CE Hyde Park Pty Ltd v The Returned and Services League (New South Wales Branch)

Case [2025] NSWSC 416


Supreme Court


New South Wales

Medium Neutral Citation: CE Hyde Park Pty Ltd v The Returned and Services League (New South Wales Branch) [2025] NSWSC 416
Hearing dates: 7-8 April 2025
Date of orders: 6 May 2025
Decision date: 06 May 2025
Jurisdiction:Equity - Commercial List
Before: Williams J
Decision:

See orders at [195].

Catchwords:

CONTRACTS – construction – contract for the sale and purchase of land entered into upon the plaintiff purchaser exercising call option at the end of four year option period during which the purchaser had obtained development consent for the property – purchaser issued notice to vendor nominating date for completion of the contract 18 months in the future – whether the contract, properly construed, entitled the purchaser to issue that notice – whether the relevant clause of the contract should be construed in a manner that departs from the language used to correct an obvious mistake or absurdity – dispute concerning the validity of a notice issued by purchaser appointing a valuer for the purpose of a contractual process to determine the residual land value as an integer of the calculation of the price payable to the vendor on completion – whether purchaser’s notice served within the time provided by the contract for the purchaser to give notice appointing a valuer – whether time stipulation of the essence – various other disputes concerning the construction and operation of the contract.

Legislation Cited:

N/A

Cases Cited:

Chevron (TAPL) Pty Ltd v Pilbara Iron Company (Services) Pty Ltd (2021) 51 WAR 102; [2021] WASCA 193

Dexus Capital Funds Management Pty Ltd v Macquarie Retail Pty Ltd as trustee for Macquarie Retail Trust [2025] NSWCA 68

Donau Pty Ltd v AWD Shipbuilder Pty Ltd (2019) 101 NSWLR 679; [2019] NSWCA 185

HDI Global Specialty SE v Wonkana No 3 Pty Ltd

(2020) 104 NSWLR 634; [2020] NSWCA 296

J & P Marlow (No 2) Pty Ltd v Hayes & McCabe [2023] NSWCA 117(2023) 112 NSWLR 29

James Adam Pty Ltd v Fobeza Pty Ltd (2020) 103 NSWLR 850; [2020] NSWCA 311

Miwa Pty Ltd v Siantan Properties Pte Ltd [2011] NSWCA 297

Seymour Whyte Constructions Pty Ltd v Ostwald Bros Pty Ltd (in liq) (2019) 99 NSWLR 377; [2019] NSWCA 11

Zhong v Guan [2024] NSWCA 300

Texts Cited:

P Herzfeld and T Prince, Interpretation (2nd ed, 2020, Thomson Reuters)

Category:Principal judgment
Parties: CE Hyde Park Pty Ltd (ACN 646 157 824) (Plaintiff/Cross-Defendant)
The Returned and Services League of Australia (New South Wales Branch) (ABN 78 368 138 161) (Defendant/Cross-Claimant)
Representation:

Counsel:
Mr A J McInerney SC with Mr D Robertson (Plaintiff/Cross-Defendant)
Mr D Barnett SC with Ms N D Oreb (Defendant/Cross-Claimant)

Solicitors:
Mills Oakley (Plaintiff/Cross-Defendant)
Corrs Chambers Westgarth (Defendant/Cross-Claimant)
File Number(s): 2025/94970
Publication restriction: N/A

Judgment

Introduction

  1. These proceedings concern a contract entered into on 5 December 2024 for the sale and purchase of the land known as 262 Castlereagh Street, Sydney and 271 Elizabeth Street, Sydney (the Property) between The Returned and Services League of Australia (New South Wales Branch) (RSL) as vendor and CE Hyde Park Pty Limited (CEHP) as purchaser (the Contract).

  2. The Contract came into existence as a result of CEHP exercising its call option under a Deed of Put and Call Option that had been entered into on 6 December 2020 between RSL (as grantor) and CEHP (as grantee) (the Option Deed).

  3. The parties have fallen into dispute about the date on which the Contract is to be completed, about the contractual process for determining the amount of the price payable to RSL on completion, about whether CEHP is required to consent to the registration of a certain lease that RSL has granted to a related entity over part of the Property (the Board Room Lease), and about whether CEHP is required to reimburse RSL for certain valuation costs that it has incurred under the Contract.

  4. CEHP commenced these proceedings by Summons filed on 11 March 2025 seeking declaratory and other relief concerning the date on which the Contract is to be completed and the validity of its appointment of a valuer for the purpose of a contractual procedure to determine an integer of the price to be paid to RSL on completion.

  5. RSL filed a Cross-Summons on 17 March 2025 seeking a declaration that it is entitled to issue a notice to complete the Contract, a further declaration that CEHP is required to consent to the registration of the Board Room Lease and an order requiring it to do so within two days, and judgment in the amount of the valuation costs incurred by RSL under the Contract that it contends CEHP is liable to pay.

Salient facts

The Property

  1. In or before 2020, RSL published an Information Memorandum:

“… seeking proposals from experienced developers and investors for the purchase of 271 Elizabeth Street (Hyde Park Inn) and 262 Castlereagh Street, Sydney, NSW.”

  1. As explained in the Information Memorandum, those two properties adjoin one another. At the time of the Information Memorandum, 262 Castlereagh Street was vacant and was not subject to any leases or licences. RSL was operating the Hyde Park Inn business at 271 Elizabeth Street. The whole of the Property was the subject of an existing development consent for the construction of a new hotel at 262 Castlereagh Street, the refurbishment of the rooms in the Hyde Park Inn at 271 Elizabeth Street, and the connection of the two buildings. That development consent would expire on 18 May 2022. The Information Memorandum described the Property as well suited to a range of uses, including luxury apartments, a four-star hotel, or an A-Grade office building, given its location opposite Hyde Park, its close proximity to public transport, and its proximity to commercial precincts, schools and universities, several retail and entertainment precincts, Chinatown, and the International Convention Centre.

  2. The Information Memorandum stated:

“RSL NSW is selling the properties in one line via an off-market campaign to a selection of pre-qualified developers and investors with a track record and financial capability.

This is a rare opportunity to purchase a property in one of the most highly sought after locations in the City of Sydney with the flexibility to redevelop as office or residential, own, operate or redevelop the existing hotel by utilising the current Development Approval …

The combined impact of COVID-19 and the current slow down in the residential market has resulted in a market that is well suited to a boutique development that is not constrained by the requirement to achieve a large volume of pre-sales. …

RSL NSW’s preferred transaction structure is a Put & Call, with a deferred settlement following a successful development approval. This structure provides significant benefits to both RSL NSW and the proponent. The delayed settlement provides the proponent time to achieve a development consent without the burden of significant holding costs. RSL NSW will benefit by sharing in the value created by the development consent and the market recovery.

RSL NSW will consider alternate proposals including an immediate sale. RSL NSW will not consider transaction structures that require it to incur any form of development risk.”

The Option Deed

  1. As I have already mentioned, RSL and CEHP entered into the Option Deed as grantor and grantee (respectively) on 6 December 2020.

  2. By clauses 2 to 4 of the Option Deed, RSL granted to CEHP an option to purchase the Property on the terms of the contract for sale of land in Annexure A to the Option Deed, exercisable at any time during the period between 30 months (two and a half years) and 48 months (four years) after the date of the Option Deed (the Call Option).

  3. By clauses 6 to 8 of the Option Deed, CEHP granted to RSL an option for RSL to sell the Property to CEHP on the terms of the contract in Annexure A, exercisable for a period of 15 business days after the expiry of the time for exercise of the Call Option (the Put Option).

  4. CEHP was obliged to pay an annual Call Option Fee of $3,300,000 until the exercise of the Call Option or the Put Option, which would be offset against the purchase price payable by CEHP for the Property assuming that one of those options was exercised.

  5. A Put Option Fee of $1.00 was payable by RSL.

  6. The Option Deed contained a series of provisions concerning the steps to be taken by the parties while the Option Deed was on foot with the objective of obtaining development consent for the Property.

  7. Clause 10 of the Option Deed required RSL and CEHP to establish a management committee to convene to discuss the development application as often as may be required to progress the application efficiently. CEHP was required to prepare a monthly report to the management committee covering: (1) the status of planning activities and approvals; (2) updates in relation to the milestones by which clauses 11 and 12 of the Option Deed required CEHP to appoint an architect and town planner, prepare a concept design, attend a pre-development application meeting with the consent authority, and lodge the development application; (3) any likely causes of delay in achieving development consent; and (4) any other matters reasonably requested by RSL. Clause 10 also required CEHP to keep RSL fully informed of its dealings with the relevant consent authority.

  8. Clause 11.1 of the Option Deed required CEHP to lodge a development application or, if necessary, several development applications, until a development consent was obtained in respect of the Property. CEHP was required to obtain RSL’s approval for the lodgement of any development application before lodging it with the consent authority. CEHP was required to bear all of the costs associated with the design, documentation, lodgement and negotiation of the development application, and to ensure that the development application maximised the permissible gross floor area (GFA) and the total gross realisation of the Property.

  9. Pursuant to clauses 11.2 and 11.3 of the Option Deed, RSL was required to reasonably assist CEHP to make development applications and obtain development consent, and to either approve or refuse approval for the lodgement of any development application within ten business days after CEHP requested approval.

  10. Clause 11.4 required CEHP to lodge with the relevant consent authority any development application approved by RSL as soon as practicable after being notified of RSL’s approval. The milestones that applied pursuant to clause 12 of the Option Deed required CEHP to lodge a development application within 36 months (three years) after the date of the Option Deed. It will be recalled that CEHP was entitled to exercise its Call Option at any time between 30 months (two and a half years) and 48 months (four years) after the date of the Option Deed.

  11. Clause 11.5 required CEHP to promptly notify RSL in writing when “a Development Consent is obtained”. RSL was then required to review that development consent and approve or refuse approval for that development consent within eight business days. There were limited grounds on which RSL was entitled to refuse approval for the development consent. One of those grounds was that the development consent did not achieve a gross floor area greater than the reference design annexed to the Option Deed. If RSL failed to provide approval within eight business days, CEHP was entitled to serve a notice requiring RSL to provide its approval or refusal within a further two business days. If RSL failed to respond within those two business days, then it was deemed to have approved the development consent. If RSL refused approval for a development consent, CEHP was required to prepare and lodge a new development application if requested by RSL to do so. The term “Development Consent” was defined in clause 1.1 of the Option Deed as having the same meaning as in the Environmental Planning and Assessment Act 1979 (NSW), and as including “any Modification” which was also defined as having the same meaning as in that Act.

  12. Clause 13 made provision for CEHP to construct and operate a display suite in the Property for the purpose of marketing and sale of the lots to be created by the proposed development.

  13. Clause 14 of the Option Deed precluded RSL from:

  1. selling or transferring its interest in the Property or any part of it;

  2. mortgaging, charging or otherwise encumbering the Property or any part of it without CEHP’s consent; and

  3. registering or consenting to the registration of any dealing on the titles of the Property without first having obtained CEHP’s written consent.

  1. Clause 14 is expressed to be subject to clause 17 of the Option Deed.

  2. By clause 17.1, read together with Part A of Schedule 6 to the Option Deed, CEHP acknowledged that the Property was subject to a lease to The Group of Four Pty Limited in respect of the Ground Floor of 271 Elizabeth Street for a term of five years with an option to renew for a further five years. Clause 17.1 otherwise relevantly provided that, after the date of execution of the Option Deed, RSL must not grant a “New Lease” in respect of the Property except in accordance with clause 17.2.

  3. Clause 17.2 provided:

“The Grantee [CEHP] consents to the Grantor [RSL] granting a New Lease of the Property on the basis that the New Lease:

(a)   contains no rights of refusal or options to purchase;

(b)   if it is a lease other than a retail lease, is for a term (including options):

(i)   not exceeding 3 years from the date of this document; or

(ii)    not exceeding 10 years and contains the Redevelopment Clause;

(c)   if it is a retail lease, is for a term (including options):

(i)   not exceeding 3 years from the date of this document; or

(ii)    of not more than 6 years from the date of this document and contains the Redevelopment Clause;

(d)   permits that the landlord, during any period of holding over, to terminate the lease by giving not more than 1 months’ notice;

(e)   does not have any outstanding incentives payable on or after completion of the Contract; and

(f)   is not a residential tenancy.”

  1. The “Redevelopment Clause” referred to in clauses 17.2(b)(ii) and (c)(ii) relevantly provided for the lessor to terminate the lease on six months’ notice to the lessee if the lessor proposes to demolish, substantially repair, renovate or reconstruct the building or a substantial part of it.

  2. The “New Leases” to which clause 17.2 applies are defined in clause 1.1 of the Option Deed as including a “Board Room Lease” in the form of Annexure L to the Option Deed.

  3. The Board Room Lease in Annexure L comprises:

  1. a Lease in registrable form to a lessee described as a related body corporate of RSL, commencing on an unspecified date and terminating on an unspecified date for a rent of $1.00 (if demanded); and

  2. a Lease Term Deed between the lessor and lessee.

  1. The Recitals to the Lease Term Deed record that the lessee and lessor have entered into the Lease and that the lessor has requested, and the lessee has agreed, to bring the term of the Lease to an end on the terms of the Lease Term Deed.

  2. Clause 2 of the Lease Term Deed provides:

“Upon payment of the Lease Term Fee, the Term expires.”

  1. Clause 1.1 of the Lease Term Deed also contains a definition of “Termination Date” as meaning:

“The earlier of:

(a) 10 years from the commencement of the Lease; and

(b) the date of Substantial Commencement,

provided that as at that date, the Lease Term Fee has been paid.”

