CITATION:Canstruct Pty Ltd v Floreani KC & Anor [2024] NTSC 104
PARTIES:CANSTRUCT PTY LTD
v
FLOREANI KC, Nicholas
and
RSA CONTRACTORS PTY LTD
TITLE OF COURT: SUPREME COURT OF THE NORTHERN TERRITORY
JURISDICTION: SUPREME COURT exercising Territory jurisdiction
FILE NO:2023-02843-SC
DELIVERED: 11 December 2024
HEARING DATES: 29 April 2024 & 30 April 2024
JUDGMENT OF: Burns J
CATCHWORDS:
CONTRACT LAW – Construction contract – Administrative Law – Jurisdictional error – Adjudication – Construction Contracts (Security of Payments) Act 2004 (NT) – Whether the Adjudicator’s failure to determine the date on or before which the adjudicated amount to be paid was fatal to the validity of the determination – Whether the Adjudicator made a jurisdictional error in failing to determine whether a payment claim complied with the requirements of the contract – Whether the Respondent is bound by its election to commence a second application – the Adjudicator fell into jurisdictional error by misconceiving his jurisdiction by determining that the contractual prerequisites for the making of a payment claim were irrelevant
Building and Construction Industry Security of Payment Act 1999 (NSW) s 29
Building andConstruction Industry Security of Payment Act 2002 (Vic)
Construction Contracts (Security of Payments) Act 2004 (NT) ss 3, 7A, 8, 10, 11, 18, 27, 28, 29, 31, 33, 34, 35, 38, 39, 41, 43, 44, 45, 46, 49
Construction Contracts Act 2004 (WA)
Mark Aronson, Matthew Groves and Greg Weeks, Judicial Review of Administrative Action and Government Liability (Lawbook Co, 7th ed, 2022)Acohs Pty Ltd v Ucorp Pty Ltd (2012) 201 FCR 173; Alliance Contracting Pty Ltd v James [2014] WASC 212; Cat Protection Society (Vic) v Arvio Pty Ltd [2018] VSC 757; Ceerose Pty Ltd v A-Civil Aust Pty Ltd [2023] NSWCA 215; Central Australian Frack Free Alliance Inc v Minister for Environment & Anor [2024] NTSC 75; CH2M Hill Australia Pty Ltd & Another v ABB Australia Pty Ltd & Another (2016) 41 NTLR 1; Commonwealth v Verwayen (1990) 170 CLR 394; Cooper & Oxley Builders Pty Ltd v Steensma [2016] WASC 386; Express Newspapers plc v News (UK) Ltd (1990) 18 IPR 201; Forrest & Forrest Pty Ltd v Wilson (2017) 262 CLR 510; Hossain v Minister for Border Protection and Anor [2018] HCA 34; 264 CLR 123; James Engineering Pty Ltd v ABB Australia Pty Ltd and Another (2019) 42 NTLR 51; K & J Burns Electrical Pty Ltd v GRD Group (NT) Pty Ltd & Another (2011) NTLR 1; Kirk v Industrial Court (NSW) [2010] HCA 1; 239 CLR 531; LPDT v Minister for Immigration, Citizenship, Migrant Services and Multicultural Affairs [2024] HCA 12; Mandurah Enterprises Pty Ltd v Western Australian Planning Commission (2008) 38 WAR 276; Project Blue Sky Inc v Australian Broadcasting Authority (1998) 194 CLR 355; Rojo Building Pty Ltd v Jillcris Pty Ltd [2006] NSWSC 309; The Pilbara Infrastructure Pty Ltd v Economic Regulation…
Keep reading for free
Create a free CaseChat account to read Canstruct Pty Ltd v Floreani KC and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Find similar cases
Other decisions on the same topics. Each opens in a new tab.
