Romaldi Constructions Pty Ltd v Adelaide Interior Linings Pty Ltd (No 2)

Link copied
Case Copied 49 min read

SUPREME COURT OF SOUTH AUSTRALIA

(Full Court: Civil)

ROMALDI CONSTRUCTIONS PTY LTD v ADELAIDE INTERIOR LININGS PTY LTD  (No 2)

[2013] SASCFC 124

Judgment of The Full Court

(The Honourable Justice Sulan, The Honourable Justice Blue and The Honourable Justice Stanley)

19 November 2013

CONTRACTS - BUILDING, ENGINEERING AND RELATED CONTRACTS - REMUNERATION - STATUTORY REGULATION OF ENTITLEMENT TO AND RECOVERY OF PROGRESS PAYMENTS - ADJUDICATION OF PAYMENT CLAIMS

PROCEDURE - JUDGMENTS AND ORDERS - ENFORCEMENT OF JUDGMENTS AND ORDERS

EQUITY - EQUITABLE REMEDIES - INJUNCTIONS - INTERLOCUTORY INJUNCTIONS - JURISDICTION

An adjudicator determined under the Building and Construction Industry Security of Payment Act 2009 (SA) that the appellant, Romaldi Constructions Pty Ltd, was liable to pay a progress payment to the respondent, Adelaide Interior Linings Pty Ltd, for work performed under a construction contract. Romaldi sued Linings in the District Court claiming damages for breach of contract.

Romaldi sought and obtained an interlocutory injunction from a Judge of the District Court restraining Linings from obtaining an adjudication certificate for the adjudication amount. On Linings' appeal, a Judge of the Supreme Court discharged that injunction.

Upon Linings obtaining an adjudication certificate and filing it in the Magistrates Court as a judgment for debt, Romaldi sought a stay of execution until determination of its damages claim in the District Court. A Magistrate summarily dismissed the application for a stay.

Romaldi appeals against the discharge of the injunction by the Judge on appeal and against the refusal of the stay application by the Magistrate. The issues raised by the appeals are:

1.  whether there was a juridical basis to grant an interlocutory injunction restraining Linings obtaining an adjudication certificate;

2.  whether Romaldi made out a ground for grant of an interlocutory injunction restraining Linings from obtaining an adjudication certificate;

3.  whether Romaldi made out a ground for grant of a stay of execution of judgment founded on the adjudication certificate;

4.  whether the Judge of the Supreme Court erred in concluding that the proper exercise of discretion on the material before the Judge of the District Court would have been to deny a stay of execution of the judgment; and

5.  whether the Magistrate erred in not hearing and determining the stay application on its merits.

Held by Blue J (Sulan and Stanley JJ agreeing) dismissing both appeals:

1.  An interlocutory injunction generally may be granted to preserve the subject matter of the substantive action, to avoid the result of the substantive action being rendered nugatory or to protect the integrity of the court’s processes once set in motion (at [65]-[67]).

2.  If there was a juridical basis for the grant of an interlocutory injunction in the present case, it must have been to avoid the result of the substantive action being rendered nugatory but it is unnecessary to decide the question whether this comprises a proper judicial basis for an interlocutory injunction (at [69]).

3.  If no interlocutory injunction were granted, Romaldi would have remained at liberty to apply for a…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Romaldi Constructions Pty Ltd v Adelaide Interior Linings Pt... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2013] SASCFC 124
Decision Date

CaseChat Overview and Summary

This matter concerned appeals by Romaldi Constructions Pty Ltd against decisions of a Magistrate and a Judge of the District Court. The dispute arose from a subcontract between Romaldi and Adelaide Interior Linings Pty Ltd for the supply and installation of linings for a college project. Linings submitted progress claims, which Romaldi disputed, alleging breaches of the subcontract by Linings. Romaldi subsequently took the work out of Linings' hands and engaged others to complete it. Linings then made a payment claim under the *Building and Construction Industry Security of Payment Act 2009* (SA) (the Act), which proceeded to adjudication. The adjudicator determined that Linings was entitled to $48,194 plus interest and adjudication fees. Romaldi commenced proceedings in the District Court seeking damages for breach of contract.

