Building and Construction Industry Security of Payment Amendment Act 2002 (NSW)
An Act to amend the Building and Construction Industry Security of Payment Act 1999 to make further provision with respect to payments for construction work and for related goods and services under construction contracts; to amend the Contractors Debts Act 1997; and for other purposes.
This Act is the Building and Construction Industry Security of Payment Amendment Act 2002.
This Act commences on a day or days to be appointed by proclamation.
The Building and Construction Industry Security of Payment Act 1999 is amended as set out in Schedule 1.
The Contractors Debts Act 1997 is amended as set out in Schedule 2.
(Section 3)
Omit section 3 (1). Insert instead:
The object of this Act is to ensure that any person who undertakes to carry out construction work (or who undertakes to supply related goods and services) under a construction contract is entitled to receive, and is able to recover, progress payments in relation to the carrying out of that work and the supplying of those goods and services.
Omit “in circumstances where the relevant construction contract fails to do so”.
Insert instead “regardless of whether the relevant construction contract makes provision for progress payments”.
Omit “setting aside of money as security for”.
Omit the subsection. Insert instead:
It is intended that this Act does not limit:
(a) any other entitlement that a claimant may have under a construction contract, or
(b) any other remedy that a claimant may have for recovering any such other entitlement.
Insert in alphabetical order:
Omit the definitions.
Omit the definition. Insert instead:
(a) the final payment for construction work carried out (or for related goods and services supplied) under a construction contract, or
(b) a single or one-off payment for carrying out construction work (or for supplying related goods and services) under a construction contract, or
(c) a payment that is based on an event or date (known in the building and construction industry as a “milestone payment”).
Omit “any building or structure” wherever occurring from section 5 (1) (c), (e) (iv) and (f).
Insert instead “any building, structure or works”.
Omit “buildings and structures”.
Insert instead “buildings, structures and works”.
Insert after section 6 (2):
In this Act, a reference to related goods and services includes a reference to related goods or services.
Omit “under this Act, calculated by reference to that date” from section 8 (1).
Omit the subsection. Insert instead:
In this section,
(a) a date determined by or in accordance with the terms of the contract as the date on which a claim for a progress payment may be made in relation to work carried out or undertaken to be carried out (or related goods and services supplied or undertaken to be supplied) under the contract, or
(b) if the contract makes no express provision with respect to the matter—the last day of the named month in which the construction work was first carried out (or the related goods and services were first supplied) under the contract and the last day of each subsequent named month.
Insert “or undertaken to be carried out” after “carried out” in section 9 (b).
Insert “or undertaken to be supplied” after “supplied”.
Insert “or undertaken to be carried out” after “carried out” in section 10 (1).
Insert “or undertaken to be supplied” after “supplied”.
Omit “2 weeks” from section 11 (b). Insert instead “10 business days”.
Insert at the end of section 11:
Interest is payable on the unpaid amount of a progress payment that has become due and payable at the rate:
(a) prescribed under the Supreme Court Act 1970 in respect of unpaid judgments of the Supreme Court, or
(b) specified under the construction contract,
whichever is the greater.
If a progress payment becomes due and payable, the claimant is entitled to exercise a lien in respect of the unpaid amount over any unfixed plant or materials supplied by the claimant for use in connection with the carrying out of construction work for the respondent.
Any lien or charge over the unfixed plant or materials existing before the date on which the progress payment becomes due and payable takes priority over a lien under subsection (3).
Subsection (3) does not confer on the claimant any right against a third party who is the owner of the unfixed plant or materials.
Omit “(or for related goods and services supplied)” from section 12 (1).
Insert instead “or undertaken to be carried out (or for related goods and services supplied or undertaken to be supplied)”.
Omit “(or for related goods and services supplied)” from the definition of
Insert instead “or undertaken to be carried out (or for related goods and services supplied or undertaken to be supplied)”.
Insert at the end of the definition:
, or
that otherwise makes the liability to pay money owing, or the due date for payment of money owing, contingent or dependent on the operation of another contract.
Omit section 13 (1). Insert instead:
A person referred to in section 8 (1) who is or who claims to be entitled to a progress payment (the
Omit the paragraph. Insert instead:
must indicate the amount of the progress payment that the claimant claims to be due (the
Insert after section 13 (2):
The claimed amount may include any amount:
(a) that the respondent is liable to pay the claimant under section 27 (2A), or
(b) that is held under the construction contract by the respondent and that the claimant claims is due for release.
A payment claim may be served only within:
(a) the period determined by or in accordance with the terms of the construction contract, or
(b) the period of 12 months after the construction work to which the claim relates was last carried out (or the related goods and services to which the claim relates were last supplied),
whichever is the later.
A claimant cannot serve more than one payment claim in respect of each reference date under the construction contract.
However, subsection (5) does not prevent the claimant from including in a payment claim an amount that has been the subject of a previous claim.
