Supreme Court
New South Wales
Medium Neutral Citation: Trinco (NSW) Pty Ltd v Alpha A Group Pty Ltd [2018] NSWSC 239 Hearing dates: 21/02/2018 Date of orders: 06 March 2018 Decision date: 06 March 2018 Jurisdiction: Equity - Technology and Construction List Before: McDougall J Decision: Adjudication determination declared void and quashed. Ancillary orders made.
Catchwords: BUILDING AND CONSTRUCTION – Building and Construction Security of Payment Act 1999 (NSW) – whether adjudication determination valid – whether payment claim made on or from a reference date – where subcontract was terminated – where subcontract did not provide for reference dates after termination – whether work was completed under the subcontract or under a separate and later subcontract – whether a payment claim comprising work under two construction contracts is valid – adjudication determination quashed Legislation Cited: Building and Construction Industry Security of Payment Act 1999 (NSW)
Building and Construction Industry Payments Act 2004 (Qld)
Uniform Civil Procedure Rules 2005 (NSW)Cases Cited: Brodyn Pty Ltd v Davenport (2004) 61 NSWLR 421
Chase Oyster Bar Pty Ltd v Hamo Industries Pty Ltd (2010) 78 NSWLR 393
Class Electrical Services v Go Electrical [2013] NSWSC 363
Coordinated Construction Co Pty Ltd v JM Hargreaves (NSW) Pty Ltd (2005) 63 NSWLR 385
Matrix Projects (Qld) Pty Ltd v Luscombe [2013] QSC 4
Rail Corporation of NSW v Nebax Constructions [2012] NSWSC 6
Southern Han Breakfast Point Pty Ltd (In Liq) v Lewence Construction Pty Ltd (2016) 91 ALJR 233Category: Principal judgment Parties: Trinco (NSW) Pty Ltd (Plaintiff)
Alpha A Group Pty Ltd (First Defendant)
Callum Campbell (Second Defendant)Representation: Counsel:
Solicitors:
S Robertson (Plaintiff)
T O Bland (First Defendant)
No appearance (Second Defendant, submitting)
Colin Biggers & Paisley Pty Ltd (Plaintiff)
Solon Lawyers (First Defendant)
File Number(s): 2017/351836
Judgment
-
HIS HONOUR: The plaintiff (Trinco) and the first defendant (Alpha) are in dispute as to a determination made by the second defendant (the adjudicator) pursuant to the Building and Construction Industry Security of Payment Act1999 (NSW) (the Security of Payment Act). The central issue is whether the underlying payment claim was made on or from a reference date under a construction contract (see ss 8(1), 13(1) of that Act.) The answer to that question requires identification of the construction contract in question.
Factual background
-
On 6 March 2017, Trinco as head contractor and Alpha as subcontractor made a written subcontract. Under that subcontract, Alpha undertook to perform tiling and silicone work for a project at Mascot. The subcontract was a construction contract for the purposes of the Security of Payment Act. The subcontract provided by Item 37 of the particulars (contained in Part A of the Annexure) that progress claims should be made on the 25th day of each month (the provision for a final payment claim may be ignored).
-
On 6 June 2017, after Alpha had carried out some work pursuant to the subcontract, a Mr Saleh of Trinco sent an email to Mr Alizada of Alpha. That email referred to earlier…
Keep reading for free
Create a free CaseChat account to read Trinco (NSW) Pty Ltd v Alpha A Group Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2018] NSWSC 239
- Decision Date
CaseChat Overview and Summary
The court found that the adjudication determination was invalid because it was based on a payment claim that did not specify the relevant reference date, as required by the Act. The determination also failed to address the issue of whether the work in question was completed under the original subcontract or under a later subcontract. The court concluded that the payment claim was not made on or from a reference date as required by the Act, and therefore the adjudication determination was not valid.
The Supreme Court of New South Wales quashed the adjudication determination, holding that the adjudicator had not properly considered the applicability of the reference date to the payment claim and had not addressed the issue of whether the work was completed under the original subcontract or a subsequent subcontract. The court's decision underscored the importance of compliance with the statutory requirements for making a valid payment claim and the need for adjudicators to properly address all relevant issues in their determinations.
The final orders included the quashing of the adjudication determination, and the case was remitted back to the original adjudicator for reconsideration in light of the court's findings.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.