The appeals raised three principal issues for determination by the Full Court of the Supreme Court of South Australia. Firstly, whether grounds were established for an interlocutory injunction to restrain Linings from obtaining an adjudication certificate. Secondly, whether grounds were established for a stay of execution of the judgment founded on the adjudication certificate. Thirdly, whether the Judge on appeal erred in concluding that the proper exercise of discretion at first instance would have been to deny a stay of execution.

The Court considered the principles governing interlocutory injunctions and stays of execution in the context of the Act. It was held that the Magistrate had erred in their approach to the application for a stay of execution. However, the Full Court found that, notwithstanding this error, the appeal against the Magistrate's orders should be dismissed. Similarly, the appeal against the Judge's decision was dismissed.

The Full Court dismissed both appeals.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

The appeals raise for determination three principal issues.1.Was there a ground established for an interlocutory injunction restraining Linings from obtaining an adjudication certificate?2.Was there a ground established for a stay of execution of the judgment founded on the adjudication certificate?3.Did the Judge on appeal err in concluding that the proper exercise of the discretion on the material before the Judge at first instance would have been to deny a stay of execution?Background In late August 2012, Romaldi and Linings entered into a subcontract for the supply and installation of linings for the Burc College Project for a contract price of $88,398,[2] subsequently adjusted to $94,825 (“the Subcontract”). It was a term of the Subcontract that Romaldi pay monthly progress claims submitted no later than the 25th day of the month by the end of the following month. Romaldi paid to Linings an advance payment of $10,000.[2] All dollar figures are inclusive of GST for consistency. On 22 September 2012, Linings submitted to Romaldi a progress claim for September for $48,455. On 21 October 2012, Linings submitted to Romaldi a progress claim for October for $10,746. On 21 October 2012, Romaldi responded to Linings’ September progress claim by assessing the value of work to date at $6,070, being less than the $10,000 advance payment. By October 2012, Linings was alleging that Romaldi was in breach of the subcontract by failing to pay the September progress claim and Romaldi was alleging that Linings was in breach of the subcontract by not complying with the program for progress of the works. On 5 November 2012, Linings re-submitted its September progress claim as a payment claim under section 13 of the Act. In due course, Romaldi responded with a payment schedule asserting that no amount was due. On 20 November 2012, Romaldi wrote to Linings stating that it intended to take the work out of Linings’ hands due to breaches of the Subcontract by non‑compliance with the program. Romaldi thereafter obtained materials and engaged labour subcontractors to complete the works at a claimed cost of $151,949. On 11 December 2012, Linings applied under section 17 of the Act for adjudication of its payment claim for September. Marisa Toffoli was appointed adjudicator. On 13 February 2013, Ms Toffoli determined under section 22 of the Act that Linings was entitled to $48,194 plus interest from 5 December 2012 plus adjudication fees. Pursuant to the determination, Romaldi was required to pay Linings the adjudicated amount within five business days of 13 February 2013. If payment did not occur within that time, Linings was entitled to apply for an adjudication certificate and file it as a judgment debt pursuant to section 25 of the Act. On 20 February 2013, Romaldi instituted the District Court action. Romaldi claimed damages for breach of contract based on the difference between the adjusted Subcontract price ($94,825) and the total cost to complete the works comprising amounts paid or to be paid to Linings of $11,000 plus $48,194 (if paid) and amounts paid to third parties of $151,949.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

It follows that, notwithstanding his error in approach, the appeal against the orders made by the Magistrate should be dismissed.Conclusion I would dismiss both appeals. I would hear the parties as to consequential orders. STANLEY J: I would dismiss both appeals. I agree with the reasons of Blue J.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.