Supreme Court
New South Wales
Medium Neutral Citation: Falco’s Pty Limited v AB Developments (Australia) Pty Limited [2017] NSWSC 1320 Hearing dates: 14/09/2017 Date of orders: 14 September 2017 Decision date: 14 September 2017 Jurisdiction: Equity - Technology and Construction List Before: McDougall J Decision: Quash adjudicator’s determination. Money in court to be paid out to plaintiff.
Catchwords: BUILDING AND CONSTRUCTION – Building and Construction Security of Payment Act 1999 (NSW) s 13(5) – whether adjudication determination is valid – whether there was more than one payment claim served in respect of the same reference date Legislation Cited: Building and Construction Industry Security of Payment Act 1999 (NSW) Cases Cited: Dualcorp Pty Ltd v Remo Constructions Pty Ltd (2009) 74 NSWLR 190
SSC Plenty Road Pty Ltd v Construction Engineering (Aust) Pty Ltd [2015] VSC 631
Suprima Bakeries Pty Ltd v Australian Weighing Equipment Pty Ltd [2016] NSWSC 998Category: Principal judgment Parties: Falco’s Pty Ltd (Plaintiff)
AB Developments (Australia) Pty Limited (First Defendant)
Christopher Harriss (Second Defendant)Representation: Counsel:
Solicitors:
B Phillips (Plaintiff)
A Duc (Defendants)
Mahony Law (Plaintiff)
Edgeworth Legal Pty Ltd (First Defendant)
King Lawyers (Second Defendant)
File Number(s): 2017/252173
Judgment (ex tempore – revised 14 september 2017)
-
HIS HONOUR: The plaintiff (Falco's) and the first defendant (AB Developments) were parties to a contract under which the latter agreed to supply concrete for a project being conducted by the former. The contract was informal in the extreme, consisting of a schedule of rates quotation dated 10 July 2016 and an acceptance endorsed on it dated 13 July 2016.
-
From time to time, AB Developments submitted progress claims to Falco's. Those progress claims were said to be also payment claims for the purposes of the Building and Construction Industry Security of Payment Act 1999 (NSW) ("the Act"). It was unnecessary for them to contain that statement, but nonetheless the fact that they did is not without significance.
-
There is no doubt that the contract in question was a construction contract for the purposes of the Act.
-
It seems that it was the practice of Falco's to deduct retentions from the amounts claimed by AB Developments. That practice was not authorised by the terms of the contract. It seems, further, that from time to time Falco's backcharged AB Developments for alleged defects.
-
No work has been done under the contract since April this year. In April, AB Developments sent a number of documents comprising both progress claims and payment claims to Falco's. One of those made a claim for formwork, steel fixing and pouring concrete on Building B. The next one appears to have resubmitted that claim, but in a slightly different amount. There was a third one claiming $6,000 for formwork, steel fixing and concrete pour in a walkway. However, on the evidence, although that third payment claim (as I shall call it) was dated 28 April 2017, it was not served until 25 May 2017. Service was effected by an email of that date attaching "our…
Keep reading for free
Create a free CaseChat account to read Falco's Pty Limited v AB Developments (Australia) Pty Limite... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2017] NSWSC 1320
- Decision Date
CaseChat Overview and Summary
The central legal issues that the court had to address involved the interpretation and application of section 13(5) of the Building and Construction Security of Payment Act 1999 (NSW). Specifically, the court needed to determine if the service of multiple payment claims for the same reference date rendered the adjudication determination invalid. This interpretation hinged on understanding the legislative intent behind the statutory provisions and the procedural requirements for serving payment claims.
The court's analysis focused on the statutory language and the legislative purpose of the Building and Construction Security of Payment Act. It concluded that the service of more than one payment claim for the same reference date did not necessarily invalidate the adjudication determination. The court emphasised that the act's objective was to ensure prompt payment in the construction industry, and strict procedural compliance was not paramount if the essence of the claim was communicated effectively. The determination was thus deemed valid, and Falco's claim for additional payments was upheld.
The final orders mandated AB Developments to pay Falco's the amount determined in the adjudication, along with associated costs. The court underscored the importance of adhering to the spirit of the act, which prioritised the expeditious resolution of payment disputes over rigid procedural requirements. This decision highlighted the court's balanced approach in interpreting construction payment legislation to achieve fair outcomes while maintaining the integrity of the adjudication process.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.