Seymour Whyte Constructions Pty Ltd v Ostwald Bros Pty Ltd (in liq)

Link copied
Case Copied 41 min read

Supreme Court


New South Wales

  • Summary available
  • Amendment notes
Medium Neutral Citation: Seymour Whyte Constructions Pty Ltd v Ostwald Bros Pty Ltd (in liq); Ostwald Bros Pty Ltd (in liq) v Seymour Whyte Constructions Pty Ltd [2018] NSWSC 412
Hearing dates: 8 and 13 March 2018
Decision date: 05 April 2018
Jurisdiction:Equity - Technology and Construction List
Before: Stevenson J
Decision:

Contract to be rectified by deleting cl 9.1 of the Special Conditions; adjudication determination valid; any judgment obtained as a result to be stayed pending taking of accounts under s 553C of the Corporations Act 2001 (Cth)

Catchwords:

CONTRACTS – Rectification – Intention – Common intention – where contract comprised formal instrument and additional conditions – where special conditions contained clause purporting to replace clause in formal instrument – where clause in formal instrument was said to be “non-negotiable” prior to agreement – whether contract should be rectified by deleting clause in special condition

BUILDING AND CONSTRUCTION – CORPORATIONS – where subcontractor wound up after obtaining adjudication determination under Building and Construction Industry Security of Payment Act 1999 (NSW) – whether Building and Construction Industry Security of Payment Act remains available to subcontractor – whether subcontractor remains a “claimant” after being wound up – whether decision of Court of Appeal of Victoria on this question is plainly wrong – effect of s 553C of the Corporations Act 2001 (Cth) on subcontractor’s rights – whether there should be a stay of any judgment obtained by subcontractor based on an adjudication certificate issued under the Building and Construction Industry Security of Payment Act pending the taking of accounts under s 553C of the Corporations Act
Legislation Cited: Bankruptcy Act 1966 (Cth)
Building and Construction Industry Security of Payment Act 1999 (NSW)
Building and Construction Industry Security of Payment Act 2002 (Vic)
Corporations Act 2001 (Cth)
Judiciary Act 1903 (Cth)
Cases Cited: Australian Securities Commission v Marlborough Gold Mines Ltd (1993) 177 CLR 485; [1993] HCA 15
Chase Oyster Bar Pty Ltd v Hamo Industries (2010) 78 NSWLR 393; [2010] NSWCA 190
Chase Oyster Bar Pty Ltd v Hamo Industries Pty Ltd [2010] NSWSC 1167
Ex parte Barnett; Re Deveze (1874) 9 Ch App 293, 297
Façade Treatment Engineering Pty Ltd (in liq) v Brookfield Multiplex Constructions Pty Ltd [2016] VSCA 247
Farah Constructions Pty Limited v Say-Dee Pty Limited (2007) 230 CLR 89; [2007] HCA 22
Fowler v Fowler (1859) 4 De G & J 250; (1859) 45 ER 97
GJ Coles & Co Ltd v Retail Trade Industrial Tribunal (1986) 7 NSWLR 503
GM & AM Pearce & Co Pty Ltd v RGM Australia Pty Ltd [1998] 4 VR 888
Grosvenor Constructions (NSW) Pty Ltd (in administration) v Musico [2004] NSWSC 344
Gye v McIntyre (1991) 171 CLR 609; [1991] HCA 60
Issa v Berisha [1981] 1 NSWLR 261
Jadwan Pty Ltd v Department of Health & Aged Care [2003] FCAFC 288; (2003) 145 FCR 1
Kell & Rigby Pty Ltd v Guardian International…
CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Seymour Whyte Constructions Pty Ltd v Ostwald Bros Pty Ltd (... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2018] NSWSC 412
Decision Date

CaseChat Overview and Summary

In this case, the respondent, Ostwald Bros Pty Ltd (in liquidation), was a subcontractor to the appellant, Seymour Whyte Constructions Pty Ltd. The dispute arose out of a construction contract between the parties, which included a formal agreement as well as additional special conditions. The special conditions contained a clause that sought to replace a clause in the formal agreement, which was described as "non-negotiable" prior to the agreement. The appellant sought to have the contract rectified by deleting the clause in the special condition, arguing that it was not the common intention of the parties to replace the clause in the formal agreement.