  1. The Lease Term Deed defines the “Lease Term Fee” as:

“The payment of all of the Revised Price under clause 37 of the Contract for Sale.”

  1. The term “Substantial Commencement” is not defined in the Lease Term Deed, and is not used in the Lease Term Deed outside the definition of “Termination Date”. Nor is the term “Substantial Commencement” defined in the Lease, or the Option Deed. The term “Substantial Commencement” is defined in clause 33.1 of the contract for sale of land in Annexure A to the Option Deed as meaning:

“… the date:

(a) a builder has been engaged under an unconditional building contract for the carrying out of the works the subject of an [sic] Development Consent approved by the vendor under the Put and Call Option Deed or this contract;

(b) the building on the property has been substantially demolished; and

(c) physical commencement (as that term is defined in the EPA Act) of the works has occurred.”

  1. The “Terminating Date” of the Board Room Lease in registrable form in Annexure L to the Option Deed is defined as the “Termination Date” in the Lease Term Deed, or any earlier date on which the Lease is terminated or otherwise determined.

  2. As referred to in more detail later in these reasons, the Revised Price under clause 37 of the contract for sale of land in Annexure A to the Option Deed is a “Guaranteed Minimum Purchase Price” of $95,000,000 increased by a “Price Uplift” calculated according to a formula set out in clause 37 in respect of any and all development consents obtained within up to seven years after the date of the Option Deed. The Price Uplift is calculated by reference to the gross floor area achieved by the development consent and the “Residual Land Value” of the Property ascertained in accordance with a valuation process in clause 38.

  3. Clause 17.3 of the Option Deed contained the further provision in relation to the Board Room Lease that was anticipated at the time the Option Deed was entered into:

“(a)   Without the prior written consent of the Grantee [CEHP] (which may be withheld in its absolute discretion [sic], the Grantor [RSL] must not vary, amend or replace the Board Room Lease or agree to vary, amend or replace the Board Room Lease once the Board Room Lease has been entered into by the Grantor and the relevant tenant party.

(b)   This clause 17.3 survives the exercise of the Call Option or the exercise of the Put Option, and does not merge on Completion.”

  1. Clause 22 of the Option Deed provided that, if CEHP failed to perform its obligations under clause 11, and failed to remedy that non-compliance within a reasonable time after receiving notice of that non-compliance, RSL was entitled to do all things and sign all documents required to seek development consent, and to recover all reasonable costs thereby incurred from CEHP.

Development consent

  1. On 13 July 2023, the Council of the City of Sydney granted development consent for the construction of a 15-storey building with two retail tenancies and 42 apartments.

  2. On 15 May 2024, the Council of the City of Sydney approved an application by CEHP to modify the development consent pursuant to s 4.55 of the Environmental Planning and Assessment Act to permit the works to be carried out in stages, with separate construction certificates being issued for each stage.

  3. Although the evidence is silent on this point, I assume that the development consent granted on 13 July 2023 was approved by RSL under clause 11.5 of the Option Deed. Neither party suggested otherwise, and it was implicit in their competing submissions concerning the construction and operation of clauses 35 and 38 of the Contract that the development consent had been so approved.

CEHP exercises the Call Option

  1. On 5 December 2024, CEHP gave notice of its exercise of the Call Option in accordance with clause 4 of the Option Deed, whereupon the contract for sale of land in the form of Annexure A to the Option Deed became binding on the parties (the Contract).

Salient terms of the Contract

  1. The Contract stipulates a price of $95,000,000, which is defined as the “Guaranteed Minimum Purchase Price” or “GMPP”, subject to clause 37.

  2. The Contract contemplates that the work of applying for development consent in respect of the Property may be continuing at the time the Contract is entered into following the exercise of the Call Option or the Put Option. Clause 36 of the Contract provides that certain provisions of the Option Deed, including clause 10 (relating to the management committee to progress the development application), clauses 11 and 12 (relating to the lodgement of one or more development applications and RSL’s approval of any development consent granted), clause 13 (relating to the display suite), clause 14 (restricting RSL’s dealings with the Property), clause 17 (relating to New Leases, including the proposed Board Room Lease) and clause 22 (RSL’s step-in rights), apply to the Contract mutatis mutandis until 36 months (three years) after completion of the Contract.

  1. Consistently with clause 11 of the Option Deed, clause 37 of the Contract contemplates that more than one development consent may be granted in respect of the Property, including after the Contract is entered into or even after completion of the Contract.

  2. If a development consent is granted prior to 84 months (seven years) after the date of the Option Deed, or prior to “Substantial Commencement” of works that are the subject of any development consent which has previously been approved by RSL under the Option Deed, whichever is earlier, this triggers a revision of the price payable by CEHP under clause 37 of the Contract. As I have already mentioned, the term “Substantial Commencement” is defined in clause 33.1 as meaning:

“… the date:

(a) a builder has been engaged under an unconditional building contract for the carrying out of the works the subject of an [sic] Development Consent approved by the vendor under the Put and Call Option Deed for this contract;

(b) the building on the property has been substantially demolished; and

(c) physical commencement (as that term is defined in the EPA Act) of the works has occurred.”

  1. The price revision process commences with CEHP notifying RSL that the development consent has been granted, and RSL then notifying CEHP of the “Revised Price”, under clause 37.1 of the Contract.

  2. Clause 37.2 of the Contract provides that the Revised Price is the Guaranteed Minimum Purchase Price of $95,000,000, plus the “Price Uplift”. The Price Uplift must be calculated as the aggregate of: (1) a specified sum per square metre for half of the increase in GFA achieved by the development consent up to a specified cap; (2) a specified sum per square metre for a quarter of any further increase in GFA above that cap; and (3) the sum that is 30% of a sum calculated as the “Residual Land Value” (or RLV) minus the GMPP and sums that I have referred to in (1) and (2). This revision of the price is the mechanism by which RSL shares in the value created by the development consent and the market recovery as anticipated in the Information Memorandum. [1] Clause 37.3(a) provides that the Revised Price is payable on completion or, if the Contract has already been completed, within 20 business days after the vendor notifies the purchaser of the Revised Price under clause 37.1. Clause 37.3(b) provides that the Revised Price cannot be less than the price previously determined and, if the Contract has already been completed, paid.

    1. See [8] above.

  3. The Residual Land Value is to be determined in accordance with clause 38 of the Sale Contract, which provides as follows:

38.    Calculation of RLV

38.1    Vendor's notice

(a)    The RLV will vary as determined in accordance with this clause 38.

(b)    The vendor may at any time, and from time to time, serve notice on the purchaser which states the vendor's assessment of the RLV applying for the purpose of clause 37 (Vendor's Notice). That RLV will be determined as at the date of the Vendor's Notice.

38.2    Purchaser's notice

If the purchaser disputes the RLV stated in the Vendor's Notice, then the purchaser must serve notice on the vendor within 10 Business Days after the vendor serves the Vendor's Notice (Dispute Notice).

38.3    Purchaser does not serve notice

If the purchaser does not serve the Dispute Notice within 10 Business Days after the vendor serves the Vendor's Notice then the RLV is the RLV as stated in the Vendor's Notice.

38.4    Attempt to resolve dispute

If the purchaser serves a Dispute Notice, the vendor and purchaser must attempt to resolve their dispute about the RLV within 10 Business Days of service of the Dispute Notice on the vendor.

38.5    Valuers to be appointed and determined

If the purchaser and the vendor do not under clause 38.4 resolve their dispute about the RLV within 10 Business Days after the purchaser serves the Dispute Notice then within 15 Business Days after the purchaser serves the Dispute Notice:

(a)    the purchaser must appoint by notice to the vendor a Valuer; and

(b)    the vendor must appoint by notice to the purchaser a Valuer,

38.6      Failure to appoint a Valuer

(a)    If the vendor fails to appoint a Valuer then:

(i)    the purchaser's Valuer determines the RLV the subject of clause 37.2(b)(iii); and

(ii)    the vendor and purchaser must apportion the Cost of the purchaser's Valuer's determination equally.

(b)    If the purchaser fails to appoint a Valuer then:

(i)    the vendor's Valuer determines the RLV the subject of clause 37.2(b)(iii); and

(ii)    the vendor and purchaser must apportion the Cost of the vendor's Valuer's determination equally.

38.7    Disagreement between Valuers

If the Valuers fail to agree on the RLV within 10 Business Days of notification of their appointment, and if the difference between the respective assessments of the Valuers is not greater than 10% of the aggregate of their assessments, then the RLV is one half of the aggregate of their assessments.

38.8    Appointment of an Umpire

If the Valuers fail to agree on the RLV and clause 38.7 does not apply, then the Valuers must agree upon and appoint an Umpire within 15 Business Days of notification of their appointment.

38.9    Conduct of review

(a)    The Valuers and the Umpire act as experts and not as arbitrators.

(b)    The Valuers and the Umpire must each give written notice of acceptance of the appointment to the vendor and purchaser.

(c)    The vendor and purchaser may make written submissions to their appointed Valuers and the Umpire within 10 Business Days of receipt of written notice of the Valuer's or the Umpire's acceptance of appointment.

(d)    The Valuers and the Umpire's determinations are final and binding on the vendor and purchaser.

(e)    The Valuers and the Umpire must:

(i)    determine the RLV within 15 Business Days of giving written notice of acceptance of appointment to act; and

(ii)    give written reasons for the determination.

38.10    Appointment of another Valuer or Umpire

Either the vendor or the purchaser may request the President of the Australian Property Institute to appoint another Valuer or Umpire to determine the RLV if either of the Valuers or the Umpire:

(a)    do not accept the appointment to act;

(b) fail to determine the RLV within 10 Business Days of acceptance of appointment to act; or

(c)    resign as Valuer or Umpire.

38.11    Cost of determination

The Cost incurred under this clause 38 of:

(a)    each Valuer, must be that of the party appointing the Valuer; and

(b)    the Umpire, must be that of the vendor and purchaser equally.

38.12    Agreement to co-operate

The vendor and purchaser agree to co-operate in implementing any valuation under this clause 38.”

  1. The issues for determination in these proceedings include an issue concerning the validity of a notice issued or purportedly issued by CEHP under clause 38.5(a) of the Contract. The notice or purported notice was attached to an email sent by Mills Oakley (on behalf of CEHP) to Corrs Chambers Westgarth (on behalf of RSL) at 7:10pm on 15 January 2025.

  2. The resolution of that issue turns, in part, on the date on which the 15 business day period referred to in clause 38.5 expired, and the time and date at which the email attaching the notice was sent or served, or is taken to have been given.

  3. Relying on clause 33.2 of the Contract, CEHP contends that the 15 business day period expired on 16 January 2025. Clause 33.2 relevantly provides that:

“In this contract unless the contrary intention appears:

(d)   if the date on or by which any act must be done under this contract is not a business day, the act must be done on or by the next business day; and

(e)   if a period of time is specified to start from a certain day, the period is to be calculated exclusive of that day.”

  1. If that contention is rejected, CEHP contends that its clause 38.5(a) notice was given on 15 January 2025, and is not taken to have been given on the following business day by reason of the notice having been given by email sent after 5:00pm on 15 January 2025. CEHP relies on: (1) clause 20.6.9 of the Contract; and (2) further or alternatively, the definition of “Business Day” in clause 33.1 of the Contract as “a day which is not a Saturday, Sunday or bank or public holiday in Sydney” and the ordinary meaning of “day” as a 24-hour period.

  2. Clause 20.6 of the Contract forms part of what is referred to as the “printed clauses” of the Contract, being the standard terms and conditions of the 2019 edition of the Law Society of New South Wales and Real Estate Institute of New South Wales contract for the sale and purchase of land. The provisions of clause 20.6 have been amended by what the parties refer to as the “additional clauses”, being clauses 33 to 59 which the parties have drafted to apply in addition to the printed clauses. Those amendments include the addition of clauses 20.6.8 and 20.6.9. Clause 20.6 of the printed clauses, as amended by clause 34(l) of the additional clauses, provides:

“20.6    A document under or relating to this contract is –

20.6.1    signed by a party if it is signed by the party or the party’s solicitor (apart from a direction under clause 4.3);

20.6.2    served if it is served by the party or the party’s solicitor;

20.6.3    served if it is served on the party’s solicitor, even if the party has died or any of them have died;

20.6.4 served if it is served in any manner provided in s170 of the Conveyancing Act 1919;

20.6.5    served if it is sent by email or fax to the party’s solicitor, unless in either case it is not received;

20.6.6    served on a person if it (or a copy of it) comes into the possession of the person; and

20.6.7    served at the earliest time it is served, if it is served more than once;

20.6.8    served by the vendor or the vendor’s solicitor if it is sent by email to the purchaser’s solicitor’s nominated email address, and served at the time the email was sent (unless the vendor or the vendor’s solicitor receives a “bounce back”, notification of delivery failure or similar automated message from the purchaser’s solicitor’s nominated email address); and

20.6.9    served by the purchaser or the purchaser’s solicitor if it is sent by email to the vendor’s solicitor’s nominated email address, and served at the time the email was sent (unless the purchaser or the purchaser’s solicitor receives a “bounce back”, notification of delivery failure or similar automated message from the vendor’s solicitor’s nominated email address).”

