| IN THE SUPREME COURT OF VICTORIA | Not Restricted | |
AT MELBOURNE
PRACTICE COURT
No. 9599 of 2006
| SIEMENS LIMITED | Plaintiff |
| v | |
| VAUGHAN CONSTRUCTIONS PTY LTD | Defendant |
---
JUDGE: | Kaye J | |
WHERE HELD: | Melbourne | |
DATE OF HEARING: | 10 November 2006 (Further written submissions received 17 and 20 November 2006) | |
DATE OF JUDGMENT: | 29 November 2006 | |
CASE MAY BE CITED AS: | Siemens Ltd v Vaughan Constructions Pty Ltd | |
MEDIUM NEUTRAL CITATION: | [2006] VSC 452 | |
---
BUILDING CONTRACTS – Claim for injunction to restrain enforcement of guarantee given under s.25(1)(b) of the Building and Construction Industry Security of Payment Act 2002 – Whether notice of dispute served on defendant commenced “other dispute resolution proceedings” under s.25(2) – Effect of notice being expressed to be “without prejudice” to rights under the contract and at law.
---
APPEARANCES: | Counsel | Solicitors |
| For the Plaintiff | Mr T.J. Margetts | Baker & McKenzie |
| For the Defendant | Mr M.A. Robins | Nathan Kuperholz |
---
TABLE OF CONTENTS
The Building and Construction Industry Security Payment Act 2002....................................... 2
Clause 25 of the Contract: Dispute Resolution........................................................................... 4
Submissions........................................................................................................................................ 5
The Notice of Dispute....................................................................................................................... 7
“Other Dispute Resolution Proceedings” – s.25(2) of the Act................................................... 8
Conclusion......................................................................................................................................... 14
HIS HONOUR:
In these proceedings the plaintiff claims an injunction to restrain the defendant from enforcing a bank guarantee for the sum of $271,813.41 issued in favour of the defendant by Citigroup on behalf of the plaintiff. The matter came before me in the Practice Court on an application by the plaintiff for an interlocutory injunction. However the factual issues in the case are not in dispute. The parties therefore agreed that the matter should proceed before me by way of the trial of the action. For that purpose I heard oral submissions, and gave the parties leave to file supplementary written submissions, which they have now done.
By an agreement in writing dated 30 June 2004 the defendant entered into a sub‑contract with the plaintiff to perform earthworks and main civil works in respect of the construction of a gas turbine power station at Laverton North. The contract price was approximately $11 million. On 30 August 2006 the defendant made progress claim No. 20 for payment of a sum of $403,820.21. The plaintiff responded by letter dated 19 September 2006 disputing that claim and stating that the scheduled amount which it proposed to pay was $94,326.51. Accordingly the defendant referred the dispute to adjudication pursuant to the provisions of the Building and Construction Industry Security of Payment Act 2002 (Victoria) (“the Act”). On 24 October 2006 the adjudicator, Mr S. Gunn, released his determination that the plaintiff was liable to pay the defendant $271,813.41 in respect to the progress claim No. 20, and that the date for payment of that sum was Tuesday, 31 October 2006.
On 31 October 2006 the plaintiff sent a letter to the defendant, copied to the defendant’s solicitors, enclosing a Notice of Dispute and a bank guarantee for the adjudicated amount of $271,813.41. The letter stated:
“Pursuant to clause 25 of…
Continue reading Siemens Ltd v Vaughan Constructions Pty Ltd
Sign in free to access the full text
- AGLC
- Siemens Ltd v Vaughan Constructions Pty Ltd [2006] VSC 452
- Case
- [2006] VSC 452
- Decision Date
CaseChat Overview and Summary
The court examined the language of the notice and the implications of it being labelled "without prejudice." The term "without prejudice" typically indicates that the communication should not be used as evidence of an admission of liability and is often used in negotiations to encourage openness without fear of legal repercussions. The court considered whether this characterisation affected the notice's status under the Act, particularly in the context of initiating dispute resolution. Ultimately, the court held that the "without prejudice" label did not preclude the notice from serving as the commencement of dispute resolution proceedings. The court reasoned that the statutory framework of the Act was designed to facilitate timely and effective dispute resolution, and the "without prejudice" nature of the notice did not alter its substantive effect of initiating the dispute resolution process.
As a result, the court determined that Siemens' claim for an injunction was not justified. The notice served was deemed to have initiated dispute resolution proceedings, and thus Siemens' guarantee could not be enforced. The court did not grant the injunction Siemens sought, allowing Vaughan to proceed with enforcing the guarantee as provided for in the contract. The final orders reflect this decision, dismissing Siemens' application for an injunction and affirming the enforceability of the guarantee.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.