Cirrus Real Time Processing Systems Pty Limited v Hawker Pacific Pty Ltd

Link copied
Case Copied 74 min read

FEDERAL COURT OF AUSTRALIA

Cirrus Real Time Processing Systems Pty Limited v Hawker Pacific Pty Ltd [2024] FCA 763

File number: NSD 1889 of 2019
Judgment of: KENNETT J
Date of judgment: 12 July 2024
Catchwords:

CONTRACTS – formation – where parties engaged in negotiations – where respondents “committed” to subcontract the applicant if successful tenderer for work from New Zealand Defence Force – where respondents ultimately subcontracted a third party to perform relevant work – whether parties reached consensus on terms of subcontract – whether alleged contract uncertain as mere agreement to agree – whether parties intended to be legally bound

CONTRACTS – interpretation – rectification by construction – where most likely that typographical error made during drafting process – where document not absurd – whether contract should be corrected by construction

CONTRACTS – interpretation – meaning of “engage” – where applicant’s construction commercially unreasonable and onerous

CONTRACTS – implied terms – where alleged implied terms would impose duties to ensure the subcontracting of the applicant – where alleged implied terms would impose duties that would unreasonably restrict the respondents’ commercial liberty – where alleged implied terms not so obvious they go without saying – whether alleged terms were implied

ESTOPPEL – estoppel by convention – where alleged assumption is about future conduct, not state of affairs – where alleged estoppel would convert non-contractual representation into binding promise – whether respondents estopped from denying the existence of a contract  

Legislation: Competition and Consumer Act 2010 (Cth), ss 4, 82, 131, Sch 2 (Australian Consumer Law) ss 18, 236
Judiciary Act 1903 (Cth) s 39B
Cases cited:

Austotel Pty Ltd v Franklins Selfserve Pty Ltd (1989) 16 NSWLR 582

Australian Broadcasting Com­ mission v Australasian Performing Right Association Ltd (1973) 129 CLR 99

Australian Broadcasting Corporation v XIVth Commonwealth Games Ltd (1988) 18 NSWLR 540

Australian Securities and Investments Commission v Cassimatis (No 8) [2016] FCA 1023; 336 ALR 209

Bache v Proctor (1780) 99 ER 247; 1 Doug 382

Banque Brussels Lambert SA v Australian National Industries Ltd (1989) 21 NSWLR 502

Booker Industries Pty Ltd v Wilson Parking (Qld) Pty Ltd (1982) 149 CLR 600

Branir Pty Ltd v Owston Nominees (No 2) Pty Ltd [2001] FCA 1883; 117 FCR 424

Butt v M'Donald (1896) 7 QLJ 68

Chartbrook Ltd v Persimmon HomesLtd [2009] UKHL 38; AC 1101

Charter Reinsurance Co Ltd v Fagan [1997] AC 313

Codelfa Construction Pty Ltd v State Rail Authority of New South Wales (1982) 149 CLR 337

Darlington Futures Ltd v Delco Australia Pty Ltd (1986) 161 CLR 500

DHJPM Pty Ltd v Blackthorn Resources Ltd [2011] NSWCA 348; 83 NSWLR 728

Ermogenous v Greek Orthodox Community of SA Inc [2002] HCA 8; 209 CLR 95

Feldman v GNM Australia Ltd [2017] NSWCA 107

Fitzgerald v Masters (1956) 95 CLR 420

Franklins Pty Ltd v Metcash Trading Ltd [2009] NSWCA; 76 NSWLR 603

Gemmell Power Farming Co Ltd v Nies (1935) 35 SR (NSW) 469

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Cirrus Real Time Processing Systems Pty Limited v Hawker Pac... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2024] FCA 763
Decision Date

CaseChat Overview and Summary

In the matter of Cirrus Real Time Processing Systems Pty Limited v Hawker Pacific Pty Ltd, the Federal Court was tasked with determining the existence and terms of a contract between the parties. Cirrus, the applicant, alleged that a contract was formed with Hawker Pacific, the respondent, on 21 December 2016, whereby Hawker Pacific would subcontract certain work to Cirrus if Hawker Pacific was successful in tendering for a project with the New Zealand Defence Force. Hawker Pacific, however, ultimately subcontracted a third party, leading Cirrus to claim breach of contract. The court was required to decide whether a binding contract existed, the meaning of certain terms, and if any terms were implied by law or equity. Additionally, Cirrus sought to rectify a typographical error in the contract documents.