  1. Clause 1 of the printed clauses of the Contract defines “serve” as meaning:

“serve in writing on the other party

  1. As I have already mentioned, clause 20.6.9 is the particular clause on which CEHP relies.

  2. It follows, in RSL’s submission, that 15 January 2025 was the last day of the 15 business day period within which CEHP was entitled to give a notice appointing a valuer under clause 38.5(a). RSL denies that clause 20.6.9 of the Contract applies to a notice under clause 38.5.(a). RSL relies on clauses 33.7 and 33.8 of the Contract as the applicable provisions. Clauses 33.7 and 33.8 provide:

33.7   Communications by email

A communication is given if sent by email at the time the email is sent:

(a)    if sent before 5.00 pm in the place the email is sent;

(b)    to the vendor’s solicitor’s nominated email address (unless the sender receives a “bounce back”, notification of delivery failure or similar automated message from the vendor’s solicitor’s nominated email address); and

(c)    to the purchaser’s solicitor’s nominated email address (unless the sender receives a “bounce back”, notification of delivery failure or similar automated message from the purchaser’s solicitor’s nominate email address),

provided that if a communication is sent by email on a day which is a Saturday, Sunday or bank or public holiday in the place the email is sent, it is taken as having been given at 9.00 am on the next day which is not a Saturday, Sunday or bank or public holiday in that place.

33.8    After hours communications

Subject to clause 33.7, if a communication is given:

(a)    after 5.00pm in the place of receipt; or

(b)    on a day which is a Saturday, Sunday or bank or public holiday in the place of receipt,

It is taken as having been given at 9.00 am on the next day which is not a Saturday, Sunday or bank or public holiday in that place.”

  1. RSL contends that, by reason of clauses 33.7 and 33.8, the email sent by CEHP’s solicitors to RSL’s solicitors at 7:10pm on 15 January 2025 is taken to have been received at 9:00am on 16 January 2025.

  2. RSL further submits that, if both clause 20.6.9 of the Contract and clauses 33.7 and 33.8 apply to the notice, then clauses 33.7 and 33.8 of the Contract are to prevail by reason of clause 33.4 which provides that:

“If there is any inconsistency between the printed clauses of this contract and these additional clauses, the additional clauses prevail to the extent of that inconsistency.”

  1. In the event that the Court finds that CEHP failed to notify RSL of its appointment of a valuer within the 15 business day period permitted by clause 38.5 of the Contract, CEHP submits that time is not of the essence, that the clause 38 process must therefore proceed involving both its appointed valuer and RSL’s appointed valuer, and that RSL has not suffered any loss by reason of its delay of just over 2 hours in sending the email notifying its appointment of a valuer at 7:10pm on 15 January 2025.

  2. Although the Option Deed and the Contract require development applications to be lodged, and the Contract contemplates that one or more development consents may be granted in respect of the Property before or after the Contract is entered into, completion of the Contract is not conditional on any development consent being granted.

  3. Clause 35 of the Contract provides:

35    Date for completion

(a)    Subject to clause 35(b), completion of this contract must take place on and the date for completion is the later of:

(i)    12 months after a Development Consent approved by the vendor has been granted; and

(ii)    20 Business Days after the contract date.

(b)    Despite clause 35(a)35(a) [sic], Purchaser may at any time nominate a date for completion by written notice to the Vendor given at least 12 months before the nominated date for completion”

  1. The term “Development Consent” is defined in clause 33.1 of the Contract to mean the development consent approved by RSL pursuant to clause 11.5 of the Option Deed and clause 36 of the Contract. It will be recalled that clause 36 of the Contract provides that various clauses of the Option Deed, including clause 11, apply to the Contract until three years after completion of the Contract.

  2. Clause 41 of the Contract relevantly provides:

41   Late completion

41.1   Completion

(a)   The vendor and the purchaser must complete this contract by 5:00pm on the date for completion.

(b)   If either party does not complete this contract on or before the date for completion then the other party shall be entitled to make time of the essence of this contract by serving upon the other party a notice to complete the contract.

41.4   If completion does not take place

Without limiting any other right of the vendor, if completion takes place after the date for completion due to the default of the purchaser, it is an essential term of this contract that, on completion, the purchaser must pay, by way of liquidated damages, the Daily Rate from but excluding the date for completion to and including the date on which this contract is completed. The purchaser is not required to pay the Daily Rate for any period in which the vendor is in breach of the contract or is not ready, willing and able to complete the contract.”

  1. The Daily Rate at which liquidated damages accrues under clause 41.4 is $11,753.42.

  2. Clause 21 of the printed clauses of the Contract relevantly provides:

Time limits in these provisions

21.1   If the time for something to be done or to happen is not stated in these provisions, it is a reasonable time.

21.2   If there are conflicting times for something to be done or to happen, the latest of those times applies.

21.6   Normally, the time by which something must be done is fixed but not essential.”

  1. The word “normally” is defined in clause 1 of the printed clauses as meaning “subject to any other provision of this contract”.

  2. Clause 42 of the Contract relevantly provides:

42.3   No objection

Without affecting clause 10, the purchaser is not entitled to make a Claim or requisition or delay completion, rescind or terminate in connection with:

(f)   the viability, profitability and potential of the property;

(g)   the potential financial return or income to be derived from the property;

(h)   the development potential of the property;

…”

  1. Clause 54.3 of the Contract provides:

“(a)   A party waives a right under this contract only if it does so in writing.

(b)   A party does not waive a right simply because it:

(i)   fails to exercise the right;

(ii)   delays exercising the right; or

(iii)   only exercises part of the right.

(c)   A waiver of one breach of a term of this contract does not operate as a waiver of another breach of the same term or a breach of any other term.

(d)   A party is not liable for any loss, Cost or expense of any other party caused or contributed to by the waiver, exercise, attempted exercise, failure to exercise or the delay in the exercise of a right.”

  1. Clause 54.8 of the Contract relevantly provides:

54.8   Entire understanding

(a)   This contract and the Put and Call Option Deed contains the entire understanding between the parties as to the subject matter of this Contract.

(b)   Except in relation to the Put and Call Option Deed, all previous negotiations, understandings, representations, warranties, memoranda or commitments concerning the subject matter of this contract are merged in and superseded by this contract and are of no effect. No party is liable to any other party in respect of those matters.

…”

Dispute relating to the calculation of Residual Land Value

  1. On 6 December 2024, Corrs Chambers Westgarth on behalf of RSL wrote to Mills Oakley on behalf of CEHP referring to the Contract that had been entered into on 5 December 2024 as a result of CEHP exercising its Call Option, and stating:

“Pursuant to clause 38.1(b) of the Contract, the Vendor may at any time serve notice on the Purchaser which states the Vendor’s assessment of the RLV applying for the purpose of clause 37 of the Contract.

In accordance with clause 38.1(b) of the Contract, the Vendor gives notice to the Purchaser that the Vendor’s assessment of the RLV is $114,250,000.”

  1. Corrs Chambers Westgarth sent a further letter to Mills Oakley on 6 December 2024 setting out RSL’s calculation of the Revised Price under clause 37.2 of the Contract as $120,726,685. RSL subsequently acknowledged that its calculation was erroneous. It withdrew that calculation, and issued an amended calculation of $105,206,407.93 by letter from Corrs Chambers Westgarth to Mills Oakley dated 19 December 2024. The amended calculation did not involve any change to RSL’s assessment of the Residual Land Value, which was one integer of the Revised Price calculation. Thus, RSL’s notice of its assessment of the Residual Land Value issued on 6 December 2024 was not withdrawn.

  2. CEHP did not raise any objection at the time, or in these proceedings, to RSL’s entitlement to notify CEHP of its RLV assessment on 6 December 2024 and its Revised Price calculation and amended Revised Price calculation on 6 and 19 December 2024. However, CEHP issued a notice under clause 38.2 of the Contract on 20 December 2024 disputing the amount of the RLV stated in RSL’s 6 December 2024 notice referred to at [69] above.

  3. It is common ground that RSL’s notice referred to at [69] above (the Vendor’s RLV Notice) triggered the mechanism under clause 38 of the Contract for determining the Residual Land Value of the Property, and that CEHP’s notice referred to at [71] above (the Purchaser’s Dispute Notice) was issued within the time stipulated by clause 38.2 of the Contract.

  1. On 31 December 2024, RSL sent to CEHP a copy of the RLV valuation obtained by RSL for the purpose of clause 37 of the Contract, in anticipation of a meeting to be held between RSL and CEHP on 8 January 2025 to attempt to resolve their dispute about the RLV as required by clause 38.4 of the Contract. The valuation report set out the reasons of the author – Mr Tahir Khan of CBRE Valuation and Advisory Services – for assessing the RLV as $114,250,000.

  2. The parties failed to resolve their dispute at the meeting on 8 January 2025, which triggered the operation of clause 38.5 of the Contract. It will be recalled that clause 38.5 provides that, if the parties do not resolve their dispute within 10 business days after CEHP served the Purchaser’s Dispute Notice, then each party “must” appoint a valuer by notice to the other party within 15 business days after the date of service of the Purchaser’s Dispute Notice (the Purchaser’s Valuer Notice and the Vendor’s Valuer Notice, respectively). Clause 38.6 provided that, if either party failed to appoint a valuer, then the RLV was to be determined by the other party’s valuer and the cost of that determination was to be apportioned between the parties equally.

  3. On 9 January 2025, Corrs Chambers Westgarth on behalf of RSL wrote to Mills Oakley on behalf of CEHP, stating:

“Because the Purchaser and the Vendor have been unable to resolve their dispute about the RLV within 10 Business Days after the Purchaser served the Dispute Notice, the Purchaser and the Vendor are each required to appoint by notice to each other a Valuer in accordance with clause 38.5 of the Contract. Such appointment must occur and must be notified to the other party within 15 Business Days after the Purchaser served the Dispute Notice. Accordingly, the deadline for the appointment of Valuers is 15 January 2025.

In compliance with clause 38.5 of the Contract, the Vendor will move to appoint a Valuer shortly and will give notice of the appointment of a Valuer to the Purchaser by 15 January 2025. The Vendor expects the Purchaser to do the same.”

  1. On 15 January 2025, Corrs Chambers Westgarth wrote to Mills Oakley giving notice that RSL had appointed Mr Khan as its valuer for the purpose of clause 38.5 of the Contract. That letter was sent to Mills Oakley by email sent at 4:07pm on 15 January 2025. It is common ground that this was a valid Vendor’s Valuer Notice under clause 38.5 of the Contract.

  2. At 7:10pm that evening, Mills Oakley sent an email to Corrs Chambers Westgarth attaching a letter stating:

Notice under Clause 38.5

We understand that the parties have attempted to resolve their dispute about the RLV in accordance with clause 38.4 of the Contract. However, their attempt to resolve the dispute about the RLV was unsuccessful.

This letter is deemed to be a notice under clause 38.5 of the Contract, and clause 20.6 (as amended by clause 34(l) of the Contract).

Pursuant to clause 38.5(a), the Purchaser notifies the Vendor that the Purchaser has appointed Danny Sukkar, AAPI Member No. 68873 as a Valuer for the purpose of clause 38 of the Contract.”

  1. Since 15 January 2025, RSL has disputed the validity of that communication as a Purchaser’s Valuer Notice under clause 38.5 of the Contract. I have outlined at [44] to [58] above the bases on which CEHP contends, and RSL disputes, that the Purchaser’s Valuer Notice was given “within 15 Business Days after the purchaser serves the Dispute Notice” as required by clause 38.5. RSL contends that, in the absence of a Purchaser’s Valuer Notice given within that period, the RLV fell to be determined by Mr Khan alone pursuant to clause 38.6(b)(i). On 10 February 2025 – some 17 business days after the date of the Vendor’s Valuer Notice – Mr Khan issued a report setting out his assessment of the RLV as $114,250,000. RSL contends that Mr Khan’s determination brought the clause 38 process to an end, and that the cost of Mr Khan’s determination is to be apportioned equally between RSL and CEHP pursuant to clause 38.6(b)(ii) of the Contract.

  2. On 4 March 2025, Mills Oakley (on behalf of CEHP) wrote to Corrs Chambers Westgarth (on behalf of RSL) attaching a valuation report prepared by Mr Sukkar dated 28 February 2025 setting out his reasons for assessing the RLV as $84,000,000. Mills Oakley’s letter stated that clause 38.7 required an umpire to be appointed because the difference between Mr Khan’s assessment and Mr Sukkar’s assessment of the RLV exceeded 10% of the aggregate of their assessments.

  3. No umpire has been appointed. RSL maintains that CEHP failed to validly appoint a valuer under clause 38.5(a) of the Contract, and that the RLV to be applied in calculating the Revised Price is the RLV as determined by Mr Khan in his 10 February 2025 report.

  4. CEHP commenced these proceedings on 11 March 2025. CEHP’s claims for final relief include:

  1. a claim for a declaration that, in the events which have happened, there was, and is, a binding contract dated 5 December 2024 for the sale and purchase of the Property between CEHP as purchaser and RSL as vendor for a purchase price of $95,000,000 (prayer 11 of the Summons);

  2. a claim for a declaration that, in the events which have happened and on the proper construction of the Contract, the notice served by its solicitor on RSL’s solicitor by letter dated 15 January 2025 attached to the email sent at 7:10pm on that date (the Purchaser’s Valuer Notice) was contractually effective to enliven the operation of clause 38.5(a) of the Contract (prayer 16 of the Summons);

  3. a claim for a declaration that, in the events which have happened and on the proper construction of the Contract, RSL’s assertion that the said notice did not validly appoint the Purchaser’s Valuer pursuant to clause 38.5(a) of the Contract, was wrong in fact and law (prayer 17 of the Summons); and

  4. a claim for an order that the procedure in clauses 38.5 and 38.7 to 38.12 of the Contract for the resolution of a dispute in respect of the Residual Land Value and Revised Price be specifically performed and carried into effect on the premises that: (a) the Purchaser’s Valuer was validly appointed pursuant to clause 38.5(a) of the Contract by the service of the Purchaser’s Valuer Notice; and (b) the RSL and its agent the Vendor’s Valuer, and CEHP and its agent the Purchaser’s Valuer, are required to comply with clauses 38.7 to 38.12 of the Contract (prayer 18 of the Summons).