Details
- Case
- [2024] NTSC 104
- Decision Date
CaseChat Overview and Summary
The court found that the Adjudicator did not commit a jurisdictional error by failing to specify the due date for payment in the First Determination. It was held that any error in determining the due date was not fatal, as the Adjudicator had jurisdiction to resolve the payment dispute and made a bona fide attempt to do so. The court also noted that the Adjudicator’s failure to determine whether the payment claim complied with the contract did not amount to a jurisdictional error, as the Adjudicator’s primary obligation was to resolve the payment dispute. The court further held that RSA had clearly elected to approbate and reprobate the First Determination by taking various actions consistent with treating it as valid.
The court concluded that RSA's actions, including requesting an extension of time from the Adjudicator and advising Canstruct of its intention to enforce the First Determination, demonstrated a clear and unequivocal election to approbate the First Determination. The reprobating act, if any, was inconsistent with this earlier approbating act. Given that RSA had gained the benefit of the First Determination and subsequently acted on it, the court found that RSA was bound by its election to approbate and reprobate the First Determination. The court found that the Adjudicator's failure to determine the due date for payment did not invalidate the First Determination.
The court ordered that the First Determination was valid and binding on the parties. RSA was granted an order enforcing the First Determination against Canstruct, and Canstruct was ordered to pay the adjudicated amount, including interest at the prescribed rate from the date the payment was due until the date of satisfaction of the judgment.
Background
Background to the litigation
Decision
Reasons for decision
Ratio Decidendi
Legal principle established
Finally, RSA submitted that it is difficult to conceive how any error by the Adjudicator in determining, or failing to determine, the date for payment of the adjudicated amount could amount to a jurisdictional error such as to invalidate the determination. It submitted that any error of reasoning made by the Adjudicator in deciding to resolve the payment dispute will necessarily be an error that is made within the Adjudicator’s jurisdiction, taking into account:a) there is no issue that a payment dispute exists and the Adjudicator has jurisdiction, and as a result is obliged to determine that payment dispute;b) the Adjudicator made a bona fide attempt to discharge their duty and determine the payment dispute; andc) the terms of that determination are in accordance with s 33(1)(b) in that they identify that Canstruct, as a party to the payment dispute, is liable to make a payment, the amount it is liable to pay, and the date on which it was due to be paid.Consideration In the Supplemental Determination, the Adjudicator argued that he had, in fact, complied in the First Determination with the requirement that he state a date on or before which Canstruct was obliged to pay the adjudicated amount. In the First Determination, under the heading “Interest”, the Adjudicator said, at [239] – [242]:Pursuant to section 35(1) of the Act, an Adjudicator may determine that interest must be paid on the amount the subject of the determination, either in accordance with the terms of the relevant contract or otherwise from the date the payment dispute arose up to the date of the determination at a rate not greater than that prescribed by the Regulations.There is no prescribed rate in the Subcontract. clause (sic) 7 of the Schedule to the Act provides that interest to be paid from the day after the relevant amount is due until it is paid. The rate of interest is that prescribed by the Regulations. Regulation 9 prescribes the rate as that applicable under section 85 of the Supreme Court Act 1961 (NT), which is currently 8% per annum.I am satisfied that the appropriate rate is that prescribed by the Regulation.Therefore, under section 35(1)(a) of the Act, Canstruct should pay interest at the rate of 8% per annum on the GST exclusive amount, not the GST inclusive amount from 15 Business Days after 23 December 2022 onwards, being the date that payment was due, but not pay in accordance with clause 42.1 of the Subcontract. In the Supplemental Determination, the Adjudicator referred to paragraph 242 of the First Determination, set out above, and went on to say, at [23] – [25]:On the basis of the above paragraph, I consider I have determined the due date for payment. However, I accept that it is not clear because I have neglected to include the actual date. This was an accidental slip or omission.15 Business Days after 23 December 2022 is 17 January 2023.In exercise of section 43(2)(a) of the Act I determine for the purpose of section 38(1)(c)(i) that the due date for payment is and was 17 January 2023.