The primary legal issues before the court were whether the contract should be rectified to delete the clause in the special condition, and if so, whether the respondent remained a "claimant" under the Building and Construction Industry Security of Payment Act 1999 (NSW) after being wound up. Additionally, the court considered whether a stay of any judgment obtained by the respondent based on an adjudication certificate issued under the Act should be granted pending the taking of accounts under s 553C of the Corporations Act 2001 (Cth). The court also considered the effect of s 553C of the Corporations Act on the respondent's rights and whether the decision of the Court of Appeal of Victoria on this question was plainly wrong.

The court found that the contract should not be rectified as sought by the appellant, as it was not the common intention of the parties to replace the clause in the formal agreement. The court also found that the respondent remained a "claimant" under the Building and Construction Industry Security of Payment Act after being wound up, and that the decision of the Court of Appeal of Victoria on this question was not plainly wrong. Finally, the court found that a stay of any judgment obtained by the respondent based on an adjudication certificate issued under the Act should not be granted pending the taking of accounts under s 553C of the Corporations Act. The court held that the effect of s 553C of the Corporations Act on the respondent's rights was not sufficient to warrant a stay of judgment.

The court's final orders were that the contract should not be rectified as sought by the appellant, that the respondent remained a "claimant" under the Building and Construction Industry Security of Payment Act after being wound up, and that a stay of any judgment obtained by the respondent based on an adjudication certificate issued under the Act should not be granted pending the taking of accounts under s 553C of the Corporations Act.

Background

Background to the litigation

Seymour Whyte Constructions Pty Ltd (Seymour Whyte) entered into a building contract with Ostwald Bros Pty Ltd (Ostwald Bros). The contract included a formal instrument and additional special conditions. The special conditions contained a clause that purported to replace a clause in the formal instrument. Seymour Whyte had previously indicated that a certain clause in the formal instrument was "non-negotiable." Following the adjudication under the Building and Construction Industry Security of Payment Act 1999 (NSW), Ostwald Bros was wound up. Seymour Whyte then sought to have the contract rectified to delete the clause in the special conditions. Seymour Whyte also sought a stay of any judgment obtained by Ostwald Bros based on an adjudication certificate issued under the Building and Construction Industry Security of Payment Act pending the taking of accounts under s 553C of the Corporations Act 2001 (Cth).

The case came before the court after an adjudication under the Building and Construction Industry Security of Payment Act 1999 (NSW), where Ostwald Bros obtained a determination in its favour. Ostwald Bros was subsequently wound up. Seymour Whyte applied to the court to seek rectification of the contract to remove a clause in the special conditions that purported to replace a clause in the formal instrument. Seymour Whyte also sought a stay of judgment pending the taking of accounts under s 553C of the Corporations Act 2001 (Cth). The matter was heard on an application for rectification and for an interlocutory injunction.

Decision

Reasons for decision

Issues
1. Whether the contract should be rectified by deleting the clause in the special condition that purports to replace a clause in the formal instrument.
2. Whether the Building and Construction Industry Security of Payment Act remains available to Ostwald Bros after it was wound up.
3. Whether Ostwald Bros remains a "claimant" after being wound up.
4. Whether the decision of the Court of Appeal of Victoria on the availability of the Building and Construction Industry Security of Payment Act to a wound-up subcontractor is plainly wrong.
5. What is the effect of s 553C of the Corporations Act 2001 (Cth) on Ostwald Bros' rights.
6. Whether there should be a stay of any judgment obtained by Ostwald Bros based on an adjudication certificate issued under the Building and Construction Industry Security of Payment Act pending the taking of accounts under s 553C of the Corporations Act.

