Supreme Court
New South Wales
Medium Neutral Citation: Suprima Bakeries Pty Ltd v Australian Weighing Equipment Pty Ltd [2016] NSWSC 998 Hearing dates: 11 July 2016 Date of orders: 21 July 2016 Decision date: 21 July 2016 Jurisdiction: Equity - Technology and Construction List Before: McDougall J Decision: Restrain first defendant from enforcing adjudication determination.
Declare determination void.Catchwords: BUILDING AND CONSTRUCTION – Building and Construction Industry Security of Payment Act 1999 – adjudication determination – whether contracts were construction contracts within the meaning of the Act – whether Adjudicator denied natural justice to plaintiff – failure to deal with claim of defective work Legislation Cited: Building and Construction Industry Security of Payment Act 1999 (NSW)
Building and Construction Industry Security of Payment Act 2002 (Vic)Cases Cited: Class Electrical Services v Go Electrical [2013] NSWSC 363
Clyde Bergemann v Varley Power [2011] NSWSC 1039
Musico v Davenport [2003] NSWSC 977
SSC Plenty Road Pty Ltd v Construction Engineering (Aust) Pty Ltd [2015] VSC 631Category: Principal judgment Parties: Suprima Bakeries Pty Ltd (Plaintiff)
Australian Weighing Equipment Pty Ltd (First Defendant)
Kenneth Spain (Second Defendant)Representation: Counsel:
Solicitors:
D S Weinberger (Plaintiff)
V Culkoff (First Defendant)
Second defendant submitted save as to costs.
Chedid Storey Legal (Plaintiff)
McInnes Wilson Lawyers (First Defendant)
Submitting appearance (Second Defendant)
File Number(s): 2015/364338
Judgment
-
HIS HONOUR: The Plaintiff (Suprima) manufactures frozen dough in premises at Minto. In 2013 and 2014, as part of a substantial upgrade to its Minto premises, Suprima agreed with the first defendant (AWE) for the latter to supply plant and equipment to be used in the manufacture of frozen dough. There is a dispute as to whether the parties’ agreement was embodied in one, or more than one, contract.
-
Suprima says that the plant and equipment supplied and installed by AWE is essentially useless. AWE disputes this.
-
AWE took the view that the contract (on its view, there was only contract) between it and Suprima was a construction contract for the purposes of the Building and Construction Industry Security of Payment Act1999 (NSW) (the Act). It served a payment claim on Suprima. Suprima served a payment schedule asserting, among other things, that there was no construction contract, and that the plant and equipment supplied by AWE was worthless.
-
The dispute was referred to the second defendant (the Adjudicator) for adjudication. He concluded that there was a construction contract. He determined that AWE was entitled to be paid $535,000.00 of the claimed amount of $662,000.00 (each rounded up to the nearest $1000.00).
The real issues for decision
-
Suprima challenges the Adjudicator’s determination. The essential issues that it raises are:
was there one contract between the parties (as AWE contended and the Adjudicator found), or were there several?
If there were several contracts, was each of them a construction contract for the purposes of the Act?
Did the Adjudicator carry out his statutory function of valuing the construction work performed by AWE under any construction contract? (I realise that the legislation…
Keep reading for free
Create a free CaseChat account to read Suprima Bakeries Pty Ltd v Australian Weighing Equipment Pty... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2016] NSWSC 998
- Decision Date
CaseChat Overview and Summary
The court had to determine if the contracts in question qualified as construction contracts under the Act, and if the Adjudicator had acted fairly by not considering the argument of defective work. The appellant argued that the Adjudicator's failure to address the defective work claim amounted to a denial of natural justice. Conversely, the respondent maintained that the Adjudicator's determination was valid and that the claim of defective work was not relevant to the adjudication process under the Act.
The court found that the contracts did qualify as construction contracts under the Act, which meant the Adjudicator's determination was binding. However, the court held that the Adjudicator's omission to address the defective work claim was indeed a denial of natural justice. This error rendered the adjudication determination invalid, leading to the conclusion that the Adjudicator had failed to observe fundamental principles of fairness. Consequently, the Supreme Court of New South Wales set aside the adjudication determination, finding in favour of the appellant.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi