Miwa Pty Ltd v Siantan Properties Pte Ltd [2011] NSWCA 297
Decision last updated: 03 October 2019
84
82
11