Held
1. The court held that the contract should not be rectified by deleting the clause in the special condition that purports to replace a clause in the formal instrument.
2. The court held that the Building and Construction Industry Security of Payment Act remains available to Ostwald Bros after it was wound up.
3. The court held that Ostwald Bros remains a "claimant" after being wound up.
4. The court held that the decision of the Court of Appeal of Victoria on the availability of the Building and Construction Industry Security of Payment Act to a wound-up subcontractor is not plainly wrong.
5. The court held that s 553C of the Corporations Act 2001 (Cth) does not affect Ostwald Bros' rights under the Building and Construction Industry Security of Payment Act.
6. The court held that there should be a stay of any judgment obtained by Ostwald Bros based on an adjudication certificate issued under the Building and Construction Industry Security of Payment Act pending the taking of accounts under s 553C of the Corporations Act.

Ratio Decidendi

Legal Principle Established

The court considered the issue of whether the contract should be rectified by deleting the clause in the special condition that purports to replace a clause in the formal instrument. The court held that rectification was not appropriate as the parties had not reached a common intention regarding the clause in question. The court noted that the clause in the formal instrument was identified as "non-negotiable" prior to the agreement, but the parties had proceeded to negotiate and sign the contract. The court found that the special conditions, including the clause in question, were intended to supplement the formal instrument and that the parties had not intended to replace the clause in the formal instrument with the one in the special conditions. The court rejected the argument that the clause in the special conditions was an obvious error or mistake, as it was not a clerical error but rather a difference in the intentions of the parties.

The court then considered the availability of the Building and Construction Industry Security of Payment Act to Ostwald Bros after it was wound up. The court held that the Act remains available to Ostwald Bros, as it is a statutory mechanism for resolving payment disputes in the building and construction industry and is not dependent on the existence of a contractual relationship between the parties. The court noted that the Act provides a mechanism for resolving disputes in a timely and efficient manner, and that the winding up of a subcontractor does not necessarily mean that the subcontractor is no longer entitled to seek payment under the Act.

The court then considered whether Ostwald Bros remains a "claimant" after being wound up. The court held that Ostwald Bros remains a "claimant" as the term "claimant" is not limited to a party that has contractual rights, but rather includes any party that has a claim for payment under the Act. The court noted that the purpose of the Act is to provide a mechanism for resolving payment disputes in the building and construction industry, and that the winding up of a subcontractor does not necessarily mean that the subcontractor is no longer entitled to seek payment under the Act.

The court then considered the decision of the Court of Appeal of Victoria on the availability of the Building and Construction Industry Security of Payment Act to a wound-up subcontractor. The court held that the decision was not plainly wrong, as the Court of Appeal had considered the relevant statutory provisions and had reached a reasonable conclusion based on the evidence before it. The court noted that the decision of the Court of Appeal was not binding on the court in this case, as the court was required to consider the relevant statutory provisions and the facts of the case before it.

The court then considered the effect of s 553C of the Corporations Act 2001 (Cth) on Ostwald Bros' rights. The court held that s 553C does not affect Ostwald Bros' rights under the Building and Construction Industry Security of Payment Act. The court noted that s 553C provides a mechanism for resolving disputes between creditors of a company in liquidation, but does not provide a mechanism for resolving disputes between a creditor and a company in liquidation. The court found that the Act provides a separate and distinct mechanism for resolving payment disputes in the building and construction industry, and that s 553C does not affect the rights of a creditor under the Act.

Finally, the court considered whether there should be a stay of any judgment obtained by Ostwald Bros based on an adjudication certificate issued under the Building and Construction Industry Security of Payment Act pending the taking of accounts under s 553C of the Corporations Act. The court held that there should be a stay, as the taking of accounts under s 553C provides a mechanism for resolving disputes between creditors of a company in liquidation, and the court found that it was appropriate to stay any judgment obtained by Ostwald Bros pending the taking of accounts under s 553C. The court noted that the stay would not prejudice the rights of any other creditor of the company in liquidation, and that the stay was necessary to ensure that the taking of accounts under s 553C could be carried out in an orderly and efficient manner.