The court found that no binding contract existed between the parties. It held that the negotiations did not result in a consensus on all essential terms, rendering the alleged contract uncertain. The court also rejected Cirrus's request to rectify a typographical error, finding that such an error was unlikely given the context. Regarding the term "engage," the court found Cirrus's interpretation to be commercially unreasonable and therefore rejected it. The court also dismissed Cirrus's claims of implied terms and estoppel, stating that any such terms or estoppel would unreasonably restrict Hawker Pacific's commercial liberty and were not obvious enough to be implied. As a result, the court dismissed Cirrus's application and ordered Cirrus to pay the respondents' costs.

The final orders of the court were that the application be dismissed and that the applicant pay the respondents' costs as agreed or assessed. The dismissal of the application meant that Cirrus's claims for breach of contract, rectification, and estoppel were not upheld. The order for costs reflected the outcome of the proceedings, ensuring that the respondents were compensated for the legal expenses incurred in defending the case.

Orders

Orders of the court

1. The application be dismissed.

2. The applicant pay the respondents’ costs as agreed or assessed.

Note: Entry of orders is dealt with in Rule 39.32 of the Federal Court Rules 2011.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

During the trial, Cirrus abandoned its claim that the respondents contravened s 18 of the ACL. The withdrawal of that claim does not affect the jurisdiction of the Court in the matter. Once federal jurisdiction over a matter is established, the Court retains its authority to decide the whole matter even if the federal aspect of the claim is withdrawn: Moorgate Tobacco Company Ltd v Philip Morris Ltd (1980) 145 CLR 457 at 477 (Stephen, Mason, Aickin and Wilson JJ); see also RNB Equities Pty Ltd v Credit Suisse Investment Services (Australia) Ltd [2019] FCA 760; 370 ALR 88 at [23] (Anderson J)).EVIDENCE Cirrus tendered a significant amount of documentary evidence and relied on statements made and affidavits sworn by Peter Freed, who is its managing director and was closely involved in the events out of which the claims arise. Mr Freed was cross-examined, although it has not been necessary for me to refer to his cross-examination in any significant way in these reasons. Cirrus also relied on expert evidence, prepared by Mr John Temple-Cole, to prove its case on loss and damage. Mr Temple-Cole was also cross-examined. For reasons I explain later, I have not assessed Cirrus’s loss. The respondents did not adduce any evidence.THE CLAIM IN CONTRACT Cirrus alleges that a contract was created on 21 December 2016; that it contained various express terms; and that it also contained an implied term. Cirrus alleges that each of those terms was breached and that it has suffered damage as a result. I have addressed the issues in that order. However, before I do so, it is necessary to pay some attention to the pleadings because the respondents indicated that they would hold Cirrus strictly to its pleaded case.The pleaded case in contract Cirrus filed a Statement of Claim which was amended twice, including on the last day of the hearing. By the end of the hearing, Cirrus’s Further Amended Statement of Claim (FASOC) alleged that a contract was created on 21 December 2016 as follows:13.On 21 December 2016 the applicant and the first and second respondents entered into a written agreement confirmed in correspondence of that date (teaming agreement).Particulars(a)Letter from the first and second respondents to the applicant dated 21 December 2016(b)Letter from the applicant to the first and second respondents dated 21 December 2016 Cirrus then pleads that the agreement contained several express terms as follows:14.It was an express term of the teaming agreement that in consideration for the applicant permitting the first and second respondents to disclose, use, incorporate or combine the information from the Version 4 Quotation in the Tender, the first and second respondents would enter a subcontract with the applicant on the basis of the Version 4 Quotation if:(a) either respondent was selected to enter contract negotiations; and(b)subsequently entered a contract with the Ministry of Defence inclusive of training system and ongoing services (Prime Contract),(Express Term).…14A.The teaming agreement incorporated by reference the terms of the Version 4 Quotation. Particulars(a)Letter from the first and second respondents to the applicant dated 21 December 2016, Reference A(b)Letter from the applicant to the first and second respondents dated 21 December 2016, Ref A14B.It was an express term of the Version 4 Quotation that, in the event that the first and second respondents entered into the Prime Contract with the Ministry of Defence in terms that differed from the Version 4 Quotation including as to price, the parties agreed that:(a)the respondents would, as prime contractor, absorb the corresponding quantum of commercial cost or risk or both;(b)the respondents could propose changes to the particular terms contained in section 10 of the Version 4 Quotation, including to attain better alignment between the terms of the Version 4 Quotation and the corresponding terms of an eventual Prime Contract;(c)in the event that the respondents proposed changes to terms of section 10 of the Version 4 Quotation, the applicant could propose a price adjustment to the prices quoted at section 10.4 and/or the schedule described at section 10.3.5 of the Version 4 Quotation; and(d)if the respondents did not agree to the proposed price adjustment, the terms of section 10 of the Version 4 Quotation would remain unchanged.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.