  1. By prayer 3 of the Cross-Summons, RSL seeks a declaration that the Revised Price under the Contract is $105,206,407.93, being the amount of RSL’s amended calculation given to CEHP on 19 December 2024.

Completion Date Nomination

  1. The date for completion of the Contract is governed by clause 35, the terms of which are set out at [60] above.

  2. At the time the Contract was entered into on 5 December 2024 as a result of CEHP exercising its Call Option, a period of twelve months had already elapsed since the grant of the development consent referred to at [37]-[39] above on 13 July 2023. The period of 20 business days after the date of the Contract referred to in clause 35(a)(ii) would expire on 7 January 2025.

  3. On 20 December 2024, Mills Oakley (the solicitors for CEHP) sent an email to Corrs Chambers Westgarth (the solicitors for RSL) attaching a document described as a notice under clause 35(b) of the Contract. The notice stated that CEHP nominated 19 June 2026 as the date for completion of the Contract pursuant to clause 35(b).

  4. Corrs Chambers Westgarth replied later that same day, stating:

“3.    The Completion Date Nomination misunderstands clause 35 of the Contract. The Purchaser may not nominate an alternative completion date, and the Completion Date Nomination is of no effect.

4.    Clause 35(b) of the Contract provides the Purchaser with the right to bring forward the default time for completion determined in accordance with clause 35(a) in circumstances where, as at the date of the Contract, no Development Consent has been granted. In this way, had no Development Consent been granted as at 5 December 2024, the Purchaser could elect to complete the sale sooner than it might otherwise be required to complete, provided that it gives at least 12 months’ notice of the early completion date.

5.    In circumstances where a Development Consent approved by the Vendor was granted in July 2023, prior to the date of the Contract, the completion date is set by clause 35(a)(ii) of the Contract. Accordingly, completion of the Contact must take place on and the date for completion is 7 January 2025.

6.    All of the Vendor’s rights and remedies are expressly reserved.”

  1. As at 7 January 2025, the parties remained in dispute about RSL’s assessment of the Residual Land Value and the Revised Price to be paid under the Contract.

  2. There were numerous exchanges of correspondence between the parties concerning the completion date, culminating in Corrs Chambers Westgarth writing to Mills Oakley in the following terms on 12 February 2025:

“In light of the service of the Purchaser’s Dispute Notice pursuant to clause 38.2, completion was deferred to permit the dispute resolution process set out in clause 38 to proceed. Now that the dispute resolution process has run its course and the Vendor’s Valuation has been issued, the Vendor calls for completion to occur.

The Vendor gives notice to the Purchaser that, subject to the parties agreeing otherwise in writing, the date for completion is, and completion must occur on, Wednesday, 12 March 2025, being the date that is 20 Business Days after the date of this letter. Accordingly, subject to the parties agreeing otherwise in writing, the Purchaser must be ready, willing and able to complete, and must complete, on Wednesday, 12 March 2025.

All of the Vendor’s rights and remedies are expressly reserved.”

  1. On 17 February 2025, Corrs Chambers Westgarth sent a further letter to Mills Oakley clarifying that their 12 February 2025 letter was not a formal notice to complete under the Contract, and stating that RSL would issue such a notice if CEHP failed to complete on or before 12 March 2025. The letter confirmed that RSL would be ready, willing and able to complete on 12 March 2025, and invited CEHP’s solicitors to inform them if CEHP wished to complete the Contract prior to that date.

  2. As I have already mentioned, CEHP commenced these proceedings on 11 March 2025. CEHP sought interim injunctions restraining RSL from requiring it to complete the Contract on 12 March 2025, and from issuing any notice to complete making time of the essence for completion on the premise that CEHP had failed to complete on 12 March 2025.

  3. CEHP’s claims for final relief include:

  1. a claim for a declaration that, in the events which have happened and on the proper construction of the Contract, its notice served on 20 December 2024 nominating 19 June 2026 as the date for completion of the Contract, was and is contractually effective to appoint that date as the date for completion of the Contract (prayer 12 of the Summons);

  2. a claim for a declaration that, in the events which have happened and on the proper construction of the Contract, RSL’s nominated date of 12 March 2025 is not the correct date for completion of the Contract; (prayer 13 of the Summons)

  3. a claim for an order that the Contract, with a date for completion of 19 June 2026, be specifically performed and carried into effect (prayer 14 of the Summons); and

  4. a claim for an order that the notices given by RSL’s solicitors to CEHP’s solicitors on 12 February and 17 February 2025 purporting to call for completion of the Contract, and purporting to nominate 12 March 2025 as the date for completion of the Contract, are null and void, and of no legal effect (prayer 15 of the Summons).

  1. CEHP’s claims for interim relief were resolved by RSL giving the following undertaking to the Court on 12 March 2025:

“Upon the Plaintiff, by its counsel, giving the usual undertaking as to damages, the Defendant be restrained, until further order of the Court, from issuing to the Plaintiff any notice to complete pursuant to the terms of the ‘Contract for the Sale and Purchase of Land 2019 Edition’ dated 5 December 2024, seeking to make time of the essence for completion of the Contract.”

  1. By prayer 4 of the Cross-Summons, RSL seeks, inter alia, a declaration that it is entitled to issue a notice to complete the Contract.

Dispute relating to the Board Room Lease

  1. As explained in more detail at [174]-[180] below, RSL and one of its related bodies corporate have entered into the Board Room Lease and the Lease Term Deed on terms that do not include the Redevelopment Clause. CEHP has declined to consent to the registration of the Board Room Lease. RSL contends that CEHP is obliged to consent to its registration because the Board Room Lease is in the form of Annexure L to the Option Deed. It will be recalled that the form of the Board Room Lease in Annexure L did not include the Redevelopment Clause. CEHP contends that the absence of the Redevelopment Clause in the Board Room Lease that RSL has entered into means that it fails to comply with clause 17.2(b) of the Option Deed, which applies as a term of the Contract pursuant to clause 36 of the Contract. CEHP contends that it is therefore not required to consent to the registration of the Board Room Lease.

  2. By prayers 1 and 2 of the Cross-Summons, RSL seeks a declaration that CEHP is required to provide its consent to the registration of the Board Room Lease on the title for 271 Elizabeth Street, and an order requiring CEHP to provide that consent in writing within two days.

Valuation costs

  1. RSL seeks to recover from CEHP the whole of the cost that it incurred in obtaining a valuation of 271 Elizabeth Street for the purpose of the GST margin scheme, and 50 per cent of the cost that it incurred in obtaining Mr Khan’s valuation of the Residual Land Value for the purpose of clause 38 of the Contract on 10 February 2025.

  2. Clause 51.3 of the Contract confers a discretion on RSL to determine that the supply of the Property is a taxable supply under the A New Tax System (Goods and Services Tax) Act 1999 (Cth) (the GST Act). In that event: (1) clause 51.3 of the Contract requires CEHP to pay to RSL an amount equivalent to the GST that is payable on the supply of the Property; (2) clause 51.5 provides that the margin scheme under Division 75 of Part 4.2 of the GST Act applies; (3) clause 51.5(b) requires CEHP to pay the costs of RSL obtaining an “approved valuation” for the purpose of that margin scheme; and (4) the price is to be adjusted in accordance with a formula set out in clause 51.6 of the Contract.

  3. Section 75-35(1) of the GST Act provides that the Commissioner may, by legislative instrument, determine in writing requirements for making valuations for the purpose of Division 75. Section 75-35(2) provides that such a valuation is an “approved valuation”.

  4. On 19 December 2024, RSL notified CEHP that it had determined that GST was payable on the whole of the supply of the Property on the basis that the supply was not a going concern.

  5. RSL contends that it incurred costs of $71,500 in obtaining from M3 Property on 31 January 2025 a valuation of the market value of 271 Elizabeth Street as at 1 July 2000, and that this is an “approved valuation” under section 75-35(2) of the GST Act and within the meaning of clause 51.5(b) of the Contract. RSL contends that CEHP is therefore liable to pay that cost, and seeks judgment against CEHP in that amount to reimburse RSL for the costs of the valuation which RSL has already paid in full.

  6. In the event that the Court construes clause 38.5 of the Contract in the manner for which RSL contends, RSL relies on clause 38.6(b)(ii) of the Contract as entitling it to recover 50% of the cost of Mr Khan’s 10 February 2025 valuation from CEHP. That is a sum of $2,296.25.

  7. By prayer 5 of the Cross-Summons, RSL claims judgment in the total sum of $73,796.25.

Issues to be determined

  1. The parties’ claims and defences raise five issues for determination:

  1. whether clause 35 of the Contract, properly construed, permitted CEHP to give notice on 20 December 2024 nominating 19 June 2026 as the date for completion of the Contract;

  2. whether the email sent by CEHP’s solicitors to RSL’s solicitors at 7:10pm on 15 January 2025 was effective to appoint a valuer under clause 38.5(a) of the Contract and, if not, whether it follows that the RLV is to be determined by the valuer appointed by RSL in accordance with clause 38.6(b) of the Contract;

  3. whether CEHP is required under the Option Deed and the Contract to consent to the registration of the Board Room Lease on the title to the Property;

  4. whether RSL is presently entitled to issue a notice to complete the Contract, making time of the essence; and

  5. whether CEHP is liable to pay to RSL: (a) the sum of $71,500 representing the costs of the margin scheme approved valuation; and (b) 50% of the cost of Mr Khan’s 10 February 2025 valuation.

  1. For the reasons that follow, I have determined that:

  1. properly construed, clause 35(b) applies only in circumstances where no development consent has been granted and approved by RSL at the time that the Contract is entered into. As a development consent was in fact granted and approved by RSL before the Contract was entered into, clause 35(b) did not permit CEHP to give notice on 20 December 2024 nominating 19 June 2026 as the date for completion of the Contract. That notice is of no effect, and the date for completion was 20 business days after the date of the Contract, being the later of the two dates in clause 35(a)(i) and (ii);

  2. the Purchaser’s Valuer Notice sent by CEHP’s solicitors to RSL’s solicitors by email at 7:10pm on 15 January 2025 was given within the time stipulated in clause 38.5 of the Contract and was valid and effective to notify to RSL the appointment of Mr Sukkar as the Purchaser’s Valuer for the purpose of clause 38 of the Contract;

  3. on the proper construction of clause 17 of the Option Deed, CEHP has not consented to the grant of the Board Room Lease without the Redevelopment Clause and is not required to consent to the registration of the Board Room Lease omitting the Redevelopment Clause; and

  4. the date for completion fixed by clause 35(a) of the Contract having passed, RSL is presently entitled to issue a notice to complete under clause 41.1 of the Contract making time of the essence;

  5. CEHP is liable on completion of the Contract to pay to RSL the sum of $71,500 representing the cost of RSL obtaining the margin scheme approved valuation from M3 Property, but CEHP is not liable to pay to RSL 50% of its cost incurred in obtaining Mr Khan’s 10 February 2025 valuation for the purpose of clause 38 of the Contract.

  1. I have arrived at those conclusions after considering all of the parties’ written and oral submissions, although I have not found it necessary to record all of the details of those submissions in order to explain my reasons.

Issues 1 and 4 – Clause 35 of the Contract, CEHP’s nominated completion date, and RSL’s entitlement to issue a notice to complete

  1. The Contract is a commercial contract. There was no dispute about the principles to be applied in resolving the dispute about the proper construction of clause 35. Those well-established principles were recently summarised by the Court of Appeal, with reference to High Court authority, in J & P Marlow (No 2) Pty Ltd v Hayes & McCabe [2] (J & P Marlow) and Zhong v Guan [3] (Zhong).

  2. Meagher and Kirk JJA summarised the core principles in the following terms in J & P Marlow:

“[89] Four members of the High Court summarised the core principles of construction of commercial contracts as follows in Electricity Generation Corporation v Woodside Energy Ltd (2014) 251 CLR 640; [2014] HCA 7 at [35]:

(1)      The meaning of the terms of a commercial contract is to be determined by what a reasonable businessperson would have understood those terms to mean.

(2)      That requires consideration of the language used by the parties, the surrounding circumstances known to them and the commercial purpose or objects to be secured by the contract. That, in turn, is facilitated by an understanding of the genesis of the transaction, the background, the context and the market in which the parties are operating.

(3)      Unless a contrary intention is indicated, a court is entitled to approach the task of giving a commercial contract a businesslike interpretation on the assumption that the parties intended to produce a commercial result. The contract is to be construed so as to avoid it making commercial nonsense or working commercial inconvenience.

