Trinco (NSW) Pty Ltd v Alpha A Group Pty Ltd

Link copied
Case Copied 24 min read

Supreme Court


New South Wales

Medium Neutral Citation: Trinco (NSW) Pty Ltd v Alpha A Group Pty Ltd [2018] NSWSC 239
Hearing dates: 21/02/2018
Date of orders: 06 March 2018
Decision date: 06 March 2018
Jurisdiction:Equity - Technology and Construction List
Before: McDougall J
Decision:

Adjudication determination declared void and quashed. Ancillary orders made.

Catchwords: BUILDING AND CONSTRUCTION – Building and Construction Security of Payment Act 1999 (NSW) – whether adjudication determination valid – whether payment claim made on or from a reference date – where subcontract was terminated – where subcontract did not provide for reference dates after termination – whether work was completed under the subcontract or under a separate and later subcontract – whether a payment claim comprising work under two construction contracts is valid – adjudication determination quashed
Legislation Cited: Building and Construction Industry Security of Payment Act 1999 (NSW)
Building and Construction Industry Payments Act 2004 (Qld)
Uniform Civil Procedure Rules 2005 (NSW)
Cases Cited: Brodyn Pty Ltd v Davenport (2004) 61 NSWLR 421
Chase Oyster Bar Pty Ltd v Hamo Industries Pty Ltd (2010) 78 NSWLR 393
Class Electrical Services v Go Electrical [2013] NSWSC 363
Coordinated Construction Co Pty Ltd v JM Hargreaves (NSW) Pty Ltd (2005) 63 NSWLR 385
Matrix Projects (Qld) Pty Ltd v Luscombe [2013] QSC 4
Rail Corporation of NSW v Nebax Constructions [2012] NSWSC 6
Southern Han Breakfast Point Pty Ltd (In Liq) v Lewence Construction Pty Ltd (2016) 91 ALJR 233
Category:Principal judgment
Parties: Trinco (NSW) Pty Ltd (Plaintiff)
Alpha A Group Pty Ltd (First Defendant)
Callum Campbell (Second Defendant)
Representation:

Counsel:
S Robertson (Plaintiff)
T O Bland (First Defendant)
No appearance (Second Defendant, submitting)

  Solicitors:
Colin Biggers & Paisley Pty Ltd (Plaintiff)
Solon Lawyers (First Defendant)
File Number(s): 2017/351836

Judgment

  1. HIS HONOUR:   The plaintiff (Trinco) and the first defendant (Alpha) are in dispute as to a determination made by the second defendant (the adjudicator) pursuant to the Building and Construction Industry Security of Payment Act1999 (NSW) (the Security of Payment Act). The central issue is whether the underlying payment claim was made on or from a reference date under a construction contract (see ss 8(1), 13(1) of that Act.) The answer to that question requires identification of the construction contract in question.

Factual background

  1. On 6 March 2017, Trinco as head contractor and Alpha as subcontractor made a written subcontract. Under that subcontract, Alpha undertook to perform tiling and silicone work for a project at Mascot. The subcontract was a construction contract for the purposes of the Security of Payment Act. The subcontract provided by Item 37 of the particulars (contained in Part A of the Annexure) that progress claims should be made on the 25th day of each month (the provision for a final payment claim may be ignored).

  2. On 6 June 2017, after Alpha had carried out some work pursuant to the subcontract, a Mr Saleh of Trinco sent an email to Mr Alizada of Alpha. That email referred to earlier…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Trinco (NSW) Pty Ltd v Alpha A Group Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2018] NSWSC 239
Decision Date

CaseChat Overview and Summary

The case of Trinco (NSW) Pty Ltd v Alpha A Group Pty Ltd involved a dispute between a subcontractor and a main contractor regarding the validity of an adjudication determination made under the Building and Construction Security of Payment Act 1999 (NSW). The primary issue was whether the adjudication determination was valid and if the payment claim was made on or from a reference date. This arose from a situation where a subcontract was terminated, and the subcontract did not provide for reference dates after termination. The court had to consider whether the work was completed under the original subcontract or under a separate and later subcontract, and whether a payment claim comprising work under two construction contracts was valid.

The court found that the adjudication determination was invalid because it was based on a payment claim that did not specify the relevant reference date, as required by the Act. The determination also failed to address the issue of whether the work in question was completed under the original subcontract or under a later subcontract. The court concluded that the payment claim was not made on or from a reference date as required by the Act, and therefore the adjudication determination was not valid.

The Supreme Court of New South Wales quashed the adjudication determination, holding that the adjudicator had not properly considered the applicability of the reference date to the payment claim and had not addressed the issue of whether the work was completed under the original subcontract or a subsequent subcontract. The court's decision underscored the importance of compliance with the statutory requirements for making a valid payment claim and the need for adjudicators to properly address all relevant issues in their determinations.

The final orders included the quashing of the adjudication determination, and the case was remitted back to the original adjudicator for reconsideration in light of the court's findings.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.