| IN THE SUPREME COURT OF VICTORIA | Not Restricted |
AT MELBOURNE
COMMON LAW AND EQUITY DIVISION
TECHNOLOGY ENGINEERING AND CONSTRUCTION LIST
S CI 2014 00726
| BRANLIN PTY LTD (ACN 108 591 304) | Plaintiff |
| v | |
| TONY TOTARO (T/A EZY DOZE IT) (ABN 78 822 145 580) | First Defendant |
| and | |
| MARIA TOTARO T/A EZY DOZE IT) (ABN 78 822 145 580) | Second Defendant |
| and | |
| NAVID KING | Third Defendant |
| and | |
| ADJUDICATE TODAY PTY LTD (ABN 39 109 605 021) | Fourth Defendant |
---
JUDGE: | VICKERY J |
WHERE HELD: | MELBOURNE |
DATE OF HEARING: | 5 AUGUST 2014 |
DATE OF JUDGMENT: | 7 OCTOBER 2014 |
CASE MAY BE CITED AS: | BRANLIN PTY LTD v TOTARO |
MEDIUM NEUTRAL CITATION: | [2014] VSC 492 |
---
BUILDING CONTRACTS - Building and Construction Industry Security of Payment Act 2002 (Vic) – Whether incorrect inclusion of non-claimable variations - Whether the construction contract contained a method for resolving disputes within the meaning of s 10A(3)(d)(ii) of the Act – Whether payment claim invalid because not served within time or in accordance with the construction contract and s 14(5) of the Act – Whether the construction contract provided a mechanism for determining the reference date for a final payment claim and when the works achieved practical completion - Whether the claimant was required to serve a further s 18(2) notice before withdrawing the first Adjudication Application and making a fresh application under s 28 of the Act – Whether breach of the rules of natural justice - Whether the adjudicator was required to take into account the respondent’s submissions – Application of s 21(2A) of the Act.
ADMINISTRATIVE LAW – Judicial review - Decision of adjudicator appointed under the Building and Construction Industry Security of Payment Act 2002 (Vic) – Whether certiorari should be granted to quash the decision.
---
APPEARANCES: | Counsel | Solicitors |
| For the Plaintiff | Mr N A Andreou | Hutchinson Legal |
| For the First and Second Defendants | Mr A R Morrison | Rigby Cooke |
| For the Third and Fourth Defendants | No Appearance |
HIS HONOUR:
This proceeding arises out of a payment claim purportedly made under the Building and Construction Industry Security of Payment Act 2002 (the ‘Act’).
On 4 October 2013 a construction contract (the ‘Construction Contract’) was entered into between the Plaintiff, Branlin Pty Ltd (‘Branlin’) (which was the Respondent under the relevant Payment Claim) and the First Defendant, Tony Totaro trading as Ezy Doze It (‘Mr Totaro’) (who was the Claimant under the relevant Payment Claim). Pursuant to the Construction Contract Branlin engaged Mr Totaro to perform preliminary site works, earthworks, water infrastructure works and concrete road pavement (the ‘Works’) at a 9 lot development site located on Broadgully Road and Glen View Close, Diamond Creek, Victoria (the ‘Project’). The contract price for the work, excluding GST, was $235,000.
The Works commenced on 9 October 2012.
Mr Totaro purported to serve a payment claim under the Act dated 7 November 2013 (the ‘Payment Claim’) upon Branlin. The Payment Claim claimed the sum of $124,240.93 (including GST) under the Act.
Branlin did not pay any…
Continue reading Branlin Pty Ltd v Totaro
Sign in free to access the full text
- AGLC
- Branlin Pty Ltd v Totaro [2014] VSC 492
- Case
- [2014] VSC 492
- Decision Date
CaseChat Overview and Summary
The court found that Branlin's payment claim was invalid due to the inclusion of non-claimable variations and the absence of a dispute resolution method in the contract. Furthermore, the payment claim was not served in accordance with the contract and the Act, rendering it invalid. The contract did not provide a mechanism for determining the reference date for a final payment claim or the completion of works. Branlin was not required to serve a further notice before withdrawing its first adjudication application and making a new one. The adjudicator's process did not breach natural justice, and there was no requirement for the adjudicator to consider the respondent's submissions. The court concluded that the adjudicator's decision was not subject to quashing on the grounds of judicial review.
The final orders of the court included dismissing Branlin's application for adjudication and affirming Totaro's cross-application for an order quashing the adjudicator's decision. The court also ordered that Totaro recover its costs of the application and cross-application.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.