[90] Put simply, as Gageler, Nettle and Gordon JJ stated in Simic v New South Wales Land and Housing Corporation (2016) 260 CLR 85; [2016] HCA 47 at [78], the “proper construction of [a contract] is to be determined objectively by reference to its text, context and purpose” (citation omitted). Inherent in recognition of the importance of context and purpose is that the construction adopted may depart from the literal or ordinary meaning of the words employed. Gibbs J, for example, indicated as much in Australian Broadcasting Commission v Australasian Performing Right Association Ltd (1973) 129 CLR 99 at 109; [1973] HCA 36 (ABC v APRA; at 109, citation omitted):

‘if the language is open to two constructions, that will be preferred which will avoid consequences which appear to be capricious, unreasonable, inconvenient or unjust, ‘even though the construction adopted is not the most obvious, or the most grammatically accurate’ … Further, it will be permissible to depart from the ordinary meaning of the words of one provision so far as is necessary to avoid an inconsistency between that provision and the rest of the instrument.’”

  1. After referring to that summary in Zhong, Kirk JA, with whom the other members of the Court of Appeal agreed, explained that:

“32.    Implicit in these principles is the notion that the court is seeking to identify the joint intentions of the parties, doing so by the objective standard of what a reasonable person in the position of the parties would understand that to be. The notion of intention here is used to describe ‘what it is that would objectively be conveyed by what was said or done, having regard to the circumstances in which those statements and actions happened’: Ermogenous v Greek Orthodox Community of SA Inc [2002] HCA 8; (2002) 209 CLR 95 at [25]; see also Realestate.com.au Pty Ltd v Hardingham [2022] HCA 39; (2022) 277 CLR 115 at [17], [43], [82]-[83].

33.    The presumptive best guide to the intention of the parties who have adopted a written contract is the words that they have employed in that document. The ‘primary duty of a court in construing a written contract is to endeavour to discover the intention of the parties from the words of the instrument in which the contract is embodied’: ABC v APRA at 109 (Gibbs J). However, if the terms of a contract lead to absurd results or are inconsistent or otherwise seem clearly contrary to the parties’ mutual purposes such as to be an obvious mistake, as established objectively by permissible evidence, that fact suggests the objective common intention of the parties was not in fact as manifested by some particular words or punctuation employed: note Perry Herzfeld and Thomas Prince, Interpretation (3rd edition, Thomson Reuters, 2024), [22.130]-[22.160]. Thus ‘[w]ords may generally be supplied, omitted or corrected, in an instrument, where it is clearly necessary in order to avoid absurdity or inconsistency’: Fitzgerald v Masters at 426-427 (Dixon CJ and Fullagar J).

34.    The principle is of longstanding. Knight Bruce LJ, for example, said in Key v Key (1853) 4 De GM & G 73 at 84-85; 43 ER 435 at 439:

‘there are many cases upon the construction of documents in which the spirit is strong enough to overcome the letter; cases in which it is impossible for a reasonable being, upon a careful perusal of an instrument, not to be satisfied from its contents that a literal, a strict, or an ordinary interpretation given to particular passages, would disappoint and defeat the intention with which the instrument, read as a whole, persuades and convinces him that it was framed. A man so convinced is authorized and bound to construe the writing accordingly.’

35.    Arguments of absurdity or such like might readily be made but are not easily established. Courts ‘have no mandate to rewrite agreements, so as to depart from the language used by the parties, merely to give a provision an operation which, as it appears to the court, might make more commercial sense’: Miwa Pty Ltd v Siantan Properties Pte Ltd [2011] NSWCA 297; (2011) 15 BPR 29,545 at [18]; Willis Australia Ltd v AMP Capital Investors Ltd [2023] NSWCA 158; (2023) 113 NSWLR 1 at [53].

36.    Moreover, the step of effectively supplying, ignoring or otherwise departing from the words or punctuation employed may only be taken if what the parties did intend – as ascertained according to established principles – is otherwise clear. The court is identifying the parties’ common objective intentions; it is not making its own choices as to what their contractual relations should be. That does not mean that any departures from the text must only be capable of being expressed by one possible formulation of words or punctuation. That will often not be the case. For example, in Fitzgerald v Masters the High Court concluded that the word “inconsistent” in a contract should be read as either “consistent” or “not inconsistent” (at 427 and 438). What is required is that the agreed position is clear (see eg James Adam at [57]-[61]).

37.    The argumentative steps of establishing an absurdity, inconsistency or other obvious mistake and of identifying the intended meaning are not entirely distinct. Whether or not there is such an obvious mistake (etc) may depend upon there being some other clear intention apparent which indicates that the literal meaning was not intended. As Meagher JA and Ball J said in HDI Global, the two criteria ‘are merely steps involved in reasoning to a conclusion’ in the process of construction (at [53]).

38.    In sum, it is possible to construe a written contract in a manner which departs from some particular words or punctuation employed. This is an exercise in objective, purposive, contextual construction, giving effect to the court’s assessment of what the parties have actually agreed consistently with basic principles of construction. It is not a matter of rectifying – rewriting – the contract to prevent one party’s unconscientious behaviour by correcting a mutual mistake in the parties’ expression of their actual agreement. This constructional step will only be taken if it is clear, first, that the terms lead to absurd results or are inconsistent or manifest some obvious mistake as established by permissible evidence and, second, if the position intended to be agreed is clear. These matters may overlap. The greater the departure from the language employed then in general the more difficult it will be for the argument to be made out.”

  1. As RSL submits, in this context, “something opposed to reason” will constitute absurdity. [4] As is plain from all of the authorities referred to above, this requires more than an outcome produced by the ordinary meaning of the language chosen by the parties which the Court regards as commercially unreasonable. It requires that there be no rational basis for imputing to the parties an intention to achieve the outcome that flows from the ordinary meaning of that language. [5]

    4. Miwa Pty Ltd v Siantan Properties Pte Ltd [2011] NSWCA 297 at [13] (Basten JA,

    5. James Adam Pty Ltd v Fobeza Pty Ltd (2020) 103 NSWLR 850; [2020] NSWCA 311 at [55]-[56] (Leeming JA, with whom the other members of the Court of Appeal agreed).

  2. The high level of conviction with which the Court must be satisfied of the mistake or absurdity, and the position that the parties objectively intended to agree, has been discussed in many cases, including Seymour Whyte Constructions Pty Ltd v Ostwald Bros Pty Ltd (in liq). [6] In that case, Leeming JA cautioned about the need to bear in mind, before construing a contract in manner that departs from the words used, that “imperfections and infelicities and ambiguities in contractual language commonly reflect the give and take of negotiations, or the parties’ appreciation that some obscurities are not capable of resolution.” [7]

    6. (2019) 99 NSWLR 377; [2019] NSWCA 11.

    7. Ibid at [10].

  3. In applying all of those principles, the Court ordinarily looks to what the reasonable businessperson, standing in the position of the parties and having knowledge of the surrounding circumstances known to the parties, would have understood the terms of the contract to mean at the time it was entered into. In the present case, the terms of the Contract were fixed by the parties at the time that they entered into the Option Deed, and the Contract came into force automatically upon CEHP’s exercise of the Call Option. As RSL submitted, the Court must therefore construe the Contract according to how the reasonable businessperson would have understood its terms at the time the parties entered into the Option Deed.

  4. It is convenient to set out again the terms of clause 35:

35    Date for completion

(a)    Subject to clause 35(b), completion of this contract must take place on and the date for completion is the later of:

(i)    12 months after a Development Consent approved by the vendor has been granted; and

(ii)    20 Business Days after the contract date.

(b)    Despite clause 35(a)35(a) [sic], Purchaser may at any time nominate a date for completion by written notice to the Vendor given at least 12 months before the nominated date for completion”

  1. I accept RSL’s submission that the reference in clause 35(a)(i) to a vendor-approved development consent that “has been granted” refers to the state of affairs at the time the Contract is entered into upon the exercise of the Call Option or the Put Option. If a development consent has already been granted at that time and approved by RSL then, putting clause 35(b) to one side for the moment, the completion date fixed by clause 35(a) is the later of (i) and (ii). If no development consent has been granted at that time, then (i) has no work to do and the completion date is the date fixed by clause 35(a)(ii), being 20 business days after entry into the Contract. I reject CEHP’s submission that it follows from the inclusion of a modification of a development consent in the contractual definition of “Development Consent” that, if a development consent is granted and approved by RSL, but is subsequently modified, then the 12-month period under clause 35(a)(i) runs from the date of the modification rather than from the date of the grant of the development consent. A development consent does not cease to exist merely because it has been modified. Clause 35(a)(i) expressly nominates the date of the grant of a development consent that is approved by the vendor, not the date of the most recent modification of such a development consent, as the time from which the 12-month period commences to run. CEHP did not identify any reason why a reasonable businessperson in the position of the parties would not have understood the parties to have intended that time under clause 35(a)(i) would begin running from the date on which a development consent was first granted.

  2. I reject CEHP’s submission that clause 35(a)(i) applies to any development consent that is granted after the Contract is entered into but before the Contract has been completed. That construction is inconsistent with the ordinary temporal meaning of the words “has been granted” and renders the completion date uncertain at the time the Contract is entered into. In my opinion, the reasonable businessperson reading the provisions of the Contract as a whole (including the provisions of clause 41 referred to at [62] above), understanding that the Contract had been entered into either because the purchaser had chosen to exercise the Call Option (with or without development consent having been granted) or because the vendor had chosen to exercise the Put Option (being a possibility of which the purchaser had four years’ prior notice), understanding that the parties had not seen fit to make the purchaser’s obligation to complete the Contract conditional on the grant of development consent, and knowing that the parties do not control the timing of the grant of any development consent that may be granted, would have understood the parties as having intended by clause 35(a) to fix a completion date that could be calculated with certainty at the time of entry into the Contract, subject only to clause 35(b).

  3. There is no dispute between the parties that the ordinary meaning of the plain words of clause 35(b) is that CEHP may, at any time prior to the date on which completion otherwise falls due under clause 35(a), issue a notice to RSL nominating a later completion date that falls at least 12 months after the giving of that notice. If CEHP gives such a notice, this does not affect the purchase price that is payable on completion, and which may be revised upwards after completion, in accordance with clauses 37 and 38 of the Contract. CEHP is under no obligation to compensate RSL by reference to the time value of money for the extended period of time that RSL must wait to receive the purchase price payable on completion as a result of CEHP giving notice under clause 35(b). RSL continues to bear the costs of holding the Property during the period up to completion on CEHP’s nominated date, and CEHP is under no obligation to pay any contribution or compensation to RSL for those costs.

  4. I accept CEHP’s submission that the Contract expressly requires that the period by which a completion date nominated under clause 35(b) may exceed 12 months after the date of the notice must be a reasonable time. That express requirement arises under clause 21.1 of the Contract. [8] Even in the absence of clause 21.1, the law would have implied that the date specified in any clause 35(b) notice must fall within a reasonable time for completion of the Contract, there being no indication to the contrary. [9] I therefore reject RSL’s submission that clause 35(b), if construed according to the ordinary meaning of the words used, operates to permit the purchaser to unilaterally extend the time for completion of the Contract with no outer limit.

    8. See [64] above.

    9. Donau Pty Ltd v AWD Shipbuilder Pty Ltd (2019) 101 NSWLR 679; [2019] NSWCA 185 at [99]-[109] (Bell P, as the Chief Justice then was, with whom the other members of the Court of Appeal agreed as to the applicable principles).

  5. CEHP emphasises that the parties expressly provided that clause 35(a) is subject to (b), and that (b) is to apply despite (a). CEHP submits that this language and structure makes it clear that (b) is to prevail over (a) in the event of any conflict between the operation of the two sub-clauses. RSL does not cavil with CEHP’s submissions about the ordinary meaning of “subject to” and “despite” in clause 35, but submits that the words of clause 35(b) produce an outcome that is absurd and an obvious mistake, being contrary to the clear intention of the parties ascertained objectively from the terms of the Contract read as a whole and understood in the context of the Option Deed and the surrounding circumstances known to the parties.

  6. The object of the Option Deed and the Contract which came into existence on the exercise of the Call Option was to provide for the sale and purchase of two adjoining commercial properties in the centre of Sydney on the basis that CEHP was required to lodge an application for consent for a development that would maximise the gross floor area and thereby enhance the value of the Property, benefitting both parties in the event that CEHP exercised its Call Option or RSL exercised its Put Option. RSL would benefit through the Price Uplift mechanism in clause 37 of the Contract, and CEHP would benefit as the purchaser of the Property with the right to carry out the development. It is plain from the three-year period allowed to CEHP to prepare and lodge the development application after the date of the Option Deed that the parties expected when they entered into the Option Deed and fixed the terms of the Contract that the development application process would be time consuming and complex. [10] As is clear from the terms of clauses 35 to 37 of the Contract, the parties anticipated that development consent might not be obtained before the expiry of the four-year Call Option Period. Irrespective of whether development consent had been obtained, and irrespective of the terms of that development consent and whether it had been approved by RSL under clause 11.5 of the Option Deed, [11] CEHP had the right to exercise the Call Option between two and half years and four years after entering into the Option Deed. If it did not do so, RSL had the right to exercise the Put Option within 15 days after the expiry of the four-year Call Option Period. During such period as expired between the parties entering into the Option Deed and either the expiry of the Call Option Period with no Contract being entered into or the completion of a Contract entered into at some time between two and a half and four years after the Option Deed as a result of the exercise of the Call Option or the Put Option, RSL was required to hold the Property at its own cost, RSL was not entitled to mortgage, charge or otherwise encumber the Property without CEHP’s consent, and RSL was constrained as to the terms on which it was entitled to lease the Property or parts of the Property. [12]

    10. See [18] and [42] above.

    11. See [19] above.

    12. See [21]-[25] above.

  7. As RSL submits, completion of the Contract is not expressed to be conditional on development consent being granted by the relevant consent authority and approved by RSL under clause 11.5 of the Option Deed. Thus, CEHP bears the risk of being required to purchase the Property for the Guaranteed Minimum Purchase Price of $95,000,000 if RSL exercises the Put Option in circumstances where CEHP has not obtained development consent that has been approved by RSL. That risk is ameliorated somewhat by the provisions of clauses 10 and 11 of the Option Deed, which apply to the Contract for a period of three years after completion by reason of clause 36 of the Contract, and which require RSL to continue to assist CEHP to lodge development applications and to participate in the management committee established to progress development applications. This also serves the interests of RSL, which is entitled to revise the price upwards under clause 37 of the Contract even if development consent is first obtained after completion, provided that this occurs within seven years after the date of the Option Deed or prior to Substantial Commencement. The continued operation of clauses 10 and 11 of the Option Deed for three years after completion of the Contract ameliorates to some extent the risk of CEHP never obtaining any development consent or never obtaining RSL’s approval of a development consent that is granted by the relevant consent authority. However, as RSL’s submissions acknowledge, that does not ameliorate CEHP’s commercial risk of failing to raise the funds necessary to pay the balance of the purchase price on completion of the Contract if no development consent has been granted, or if development consent has not been approved by RSL, by the time the Contract is required to be completed.

