| IN THE SUPREME COURT OF VICTORIA | Not Restricted |
AT MELBOURNE
COMMERCIAL COURT
TECHNOLOGY, ENGINEERING AND CONSTRUCTION LIST
S ECI 2020 01564
| CITI-CON (VIC) PTY LTD (ACN 143 889 678) | Plaintiff |
| v | |
| TROJAN BUILT PTY LTD (ACN 609 321 708) and ROBERT SUNDERCOMBE (IN HIS CAPACITY AS ADJUDICATOR APPOINTED UNDER SECTION 20(1) OF THE BUILDING AND CONSTRUCTION INDUSTRY SECURITY OF PAYMENT ACT 2002 (VIC) | First Defendant Second Defendant |
---
JUDGE: | Stynes J |
WHERE HELD: | Melbourne |
DATE OF HEARING: | 18 August 2020 |
DATE OF JUDGMENT: | 1 September 2020 |
CASE MAY BE CITED AS: | Citi-Con (Vic) Pty Ltd v Trojan Built Pty Ltd |
MEDIUM NEUTRAL CITATION: | [2020] VSC 557 |
---
BUILDING CONTRACTS – Whether Adjudicator erred in determining the reference date applicable to the Payment Claim – Whether Payment Claim was served within prescribed time under the Act – Whether Payment Claim is a final payment claim – Whether Adjudicator failed to perform statutory function under Act – Building and Construction Industry Security of Payment Act 2002 (Vic) ss 9, 10B, 13, 14, 22, 23 and 48 – Southern Han Breakfast Point Pty Ltd (in liq) v Lewence Construction Pty Ltd (2016) 260 CLR 340, applied – Shape Australia Pty Ltd v The Nuance Group Pty Ltd [2018] VSC 808, applied – Commercial & Industrial Construction Group Pty Ltd v King Construction Group Pty Ltd [2015] VSC 426, applied – Ian Street Developer Pty Ltd v Arrow International Pty Ltd (2018) 54 VR 721, applied – Protectavale Pty Ltd v K2K Pty Ltd [2008] FCA 1248, applied – Hickory Developments Pty Ltd v Schiavello (Vic) Pty Ltd (2009) 26 VR 112, applied – Cat Protection Society v Arvio [2018] VSC 757, applied – Maggbury Pty Ltd v Hafele Australia Pty Ltd (2001) 210 CLR 181, applied – Wilson v Anderson (2002) 213 CLR 401, applied – Mackie Pty Ltd v Counahan [2013] VSC 694, applied – Levi Pty Ltd v Z&H Building Development Pty Ltd [2019] VSC 633, applied – SSC Plenty Road Pty Ltd v Construction Engineering (Aust) Pty Ltd [2015] VSC 631, applied.
---
APPEARANCES: | Counsel | Solicitors |
| For the Plaintiff | Ms Christie Jones | EIDELWEISZ Lawyers |
| For the Defendant | Mr Nicholas Phillpott | Oldham Construction Lawyers |
HER HONOUR:
Introduction
On 30 November 2018 the plaintiff as builder engaged the first defendant as subcontractor to supply and install a flooring system at the plaintiff’s development at 2 The Crossing Caroline Springs for the sum of $1,179,941.35 (exclusive of GST) (Subcontract).
This proceeding arises under the Building and Construction Industry Security of Payment Act 2002 (Vic) (the SOP Act) in relation to an adjudication determination made by the second defendant (the Adjudicator)[1] on 6 March 2020 (the Adjudication Determination) in relation to a payment claim issued by the first defendant dated 3 February 2020 (the Payment Claim) under the Subcontract.
[1]By letter dated 3 April 2020, the second defendant informed the Court that he did not intend…
Keep reading for free
Create a free CaseChat account to read Citi-Con (Vic) Pty Ltd v Trojan Built Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2020] VSC 557
- Decision Date
CaseChat Overview and Summary
The court considered the relevant provisions of the Building and Construction Industry Security of Payment Act 2002 (Vic) and the authorities cited by both parties. The court held that the adjudicator had erred in determining the reference date applicable to the payment claim. The court found that the reference date should have been the date of the payment claim, rather than the date of the progress claim. The court also held that the payment claim was not a final payment claim, as it did not include all the amounts that the respondent was entitled to claim under the contract. The court further found that the adjudicator had failed to perform his statutory function under the Act, as he had not considered all the relevant evidence and had made errors in his determination. The court therefore set aside the adjudicator's decision and remitted the matter back to the adjudicator for reassessment.
The court made orders setting aside the adjudicator's decision and remitting the matter back to the adjudicator for reassessment. The court also made orders for costs, awarding costs to the respondent in relation to the proceeding in the Supreme Court and to the applicant in relation to the adjudication. The court noted that the parties were free to agree on a new adjudicator or to proceed with the existing adjudicator, as appropriate.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.