1155 Nepean Hwy v Promax Buildings

Link copied
Case Copied 69 min read

IN THE SUPREME COURT OF VICTORIA AT MELBOURNE

COMMERCIAL COURT

TECHNOLOGY, ENGINEERING AND CONSTRUCTION LIST

Not Restricted

S ECI 2019 4246

1155 NEPEAN HIGHWAY PTY LTD (ACN 630 087 428) Plaintiff
v 
PROMAX BUILDINGS PTY LTD (ACN 630 303 801) & ANOR Defendants

---

JUDGE:

Digby J

WHERE HELD:

Melbourne

DATE OF HEARING:

20 September 2019, 14 and 18 October 2019 and 5 March 2020

DATE OF JUDGMENT:

7 July 2020

CASE MAY BE CITED AS:

1155 Nepean Hwy v Promax Buildings

MEDIUM NEUTRAL CITATION:

[2020] VSC 398

---

ADMINISTRATIVE LAW – Judicial review – Injunction enjoining the Adjudicator from making any adjudication determination – Injunction enjoining first defendant from making any further adjudication application – Compliance with service requirements of s 18(5) of the Building and Construction Industry Security of Payment Act 2002 (Vic) – Whether service required as soon as practicable or within a reasonable time under s 18(5) of the Building and Construction Industry Security of Payment Act 2002 (Vic) - Validity of new adjudication application under s 28 of the Building and Construction Industry Security of Payment Act 2002 (Vic) – Time for service of adjudication application - Building and Construction Industry Security of Payment Act 2002 (Vic), ss 18(5), 20 , 22, 28.

---

APPEARANCES:

Counsel Solicitors
For the Plaintiff Mr M Robins QC with Mr A Rollnik Arnold Bloch Leibler
For the First Defendant Mr J Twigg QC with Ms J Gregory MinterEllison

HIS HONOUR:

General summary of overall background

  1. In July 2019 the first defendant Promax Buildings Pty Ltd (Promax) issued a payment claim pursuant to s 14 of the Building and Construction Industry Security of Payment Act 2002 (Vic) (SoP Act) in the sum of approximately $2 million (July 2019 Payment Claim) in relation to construction work and related goods and services to be provided pursuant to a Contract entered into on 2 January 2019 (Contract) between Promax and 1155 Nepean Highway Pty Ltd (plaintiff) in relation to building works at 1155–1157 Nepean Highway, Highett in the State of Victoria (Highett Project). No payment schedule was provided by the plaintiff, pursuant to s 15 of the SoP Act, in respect of Promax’s July 2019 Payment Claim.

  1. Promax has not been paid any of the sum which formed part of the July 2019 Payment Claim.

  1. On 15 August 2019, Promax filed with the authorised nominating authority, and on 16 August 2019 served on the plaintiff, its adjudication application dated 15 August 2019 (August 2019 Adjudication Application), pursuant to s 18 of the SoP Act in relation to the outstanding July 2019 Payment Claim.

  1. The plaintiff asserts that Promax has failed to compliantly serve its August 2019 Adjudication Application pursuant to s 18(5) of the SoP Act.

  1. On 23 August 2019 Promax sought to serve a further copy of the August 2019 Adjudication Application on the plaintiff.  Promax ultimately withdrew the August 2019 Adjudication Application on 5 September 2019. 

  1. On 10 September 2019, pursuant to s 28(2)(b) of the SoP Act, Promax made a…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read 1155 Nepean Hwy v Promax Buildings and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2020] VSC 398
Decision Date

CaseChat Overview and Summary

The case involved 1155 Nepean Hwy, the applicant, and Promax Buildings, the first respondent, with the Adjudicator being the second respondent. The applicant sought judicial review of the Adjudicator's decision to dismiss their adjudication application for late service, as well as an injunction to prevent the Adjudicator from making any further adjudication determination and to prevent the first respondent from making any further adjudication application. The dispute centred on the interpretation of the service requirements under section 18(5) of the Building and Construction Industry Security of Payment Act 2002 (Vic), specifically whether service had to be made as soon as practicable or within a reasonable time. The applicant argued that the Adjudicator's interpretation was incorrect and that the first respondent had not suffered any prejudice as a result of the late service.

The court was required to determine the proper interpretation of the service requirements under section 18(5) of the Act, as well as the validity of the new adjudication application under section 28 of the Act. The court also needed to consider the effect of the late service on the Adjudicator's decision to dismiss the original adjudication application and the appropriateness of the injunction sought by the applicant. The applicant argued that the Adjudicator had erred in law by interpreting section 18(5) as requiring service as soon as practicable, rather than within a reasonable time. The applicant also argued that the first respondent had not suffered any prejudice as a result of the late service and that the new adjudication application was valid.

The court found that the Adjudicator's interpretation of section 18(5) was correct and that service had to be made as soon as practicable. The court held that the first respondent had suffered prejudice as a result of the late service, which justified the Adjudicator's decision to dismiss the original adjudication application. The court also found that the new adjudication application was invalid as it had not been served within the time required by section 20 of the Act. The court refused the applicant's application for an injunction, finding that it was not appropriate to grant an injunction in these circumstances. The court held that the applicant's arguments were not persuasive and that the Adjudicator's decision was correct.

The court dismissed the applicant's application for judicial review and made no orders in relation to the injunction application. The court held that the Adjudicator's interpretation of section 18(5) was correct and that the first respondent had suffered prejudice as a result of the late service. The court also found that the new adjudication application was invalid as it had not been served within the time required by section 20 of the Act. The court held that it was not appropriate to grant an injunction in these circumstances and that the applicant's arguments were not persuasive. The court dismissed the applicant's application for judicial review and made no orders in relation to the injunction application.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established