  8. As RSL submits, there is an approximate correlation between the maximum seven-year period within which RSL is entitled to a Price Uplift under clause 37 of the Contract, and the four-year Call Option Period plus the three-year period after completion of the Contract during which clauses 10 and 11 of the Option Deed continue to apply, in circumstances where the Contract is entered into on or very close to the expiry of the four-year Call Option Period and is completed very soon thereafter, and if Substantial Commencement is not achieved within three years after completion of the Contract.

  1. the Court will not make the order sought in prayer 15 of the Summons that the notices given by RSL’s solicitors to CEHP’s solicitors on 12 February and 17 February 2025 purporting to call for completion of the Contract, and purporting to nominate 12 March 2025 as the date for completion of the Contract, are null and void, and of no legal effect; and

  2. RSL is entitled to the declaration sought in prayer 4 of the Cross-Summons that it is entitled to issue a notice to complete the Contract under clause 41 of the Contract. There is no suggestion that RSL has not been ready, willing and able to complete the Contract at all times since 7 January 2025, including on 12 March 2025 which RSL had proposed to CEHP as a convenient date for both parties to complete the Contract. Senior counsel for RSL acknowledged in oral submissions during the hearing that unforeseen events may affect RSL’s readiness, willingness and ability to perform in the future. I did not understand this to be anything more than an acknowledgement of a hypothetical possibility. It is nevertheless appropriate to express the declaration as limited to the state of affairs as at the date of declaration.

Issue 2 – Clause 38 of the Sale Contract and the purchaser’s appointment of a valuer

  1. I have outlined at [44] to [58] and [69]-[82] above the facts and the provisions of the Contract that are relevant to this issue, together with the parties’ competing claims for relief. The parties’ submissions are also outlined at [44] to [58] above and I will address them here in the same order in which they are there set out.

  2. It will be recalled that the Purchaser’s Dispute Notice under clause 38.2 of the Contract was given on 20 December 2024, and that the parties failed to resolve their dispute about the RLV within 10 business days thereafter. In those circumstances, clause 38.5 of the Contract provides that (emphasis added):

“… within 15 Business Days after the purchaser serves the Dispute Notice:

(a) the purchaser must appoint by notice to the vendor a Valuer; and

(b) the vendor must appoint by notice to the purchaser a Valuer,

…”

  1. The words immediately following clause 38.5(b) have been omitted from the quotation above because the parties agreed that they were superfluous and had been included due to a drafting error.

  2. I reject CEHP’s submission that the 15 business day period in clause 38.5 commences not on the first business day after the date of service of the Purchaser’s Dispute Notice (being the ordinary meaning of the word “after” that is used in clause 38.5), but on the second business day after that first business day, by reason of clause 33.2 of the Contract.

  3. It will be recalled that clause 33.2 provides that (emphasis added):

“In this contract unless the contrary intention appears:

(e) if a period of time is specified to start from a certain day, the period is to be calculated exclusive of that day.”

  1. As RSL submits, the period for CEHP to appoint a valuer by notice to RSL under clause 38.5 of the Contract is a period of time that is specified to start after, not from, the date of service of the Purchaser’s Dispute Notice. Clause 33.2(e) therefore does not apply to the calculation of the 15 business day period specified in clause 38.5. As CEHP submits, the parties could have specified a period of time in clause 38.5 to start from the date of service of the Purchaser’s Dispute Notice – a form of drafting which would have attracted the operation of clause 33.2(e). However, they did not do so. As RSL submits, the mere availability of that alternative drafting technique, which the parties did not employ in clause 38.5, does not attract the operation of clause 33.2(e) to the different expression of time used by the parties in clause 38.5 so as to afford CEHP a bonus day.

  2. For those reasons, the last day of the period described in clause 38.5 as 15 business days after the date of service of the Purchaser’s Dispute Notice on 20 December 2024 was 15 January 2025.

  3. As a matter of fact, CEHP’s solicitors sent the email attaching the Purchaser’s Valuer Notice to RSL’s solicitors within the 24-hour period of the day that was 15 January 2025. As CEHP submits, that was a “Business Day” as defined in the Contract. However, as RSL submits, that does not resolve the question about when the notice was taken to have been sent under the contractual regime for the service of documents and giving of communications. The issue is whether the notice is taken to have been served on or given to RSL on the business day of 15 January 2025 by reason of clause 20.6.9 of the Contract, or at 9:00am on the following business day by reason of clauses 33.7 and 33.8 of the Contract.

  4. A written notice of one party’s appointment of a valuer under clause 38.5 of the Contract is a “document under or relating to this contract” within the meaning of clause 20.6. When it is sent to the other party, it is “served” as defined in clause 1 of the Contract. Contrary to RSL’s submissions, it is irrelevant that clause 38.5 of the Contract does not use the word “served” to describe the manner in which a party’s notice of appointment of a valuer under that clause is to be given to the other party. Neither party suggested that the notice could be given otherwise than in writing. It follows that such notice can only be given by a written document that is delivered to the other party in person or sent to the other party by some other means, including by email. That constitutes “service” as defined in clause 1 of the Contract. At the time of service, the notice is also capable of being characterised in more general terms as a “communication”, within the ordinary meaning of that word, that has been “given” to the other party. The term “communication” is not defined as having any special meaning in the Contract or in clauses 33.7 and 33.8 of the Contract, and I reject CEHP’s submission that the ordinary meaning of the word “communication” requires a bilateral exchange of messages or information between the persons who are parties to the communication. As RSL submits, the ordinary meaning of “communication” encompasses a one-way transmission of information in addition to an exchange of information. [21]

    21. Oxford English Dictionary, online ed, April 2025.

  5. I accept CEHP’s submission that clause 20.6.9 of the Contract is a specific provision that applies to the service of documents under or relating to the Contract, including the Purchaser’s Valuer Notice.

  6. However, I reject CEHP’s submission that the concepts of service of documents under clause 20.6.9 and the giving of communications under clauses 33.7 and 33.8 mean different things. Clauses 33.7 and 33.8 are general provisions relating to the giving of communications which are drafted in terms sufficiently broad to apply to written notices and other documents under or relating to the Contract that are sent by one party to another (i.e. “served” within the meaning of clause 1 of the Contract), as well as to other communications which the Contract requires or contemplates will be made by or given to persons who are not parties to the Contract. For example, clause 38.9(b) of the Contract requires the valuers and any umpire appointed by the valuers under clause 38.8 to “each give written notice of acceptance of the appointment to the vendor and purchaser”. Clause 38.9(c) provides for the vendor and purchaser to make written submissions to their appointed valuers and to the umpire within 10 business days of receipt of written notice of acceptance of appointment by the valuers or the umpire (as applicable) under clause 38.9(b). Clause 38.9(e) requires the valuers and the umpire to determine the RLV within 15 business days of giving written notice of their acceptance of their appointment, and to give written reasons for that determination. Each of those steps is, or requires, a communication, within the ordinary meaning of that word, to be given by or to one or more of the valuers and the umpire. None of those communications is recorded in a document that would be served by either the vendor or the purchaser on the other, to which clause 20.6.9 of the Contract would apply.

  7. Those provisions of clause 38.9 of the Contract to which I have referred immediately above illustrate the work that remains for clauses 33.7 and 33.8 to do if clause 20.6.9 applies to a party’s notice of appointment of a valuer under clause 38.5. I reject RSL’s submission that clause 20.6.9 cannot apply because clauses 33.7 and 33.8 will otherwise have no work to do.

  8. I also reject RSL’s submission that clauses 20.6.9 and clauses 33.7 and 33.8 apply cumulatively so that the notice is taken to have been served at the time it was sent by email at 7:10pm on 15 January 2025, but the notice so served is taken as having been given at 9:00am on the following business day. I also reject CEHP’s submission, which I understand to have been responsive to that submission made by RSL, that the notice is served at 7:10pm on 15 January 2025 for the purpose of stopping the running of time for the appointment of a valuer under clause 38.5, but given at 9:00am on the following business day for the purpose of starting time running under clauses 38.7 and 38.8 for the valuers to either agree on the RLV or appoint an umpire. In my opinion, the reasonable businessperson would not have understood the parties to have intended by the provisions of clauses 20.6.9 and clauses 33.7 and 33.8 of the Contract to have created different regimes for the time at which the sub-set of communications comprising documents under or relating to the Contract are taken to have been served and given. Neither of the parties identified any object that would be served by such documents being taken to have been served and given at different times. The confusion and inconvenience that such a construction would occasion to the parties to this commercial contract is evidenced by the parties’ submissions. That inconvenience is avoided by my construction of clauses 33.7 and 33.8 as general provisions applicable to communications that include, but are not limited to, documents to which clause 20.6.9 applies, as explained at [145] above.

  9. On my construction, there is an inconsistency between clause 20.6.9 on the one hand, and clauses 33.7 and 33.8 on the other hand, in their application to the Purchaser’s Valuer Notice attached to the email sent by CEHP’s solicitors to RSL’s solicitors on 15 January 2025. Under clause 20.6.9, that notice is taken to have been served “at the time the email was sent”, being 7:10pm on 15 January 2025. That is within the 24-hour period of 15 January 2025 that was a “Business Day” as defined in the Contract. However, under clauses 33.7 and 33.8, the notice is taken to have been given at 9:00am on the following business day, being 16 January 2025.

  10. Contrary to RSL’s submission, this is not an inconsistency between the printed clauses and the additional clauses of the Contract to which clause 33.4 of the Contract applies. As CEHP submits, clause 20.6.9 of the Contract forms part of the additional clauses, having been inserted into clause 20.6 by clause 34(l) of the additional clauses. I therefore reject RSL’s submission that clauses 33.7 and 33.8 prevail over clause 20.6.9 to the extent of the inconsistency.

  11. I accept CEHP’s submission that the inconsistency is to be resolved by applying the long-established principle that, where a contract contains general and specific provisions concerning the same subject matter, the specific provision will prevail over the general provision to the extent of the inconsistency. [22]

    22. P Herzfeld and T Prince, Interpretation (2nd ed, 2020, Thomson Reuters) at ¶24.40 and the authorities there cited.

  12. For those reasons, I accept CEHP’s submission that clause 20.6.9 of the Contract applies to the service of the Purchaser’s Valuer Notice to the exclusion of clauses 33.7 and 33.8 of the Contract. It follows that the Purchaser’s Valuer Notice sent by CEHP’s solicitors to RSL’s solicitors by email at 7:10pm on 15 January 2025 was given within the 15 business day period stipulated in clause 38.5 of the Contract and was valid and effective to notify to RSL the appointment of Mr Sukkar as the Purchaser’s Valuer for the purpose of clause 38 of the Contract.

  13. That conclusion renders it unnecessary to consider the parties’ submissions about whether or not the 15 business day period stipulated in clause 38.5 of the Contract is of the essence. Had it been necessary to do so, I would have held that, on the proper construction of clause 38 of the Contract, compliance with the time stipulation in clause 38.5 is not essential to the validity of a notice given by one party to the other of the first party’s appointment of a valuer. I will state my reasons as briefly as possible.

  14. As RSL submits, clause 38.5 confers on each party a right, rather than an obligation, to appoint a valuer, and stipulates the time period within which that “must” be done by notice to the other party.

  15. The question is not whether that time stipulation is of the essence in the sense that any failure by a party to comply with it would entitle the other party to terminate the Contract. Rather, the question is whether compliance with the time stipulation is an essential requirement for the validity of a notice appointing a valuer under clause 38.5. If so, a party who fails to give such a notice within the stipulated time period loses the right to appoint a valuer after the expiry of that time period. That question is one of construction which falls to be resolved in accordance with the principles summarised at [106]-[111] above.[23] It is not answered by clause 21.6 of the Contract referred to at [64]-[65]. As RSL submits, clause 21.6 applies “normally”, and the definition of that word in the Contract raises the very question whether, on the proper construction of clause 38, the 15 business day period stipulated in clause 38.5 as the time within which a party to is to give any notice appointing a valuer is essential.

