SUPREME COURT OF SOUTH AUSTRALIA
(Civil: Application)
MAXCON CONSTRUCTIONS P/L v VADASZ & ORS
[2016] SASC 148
Judgment of The Honourable Justice Stanley
9 September 2016
CONTRACTS - BUILDING, ENGINEERING AND RELATED CONTRACTS - REMUNERATION - STATUTORY REGULATION OF ENTITLEMENT TO AND RECOVERY OF PROGRESS PAYMENTS - ADJUDICATION OF PAYMENT CLAIMS
ADMINISTRATIVE LAW - JUDICIAL REVIEW - POWERS OF COURTS UNDER JUDICIAL REVIEW LEGISLATION - STAY OF PROCEEDINGS AND INTERLOCUTORY RELIEF
BANKRUPTCY - SCOPE AND POLICY OF LEGISLATION - GENERALLY
In this matter there are two applications before the Court. The applications arise out of a dispute over progress payments for building work.
The first defendant is a piling contractor and at all relevant times an undischarged bankrupt. The plaintiff is a builder and head contractor for a development known as Bohem Apartments in Wright Street, Adelaide. On or about 15 December 2015 the plaintiff and the first defendant entered into a written contract for the first defendant to supply and install piling for the Bohem Apartments development. The contract price was the sum of $782,100 (inclusive of GST).
There is an issue between the parties as to whether the first defendant disclosed to the plaintiff prior to entering into the contract that he was an undischarged bankrupt.
The first defendant completed the piling works in about mid-February 2016. On 25 February 2016 the first defendant served on the plaintiff a payment claim seeking payment of $204,864.55 (inclusive of GST) pursuant to the contract. On 8 March 2016 the plaintiff issued a payment schedule for the amount of $141,163.55 (inclusive of GST). On 18 March 2016 the first defendant made an application for adjudication in respect of the payment claim.
On 6 April 2016 the third defendant made a decision on the adjudication in the amount of $214,614.35. The plaintiff failed to pay the first defendant this amount. On 8 July 2016 Kourakis CJ made an order that the plaintiff was to pay into this Court the sum of $215,030.85. The plaintiff paid that sum into court.
The first defendant seeks orders that he be granted leave to register judgment against the plaintiff in accordance with an adjudication certificate issued pursuant to s 22 of the Building and Construction Industry Security of Payment Act 2009 (SA) (the Act) in the sum of $215,030.85 and an order for payment to him out of the Supreme Court Suitor’s Fund in the sum of $141,163.55. There is no opposition to the application for leave to register the judgment pursuant to the adjudication certificate in the sum of $215,030.85. The plaintiff has brought an application for judicial review seeking to have the adjudication set aside and, in the meantime, seeks an interlocutory order for a stay of the adjudicator’s decision made pursuant to s 22 of the Act.
Held:
1. The plaintiff has demonstrated an arguable case on the application for judicial review. It is arguable on the material before the court that the adjudicator lacked the jurisdiction to make a determination pursuant to…
Continue reading Maxcon Constructions P/L v Vadasz
Sign in free to access the full text
- AGLC
- Maxcon Constructions P/L v Vadasz [2016] SASC 148
- Case
- [2016] SASC 148
- Decision Date
CaseChat Overview and Summary
The primary legal issues addressed by the court included whether the plaintiff had a genuine set-off claim against the first defendant exceeding $165,583.18, and whether the first defendant had disclosed his status as an undischarged bankrupt before entering into the contract. The court considered evidence from both parties, including affidavits and contract amendments, to assess these issues. The court examined the statutory framework under which the adjudication occurred, focusing on the purpose of the Act to ensure progress payments are made and recovered effectively.
The court reasoned that while the plaintiff had claims against the first defendant, the risk of the plaintiff not recovering some of the amount in its payment schedule, coupled with the policy of the Act, necessitated a refusal of the stay and an order for payment to the first defendant. The court found no merit in the plaintiff's argument regarding the first defendant's failure to disclose his bankruptcy status and determined that the adjudication decision should be enforced.
The court ordered the dismissal of the plaintiff's application for a stay, granted the first defendant leave to register judgment in the sum of $215,030.85, and ordered payment out of the Supreme Court Suitor’s Fund to the first defendant in the sum of $141,163.55. The court also directed the parties to address the issue of costs.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.