Supreme Court
New South Wales
Medium Neutral Citation: Ceerose Pty Limited v A-Civil Aust Pty Ltd (No 5) [2023] NSWSC 1012 Hearing dates: 14 August 2023 Decision date: 24 August 2023 Jurisdiction: Equity - Technology and Construction List Before: Ball J Decision: See [44] to [45]
Catchwords: BUILDING AND CONSTRUCTION — Adjudication of payment claim under Security of Payment Act — Stay of judgment — Whether judgment based on an adjudication determination should be stayed pending determination of an appeal that has been heard — Whether judgment should be stayed pending determination of proceedings under the construction contract — Whether unfavourable inferences should be drawn regarding the claimant’s financial position — Where evidence falls short of proving claimant will be unable to repay amounts if it is unsuccessful in the contractual proceedings
Legislation Cited: Building and Construction Industry Security of Payment Act 1999 (NSW)
Cases Cited: A‑Civil Aust Pty Ltd v Ceerose Pty Ltd [2023] NSWCA 144
Ceerose Pty Ltd v A‑Civil Aust Pty Ltd [2023] NSWSC 239
Ceerose Pty Ltd v A‑Civil Aust Pty Ltd (No 2) [2023] NSWSC 401
Hakea Holdings Pty Limited v Denham Constructions Pty Ltd [2016] NSWSC 1120
Klewer v Official Trustee in Bankruptcy (No 2) [2010] NSWCA 258
R J Neller Building Pty Ltd v Ainsworth [2009] 1 Qd R 390; [2009] QCA 397
Romaldi Constructions Pty Ltd v Adelaide Interior Linings Pty Ltd (No 2) [2013] SASCFC 124
Veolia Water Solutions v Kruger Engineering [No 3] [2007] NSWSC 459
Category: Procedural rulings Parties: Ceerose Pty Limited (Plaintiff | First Cross-Defendant)
A-Civil Aust Pty Ltd (First Defendant | Cross-Claimant)
John Tuhtan (Second Defendant | Second Cross Defendant)
ABC Dispute Resolution Service (Third Defendant)Representation: Counsel:
Solicitors:
S Robertson SC with J Wright (Plaintiff | First Cross-Defendant)
FP Hicks SC with L Gor (First Defendant | Cross-Claimant)
Salim Rutherford Lawyers (Plaintiff | First Cross-Defendant)
M&A Lawyers (First Defendant | Cross-Claimant)
Submitting Appearances (Second Defendant | Second Cross Defendant and Third Defendant)
File Number(s): 2022/217806 and 2022/236818 Publication restriction: None
JUDGMENT
Introduction
-
These proceedings concern two adjudication determinations obtained by the defendant subcontractor (A‑Civil) against the plaintiff builder (Ceerose) under the Building and Construction Industry Security of Payment Act 1999 (NSW) (the Act) in respect of work done on two projects, one in York Street, Sydney and the other in Greenknowe Avenue, Elizabeth Bay.
-
In relation to the York Street project, the adjudicator determined that the amount of $2,045,457.97 was payable by Ceerose to A‑Civil. In relation to the Elizabeth Bay project, the adjudicator determined that an amount of $349,324.36 was payable by Ceerose to A‑Civil. The former determination was made on 2 August 2022. The latter was made on 11 July 2022.
-
Ceerose sought in these proceedings orders quashing the two adjudication determinations on the ground that they were affected by jurisdictional error. It also sought final injunctions restraining A‑Civil from seeking to enforce the adjudication determinations.
-
The proceedings were heard by Darke J. In judgments delivered on 20…
Keep reading for free
Create a free CaseChat account to read Ceerose Pty Limited v A-Civil Aust Pty Ltd (No 5) and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2023] NSWSC 1012
- Decision Date
CaseChat Overview and Summary
The legal issues before the court included whether the judgment should be stayed pending the determination of an appeal that had already been heard and the determination of the contractual proceedings. Another issue was whether unfavourable inferences should be drawn regarding Ceerose’s financial position if the evidence did not conclusively prove that Ceerose would be unable to repay the amounts if it was unsuccessful in the contractual proceedings. The court had to weigh the competing interests of enforcing prompt payment legislation against the rights of the respondent to have the dispute resolved comprehensively through the contractual dispute resolution process.
The court found that the judgment should not be stayed pending the outcome of the appeal, as the appeal process had already been initiated and was being determined. Regarding the contractual proceedings, the court held that there was insufficient evidence to draw unfavourable inferences about Ceerose’s financial position. The court emphasised that the evidence must demonstrate a clear inability to repay, which was not established in this case. Consequently, the court dismissed the application to stay the judgment and ruled in favour of Ceerose.
The final orders of the court confirmed that the judgment for Ceerose Pty Limited would stand, and the application for a stay was dismissed. A-Civil Aust Pty Ltd was ordered to pay Ceerose’s costs of the application. This decision underscored the importance of the Security of Payment Act in ensuring timely payments in the construction industry, while also considering the rights of respondents in contractual disputes.