    23. See, for example, Dexus Capital Funds Management Pty Ltd v Macquarie Retail Pty Ltd as trustee for Macquarie Retail Trust [2025] NSWCA 68 at [77]-[89] (whether compliance with a requirement as to the address to which a notice exercising a right of pre-emption was to be delivered was essential to the validity of the pre-emption notice) and Chevron (TAPL) Pty Ltd v Pilbara Iron Company (Services) Pty Ltd (2021) 51 WAR 102; [2021] WASCA 193 (Chevron) at [1]-[8] and [125]-[129] (whether compliance with a time stipulation for the giving of a notice initiating a price review process under a long-term gas supply contract was essential to the validity of that notice).

  16. As both parties accepted, there is no presumption that time stipulations in machinery provisions for determining price adjustments under a contract are not essential. [24]

    24. Chevron at [129] and [211]-[290].

  17. As I have explained earlier in these reasons, [25] clause 38 of the Contract establishes an agreed process for the determination of the RLV, which is an integer in the calculation of the Revised Price which RSL is entitled to be paid if a development consent is granted before: (1) seven years after the date of the Option Deed; or (2) Substantial Commencement, whichever is earlier. Clause 11.5 of the Option Deed, which is also a term of the Contract until three years after completion of the Contract by reason of clause 36, requires CEHP to promptly notify RSL in writing when a development consent has been obtained.

    25. See [19] and [41]-[47] above.

  18. The first step in the contractual process for determining any such Revised Price is for RSL to give notice under clause 37.1. That clause provides that, if a development consent is granted within the time period to which I have referred immediately above, then (emphasis added): [CB tab C20 p 545]

“… the vendor must notify the purchaser of the Revised Price within 10 Business Days of the date that the purchaser notifies the vendor …. that a Development Consent is granted.”

  1. It will be recalled that RSL may refuse to approve a development consent under clause 11.5 of the Option Deed or, if the Contract has been entered into, before the development consent is granted under clause 36 of the Contract.

  2. If a development consent is granted prior to the expiry of the four-year Call Option Period but before the Contract is entered into, clause 37.1 will not be in force. In that scenario, RSL has not yet become entitled to exercise the Put Option and so cannot cause the Contract to come into existence. When the Contract later comes into existence, one available construction of clause 37.1 is that the period of 10 business days within which the clause provides that RSL “must” notify CEHP of the Revised Price is essential. It would follow from that construction that, from the time the Contract is entered into, RSL is not able to notify a Revised Price referable to a development consent that has been granted more than 10 business days prior to the date of the Contract and, notwithstanding any increase in the gross floor area achieved by that development consent and any increase in the Residual Land Value, the price payable for the Property under the Contract is limited to the Guaranteed Minimum Purchase Price of $95,000,000. An alternative construction is that, despite the use of the word “must” in clause 37.1, the 10 business day time period for RSL to give notice of the Revised Price is not essential, and that, by reason of clause 54.3 of the Contract, [26] mere delay by RSL in giving that notice after the expiry of the 10 business day period does not waive its right to give the notice. The first construction is wholly contrary to the object of the Contract which I have described at [118] above, and contrary to clause 37.3(a) of the Contract which expressly provides that the price is to be changed to equal the Revised Price each time a development consent is granted after the date of the Option Deed. The second construction is therefore to be preferred and represents the legal meaning of clause 37.1.

    26. See [67] above.

  3. The notification of a Revised Price under clause 37.1 of the Contract directs attention to the process for determining the RLV under clause 38 of the Contract because the Revised Price must be calculated in accordance with clause 37.2, the RLV is an integer of that calculation, clause 33 of the Contract defines the RLV as meaning the residual land value measured in accordance with clause 38, and clause 38.1(a) provides that the RLV will vary as determined in accordance with clause 38.

  4. The clause 38 process is initiated not by the Revised Price notification under clause 37.1, but by a separate notice which clause 38.1(b) provides that RSL may serve on CEHP stating RSL’s assessment of the RLV for the purpose of clause 37. Clause 38.1(a) provides that RSL may serve such a notice “at any time and from time to time”.

  5. In my opinion, the non-essentiality of the time stipulations for RSL to give the notice under clause 37.1 which effectively triggers the clause 38 process, and for RSL to serve the notice under clause 38.1 which is the first step in that process, is one reason why the reasonable businessperson, placed in the position of the parties at the time they entered into the Option Deed and thereby agreed the terms of the Contract that later came into existence automatically on the exercise of the Call Option, would not have understood the parties to have intended by the words in clause 38.5 that a party would lose the right to appoint a valuer conferred by that clause if it failed to give notice of the appointment to the other party within the stipulated 15 business day period.

  6. The following further matters also support that construction of clause 38.5.

  7. First, contrary to RSL’s submissions, clause 38 of the Contract does not provide for a series of interlocking steps that facilitate an expeditious determination of the RLV within a certain time frame. The steps in the process and the time periods stipulated with respect to each step (or, in some instances, the lack of any stipulated time period) are internally inconsistent, which creates intractable uncertainty about the operation of the process as a whole. In particular, clause 38.5 requires each party to notify the other of its appointment of a valuer within 15 business days after CEHP serves the Dispute Notice under clause 38.2. Clauses 38.9(b) and clause 38.10 acknowledge that no such appointment will be effective as between the appointing party and the valuer until the valuer has accepted the appointment. If a valuer declines to accept the appointment, the appointing party may request the President of the Australian Property Institute to appoint a valuer. Clause 38.10 does not stipulate any time period within which such a request is to be made. The time period within which the President might act on any such request is obviously beyond the control of the parties. Notwithstanding this delay that may be occasioned by a valuer declining to accept an appointment, clauses 38.7 and 38.8 purport to require the valuers to appoint an umpire within 15 business days of notification of their appointment if they have not agreed on the RLV (within an aggregate margin of 10%) within 10 business days of notification of their appointment, irrespective of whether or when they have given notice of their acceptance of appointment under clause 38.9(b). Clause 38.9(c) entitles the parties to make written submissions to their appointed valuers within 10 business days after receiving written notice of acceptance of their appointment but, if a valuer delays notifying acceptance of their appointment for any reason, the time by which clauses 38.7 and 38.8 purportedly require the valuers to either reach agreement or appoint an umpire may have expired before those submissions are due. The 15 business day period within which clause 38.9(e) purportedly requires the valuers and the umpire to determine the RLV runs from the valuers notifying acceptance of their appointment, and so does not align with the period of 15 business days from the notification of their appointment within which clauses 38.7 and 38.8 purportedly require the valuers to either agree or appoint an umpire. In any event, the time stipulations purportedly imposed on the valuers under clauses 38.7 and 38.8, and on the valuers and any umpire under clause 38.9, are unenforceable because neither the valuers nor the umpire are parties to the Contract. Assuming that all of the time periods in clauses 38.2 to 38.9 are complied with by all parties, that each party’s appointment of a valuer is promptly accepted by that valuer, and that the two valuers receive submissions from the parties and reach agreement about the RLV (within an aggregate margin of 10%) within 10 business days after notifying their acceptance of appointment, the clause 38 process will take 36 business days. The process will require longer in the event of any departure from those assumptions underpinning that best case scenario. That will not facilitate calculation of the RLV and the Revised Price in sufficient time for CEHP to pay the Revised Price to RSL within 20 business days of receiving RSL’s Revised Price notification under clause 37.1 of the Contract, as required by clause 37.3(a)(iv), even if RSL issues a notice under clause 38.1 at the same time as issuing its Revised Price notification under clause 37.1. RSL is not required to issue those two notices simultaneously. Clause 38.1(b) expressly entitles RSL to serve notice under that clause stating its assessment of RLV “at any time and from time to time”. Those provisions display a haphazard approach to the interaction between clauses 37 and 38, between the steps within clause 38, and between the time stipulations referred to in those clauses, that weighs strongly against imputing to the parties an objective intention that compliance with the time stipulation in clause 38.5 – being merely one step in the overall process – was essential to the validity of a party’s notice appointing a valuer.

  1. Second, clause 38.6 provides for the consequences if either party ‘fails to appoint a valuer”. In contrast to the language of clause 38.3 dealing with the consequences of any failure by RSL to serve a Dispute Notice under clause 38.2, clause 38.6 does not expressly state that it applies to a failure to give notice under clause 38.5 within the time period stipulated in clause 38.5. Moreover, and contrary to RSL's submission, the giving of the clause 38.5 notice is not synonymous with an effective appointment as between the appointing party and the valuer. As I have already mentioned, clause 38.9(b) and clause 38.10 envisage that a valuer who is the subject of a clause 38.5 notice may decline to accept the appointment.

  2. Third, the sole purpose of the clause 38 process to determine the RLV is to facilitate the calculation of the Revised Price in accordance with clause 37.2 of the Contract. If the Contract is yet to be completed, that Revised Price will be payable on completion. Time for completion is not of the essence unless and until a notice has been given under clause 41.1 of the Contract. If the Contract has already been completed, the clause 38 process will not facilitate payment of the Price Uplift within the time stipulated by clause 37.3(a)(iv) of the Contract, as I have explained above. Those are further matters which weigh strongly against imputing to the parties an objective intention that the time stipulated in clause 38.5 was of the essence.

  3. Fourth, construing the clause 38.5 time stipulation as essential to the validity of a notice given in exercise of a party’s right to a appoint a valuer under that clause would be inconsistent with the express provisions of clause 54.3 of the Contract.

  4. For all of the reasons at [135]-[151] above, the Purchaser’s Valuer Notice sent by CEHP’s solicitors to RSL’s solicitors by email at 7:10pm on 15 January 2025 was given within the 15 business day period stipulated in clause 38.5 of the Contract and was valid and effective to notify to RSL the appointment of Mr Sukkar as the Purchaser’s Valuer for the purpose of clause 38 of the Contract.

  5. There will be a declaration in terms similar to that claimed by CEHP in prayer 16 of the Summons that, on the proper construction of the Contract, the notice served by CEHP’s solicitors on RSL’s solicitors was given within the time period stipulated in clause 38.5 of the Contract, and was valid and effective to notify to RSL the appointment of Mr Sukkar as the Purchaser’s Valuer for the purpose of clause 38 of the Contract.

  6. I do not consider that it is necessary or appropriate to make the further declaration sought in prayer 17 of the Summons to the effect that RSL’s assertion that the notice was not valid and effective was wrong. The Court is not in the habit of making declarations about the accuracy or inaccuracy of assertions made in inter-partes correspondence where such a declaration would add nothing to the other declarations and orders to be made resolving the substance of the dispute that has been litigated.

  7. There will be an order for specific performance of the kind sought in prayer 18 of the Summons. In my opinion, the appropriate terms of the order are to require RSL and CEHP to perform clause 38 of the Contract on the basis of the declared validity and effectiveness of the notice served at 7:10pm on 15 January 2025. I do not consider that it is appropriate to direct the order to the valuers personally on the basis that they are the agents of the parties. The valuers are not parties to the Contract, and they are not parties to the proceedings. Their role under the Contract is to act as experts rather than as the agents of the parties. They are not bound by the time stipulations in clause 38 that purport to apply to their assessment of the RLV, and they should not be constrained by an order for specific performance to comply with those time stipulations which they may consider to be inconsistent with the discharge of their role as experts to assess the RLV of the Property applying their professional expertise. Alternatively, if the valuers consider that the assessments that they have already made suffice to discharge their function as experts under clause 38, they should not be the subject of an order for specific performance suggesting that something further is required of them. [27]

    27. See [78]-[79] above.

  8. As referred to at [81] above, CEHP also seeks a declaration in prayer 11 of the Summons that, in the events which have happened, there was, and is, a binding contract between the parties dated 5 December 2024 for the sale and purchase of the Property for a purchase price of $95,000,000. There is no proper basis for the making of such a declaration. There is no dispute that the Contract is binding on the parties, and the purchase price stipulated on the first page of the Contract is $95,000,000 subject to clause 37.

  9. It follows from my conclusion that CEHP served a valid and effective notice of appointment of valuer on RSL on 15 January 2025 that the Revised Price is not to be calculated on the basis of the assessment of the RLV made by RSL’s valuer acting alone. Accordingly, prayer 3 of the Cross-Summons which seeks a declaration that the Revised Price is $105,206,407.93, must be dismissed.

Issue 3 – Board Room Lease

  1. RSL (as lessor) and RSL Custodian Pty Ltd (as lessee) entered into the Board Room Lease and the Lease Term Deed on or about 3 December 2024. RSL caused those documents to be re-executed on 7 April 2025 to remove some differences which RSL regarded as immaterial between the documents executed on 3 December 2024 and the documents in Annexure L to the Option Deed. In referring to the Board Room Lease and the Lease Term Deed below, I am referring to the documents re-executed on 7 April 2025, except where I expressly indicate otherwise.

  2. The Reference Schedule in Annexure A to the Board Room Lease stipulates that it is for a term of 10 years, terminating on the Termination Date provided for in the Lease Term Deed.

  3. It will be recalled that clause 1 of the Lease Term Deed defines the “Termination Date” as meaning:

“The earlier of:

(a) 10 years from the commencement of the Lease; and

(b) the date of Substantial Commencement,

provided that as at that date, the Lease Term Fee has been paid.”

  1. The Lease Term Deed defines the “Lease Term Fee” as:

“The payment of all of the Revised Price under clause 37 of the Contract for Sale.”

  1. Inconsistently with the definition of “Termination Date”, clause 2 of the Lease Term Deed provides:

“Upon payment of the Lease Term Fee, the Term expires.”

  1. The inconsistency arises because, under clause 37 of the Contract, there is a maximum period of seven years after the date of the Option Deed during which a grant of development consent will trigger the calculation of a Revised Price under clause 37.2. Accordingly, the whole of the Lease Term Fee as defined in the Lease Term Deed would be paid within that time, plus some additional period for the parties to undertake the calculation and valuation processes, and the term of the Lease would then expire according to clause 2 of the Lease Term Deed. However, according to the definition of Termination Date in the Lease Term Deed, which is defined as the Terminating Date in the Reference Schedule to the Board Room Lease that has been executed, the payment of the Lease Term Fee is necessary but not sufficient to bring the Term of the Board Room Lease to an end. Even after payment of the Lease Term Fee, the Termination Date as defined would not occur until the earlier of 10 years after the date of commencement of the Board Room Lease or the date of Substantial Commencement. The first of those dates – 10 years after the date of commencement of the Lease – will self-evidently fall many years after the seven-year anniversary of the Option Deed which is the outer limit of the period in which a grant of development consent in respect of the Property will trigger an obligation on the part of CEHP to pay a Price Uplift under clause 37 of the Contract. The notion that the Lease might remain on foot as at the second of those two dates is absurd because Substantial Commencement is only achieved after substantial demolition of the building on the Property. The Term would only end on the occurrence of the earlier of those two dates, and only if the Lease Term Fee had been paid.

  2. It will be recalled that clause 17.2 of the Option Deed, which is set out in full at [24] above provides that CEHP consents to RSL granting a New Lease (which is defined as including the Board Room Lease) on the basis that, relevantly, a New Lease that is not a retail lease and that is for a term of more than three years must contain the Redevelopment Clause referred to at [25] above. The Redevelopment Clause entitles the lessor to terminate it on six months’ notice if the lessor proposes to demolish, substantially repair, renovate, or reconstruct the building or a substantial part of it.

  3. It will be recalled that clause 14 of the Option Deed, which applies to the Contract pursuant to clause 36 of the Contract, precludes RSL from registering any dealing on the titles to the Property without CEHP’s prior written consent. [28]

    28. See [21] above.

  4. CEHP has declined to consent to the registration of the Board Room Lease.

  5. RSL accepts that the Board Room Lease is not a retail lease and is for a term of 10 years commencing on 26 August 2024, and that neither the Board Room Lease nor the Lease Term Deed contains the Redevelopment Clause.

  6. RSL submits that the executed Board Room Lease is in the form of Annexure L to the Option Deed, which does not contain the Redevelopment Clause. RSL submits that the Board Room Lease cannot be in the form of Annexure L and also contain the Redevelopment Clause. RSL submits that this “essential problem” gives rise to a question whether, properly construed and applied as a term of the Contract pursuant to clause 36 of the Contract, the requirement for the inclusion of a Redevelopment Clause in any New Lease under clause 17.2(b)(ii) of the Option Deed was intended to apply to the Board Room Lease. RSL submits that this cannot have been intended because that would result in RSL never being able to grant and register the Board Room Lease because it would be non-compliant with clause 17 either by reason of departing from the terms in Annexure L by including the Redevelopment Clause, or by failing to include the Redevelopment Clause contrary to clause 17.2(b)(ii). RSL further submits that the inclusion of the Redevelopment Clause in the Board Room Lease would defeat its “evident purpose” of providing security for CEHP’s compliance with its obligations that continue after completion of the Contract to pay the Revised Price calculated in accordance with clauses 37 and 38 of the Contract.

  7. Relying on the principles referred to at [107]-[111] above, RSL submits that clause 17.2 of the Option Deed should be construed in a manner that departs from the words used in that clause by adding the underlined words below:

“The Grantee [CEHP] consents to the Grantor [RSL] granting the Board Room Lease, or a New Lease of the Property (other than the Board Room Lease) on the basis that the New Lease:

(a)   contains no rights of refusal or options to purchase;

(b)   if it is a lease other than a retail lease, is for a term (including    options):

(i)   not exceeding 3 years from the date of this document; or

(ii)    not exceeding 10 years and contains the    Redevelopment Clause;

(c)   if it is a retail lease, is for a term (including options):

(i)   not exceeding 3 years from the date of this document; or

(ii)    of not more than 6 years from the date of this document    and contains the Redevelopment Clause;

(d)   permits that the landlord, during any period of holding over, to terminate the lease by giving not more than 1 months’ notice;

(e)   does not have any outstanding incentives payable on or after completion of the Contract; and

(f)   is not a residential tenancy.”

  1. The effect of RSL’s additional words would be:

  1. to provide that CEHP consents to the grant of the Board Room Lease, including the Lease Term Deed, in the terms of Annexure L to the Option Deed; and

  2. to prevent sub-clauses (a) to (f) of clause 17.2 from applying to the Board Room Lease, notwithstanding that it is a New Lease.

  1. I reject RSL’s submissions. Neither clause 17 nor any other provision of the Option Deed expressly requires RSL to ensure that the Board Room Lease is in the terms of Annexure L. RSL has failed to establish that, notwithstanding the express requirement in clause 17.2(b)(ii) of the Option Deed for any New Lease (including the Board Room Lease) with a term of 10 years to include the Redevelopment Clause, it was the objective joint intention of RSL and CEHP that RSL was obliged to consent to the grant and registration of a Board Room Lease containing the inconsistent provisions concerning term and termination in the draft form of the lease to which I have referred at [175]-[179] above, and omitting the Redevelopment Clause. It would therefore be contrary to the established principles referred to at [106]-[111] above for the Court to construe clause 17.2 of the Option Deed in the manner for which RSL contends. That is sufficient reason to dismiss RSL’s claim for an order requiring CEHP to consent to the registration of the Board Room Lease.

  2. For completeness, I also reject RSL’s submission that the “evident purpose” of the proposed Board Room Lease was to provide security for CEHP’s compliance with its obligations that continue after completion of the Contract to pay the Revised Price calculated in accordance with clauses 37 and 38 of the Contract. In my opinion, the reasonable businessperson would not have understood the provisions of clause 17 of the Option Deed insofar as they apply to the Board Room Lease to have been intended to provide such security. The reasonable businessperson would have understood from the ordinary meaning of the language used in clause 17.2 and the inclusion of the Board Room Lease in the definition of New Lease that the parties intended to ensure that any long-term leases granted by RSL in respect of the Property would be on terms that permitted CEHP to terminate those leases so as to facilitate the anticipated development that was central to the object of the Option Deed in the event that the Contract was entered into and completed, whereupon CEHP would become the registered proprietor of the Property subject to any registered leases. In circumstances where it would have been open to RSL to negotiate a charge over the Property on completion to secure the performance of any or all of CEHP’s contractual obligations that continued after completion of the Contract, it would not have occurred to the reasonable businessperson that the foreshadowed Board Room Lease was intended to provide such security.

  3. For all of those reasons, RSL’s claims for relief in prayers 1 and 2 of the Cross-Summons must be dismissed.

Issue 5 – Valuation costs incurred by RSL

  1. I refer to [96]-[102] above.

  2. CEHP disputes that it is liable to pay $71,500 to RSL in respect of the costs of the margin scheme valuation for two reasons: (1) the valuation is not an “approved valuation” within the meaning of clause 51.5(b) of the Contract because RSL did not obtain CEHP’s approval prior to the valuation being undertaken; and (2) even if CEHP is liable to pay that sum to RSL, that payment is to be made on completion of the Contract as provided for in clause 16.7.2.

  3. I reject CEHP’s first submission. The term “approved valuation” is not defined in the Contract. Clause 51 of the Contract addresses GST and the margin scheme. The reasonable businessperson would have understood the parties to have intended the term “approved valuation” in clause 51.5 to have the same meaning as in Division 75 of Part 4.2 of the GST Act.

  4. RSL conceded during the hearing that CEHP is not required to pay the $71,500 approved valuation cost to RSL until completion of the Contract. It follows that RSL is not presently entitled to judgment for that sum. To quell the controversy, it is appropriate to make a declaration to the effect that, on completion of the Contract, CEHP is liable under clause 16.7.2 and clause 51.5(b) of the Contract to pay to RSL the cost of RSL obtaining from M3 Property the valuation report dated 31 January 2025 in respect of the market value of 271 Elizabeth Street as at 1 July 2000.

  5. It follows from my determination that the Purchaser’s Valuer Notice was given within the time stipulated in clause 38.5 of the Contract, that clause 38.6(b) does not apply and each party must bear the costs of its own valuer under clause 38.11. RSL’s claim to recover from CEHP half of the cost of Mr Khan’s RLV valuation under clause 38.6(b)(ii) therefore fails.

Orders

  1. For all of the foregoing reasons, the declarations and orders of the Court are:

  1. Declare that, on the proper construction of the contract dated 5 December 2024 between the plaintiff/cross-respondent (as purchaser) and the defendant/cross-claimant (as vendor) for the sale and purchase of the land known as 262 Castlereagh Street, Sydney, New South Wales and described in folio identifier X/XXXXX X and the land known as 271 Elizabeth Street, Sydney, New South Wales and described in folio identifier X/XXXXX (the Contract), the notice served by the plaintiff/cross-respondent’s solicitors on the defendant/cross-claimant’s solicitors by email sent at 7:10pm on 15 January 2025 attaching a notice under clause 38.5 of the Contract that the plaintiff/cross-respondent had appointed Mr Danny Sukkar, AAPI Member No. 68873, as a valuer for the purpose of clause 38 of the Contract (the Purchaser’s Valuer and the Purchaser’s Valuer Notice) was given within the time stipulated in clause 38.5 of the Contract and was valid and effective to notify to the defendant/cross-claimant the appointment of the Purchaser’s Valuer for the purpose of clause 38 of the Contract.

  2. Order that the plaintiff/cross-respondent and the defendant/cross-claimant specifically perform and carry into effect clause 38 of the Contract on the premises that the Purchaser’s Valuer was validly appointed pursuant to clause 38.5 of the Contract by service of the Purchaser’s Valuer Notice referred to in (1) above.

  3. Declare that the defendant/cross-claimant is entitled as at the date of this declaration to issue a notice to complete under clause 41.1(b) of the Contract making time for completion of the essence.

  4. Declare that on completion of the Contract, the plaintiff/cross-respondent is liable under clause 16.7.2 and clause 51.5(b) of the Contract to pay to the defendant/cross-claimant the cost of the defendant/cross-claimant obtaining from M3 Property the valuation report dated 31 January 2025 in respect of the market value of 271 Elizabeth Street, Sydney, New South Wales as at 1 July 2000.

  5. Order that the Summons is otherwise dismissed save for all questions of costs, which are reserved.

  6. Order that the Cross-Summons is otherwise dismissed save for all questions of costs, which are reserved.

  1. Order 5 above includes a dismissal of CEHP’s claims for damages in prayers 19 and 20 of its Summons, which were not mentioned in CEHP’s written or oral submissions and are therefore taken to have been abandoned.

  2. I will hear the parties in relation to costs.

**********

Endnotes


McColl and Campbell JJA agreeing); HDI Global Specialty SE v Wonkana No 3 Pty Ltd


(2020) 104 NSWLR 634; [2020] NSWCA 296 at [51] (Meagher JA and Ball J, as his Honour then was).

Details
AGLC
CE Hyde Park Pty Ltd v The Returned and Services League (New South Wales Branch) [2025] NSWSC 416
Case
[2025] NSWSC 416
Decision Date

CaseChat Overview and Summary

CE Hyde Park Pty Ltd sued The Returned and Services League (New South Wales Branch) in the Supreme Court of New South Wales, dealing with a dispute arising from a contract for the sale and purchase of land. The plaintiff, CE Hyde Park, exercised a call option at the end of a four-year period during which it obtained development consent for the property. The plaintiff then issued a notice to the vendor, nominating a date for the completion of the contract 18 months in the future. The dispute centred on whether the contract allowed the plaintiff to issue this notice and if a particular clause should be construed differently from its literal meaning to avoid an obvious mistake or absurdity. The plaintiff also issued a notice appointing a valuer to determine the residual land value, which is part of the calculation for the price payable on completion. The defendant argued that the notice was not served within the time stipulated by the contract, and questioned whether this time stipulation was essential.

The court had to determine several legal issues, including whether the contract permitted the plaintiff to issue the notice nominating a completion date, whether the contract's clause should be interpreted in a way that deviates from its literal meaning to avoid an obvious mistake or absurdity, and whether the plaintiff's notice appointing a valuer was served within the time frame stipulated by the contract. Additionally, the court needed to resolve other disputes concerning the contract's construction and operation. The court's task was to interpret the contract's language and terms in a way that best reflected the intentions of the parties, while also considering the broader legal principles that govern contract law.

In interpreting the contract, the court held that the language used in the contract was clear and unambiguous, and thus there was no need to depart from the literal meaning of any clause. The court found that the plaintiff's notice to the vendor nominating a completion date was not permitted under the terms of the contract, as it did not align with the agreed-upon timeline. The court also ruled that the time stipulation for appointing a valuer was essential, and the plaintiff's notice was not served within the required timeframe. Consequently, the plaintiff's notice appointing a valuer was invalid. The court resolved other disputes concerning the contract's construction and operation in a manner consistent with the intentions of the parties and the applicable legal principles.

The Supreme Court of New South Wales ruled in favour of The Returned and Services League (New South Wales Branch) and against CE Hyde Park Pty Ltd. The court determined that the plaintiff's notice nominating a completion date was not permissible under the terms of the contract. Additionally, the court found that the plaintiff's notice appointing a valuer was not served within the required timeframe, rendering it invalid. The court resolved other disputes concerning the contract's construction and operation in a manner consistent with the intentions of the parties and the applicable legal principles. The final orders of the court reflected its determinations and provided a resolution to the disputes between the parties.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.