Omit section 15 (2) (a). Insert instead:
may:
(i) recover the unpaid portion of the claimed amount from the respondent, as a debt due to the claimant, in any court of competent jurisdiction, or
(ii) make an adjudication application under section 17 (1) (b) in relation to the payment claim, and
Omit the subsection. Insert instead:
If the claimant commences proceedings under subsection (2) (a) (i) to recover the unpaid portion of the claimed amount from the respondent as a debt:
(a) judgment in favour of the claimant is not to be given unless the court is satisfied of the existence of the circumstances referred to in subsection (1), and
(b) the respondent is not, in those proceedings, entitled:
(i) to bring any cross-claim against the claimant, or
(ii) to raise any defence in relation to matters arising under the construction contract.
Omit section 16 (2) (a). Insert instead:
may:
(i) recover the unpaid portion of the scheduled amount from the respondent, as a debt due to the claimant, in any court of competent jurisdiction, or
(ii) make an adjudication application under section 17 (1) (a) (ii) in relation to the payment claim, and
Omit the subsection. Insert instead:
If the claimant commences proceedings under subsection (2) (a) (i) to recover the unpaid portion of the scheduled amount from the respondent as a debt:
(a) judgment in favour of the claimant is not to be given unless the court is satisfied of the existence of the circumstances referred to in subsection (1), and
(b) the respondent is not, in those proceedings, entitled:
(i) to bring any cross-claim against the claimant, or
(ii) to raise any defence in relation to matters arising under the construction contract.
Omit the section. Insert instead:
A claimant may apply for adjudication of a payment claim (an
(a) the respondent provides a payment schedule under Division 1 but:
(i) the scheduled amount indicated in the payment schedule is less than the claimed amount indicated in the payment claim, or
(ii) the respondent fails to pay the whole or any part of the scheduled amount to the claimant by the due date for payment of the amount, or
(b) the respondent fails to provide a payment schedule to the claimant under Division 1 and fails to pay the whole or any part of the claimed amount by the due date for payment of the amount.
An adjudication application to which subsection (1) (b) applies cannot be made unless:
(a) the claimant has notified the respondent, within the period of 20 business days immediately following the due date for payment, of the claimant’s intention to apply for adjudication of the payment claim, and
(b) the respondent has been given an opportunity to provide a payment schedule to the claimant within 5 business days after receiving the claimant’s notice.
An adjudication application:
(a) must be in writing, and
(b) must be made to an authorised nominating authority chosen by the claimant, and
(c) in the case of an application under subsection (1) (a) (i)—must be made within 10 business days after the claimant receives the payment schedule, and
(d) in the case of an application under subsection (1) (a) (ii)—must be made within 20 business days after the due date for payment, and
(e) in the case of an application under subsection (1) (b)—must be made within 10 business days after the end of the 5-day period referred to in subsection (2) (b), and
(f) must identify the payment claim and the payment schedule (if any) to which it relates, and
(g) must be accompanied by such application fee (if any) as may be determined by the authorised nominating authority, and
(h) may contain such submissions relevant to the application as the claimant chooses to include.
The amount of any such application fee must not exceed the amount (if any) determined by the Minister.
A copy of an adjudication application must be served on the respondent concerned.
It is the duty of the authorised nominating authority to which an adjudication application is made to refer the application to an adjudicator (being a person who is eligible to be an adjudicator as referred to in section 18) as soon as practicable.
Omit section 19 (1). Insert instead:
If an authorised nominating authority refers an adjudication application to an adjudicator, the adjudicator may accept the adjudication application by causing notice of the acceptance to be served on the claimant and the respondent.
Omit “The” from section 20 (1).
Insert instead “Subject to subsection (2A), the”.
Insert after section 20 (2):
The respondent may lodge an adjudication response only if the respondent has provided a payment schedule to the claimant within the time specified in section 14 (4) or 17 (2) (b).
The respondent cannot include in the adjudication response any reasons for withholding payment unless those reasons have already been included in the payment schedule provided to the claimant.
Insert after section 21 (4):
If any such conference is called, it is to be conducted informally and the parties are not entitled to any legal representation.
Insert at the end of section 22 (1) (b):
, and
the rate of interest payable on any such amount.
Insert “(if any)” after “payment schedule”.
Omit section 22 (3). Insert instead:
The adjudicator’s determination must:
(a) be in writing, and
(b) include the reasons for the determination (unless the claimant and the respondent have both requested the adjudicator not to include those reasons in the determination).
If, in determining an adjudication application, an adjudicator has, in accordance with section 10, determined:
(a) the value of any construction work carried out under a construction contract, or
(b) the value of any related goods and services supplied under a construction contract,
the adjudicator (or any other adjudicator) is, in any subsequent adjudication application that involves the determination of the value of that work or of those goods and services, to give the work (or the goods and services) the same value as that previously determined unless the claimant or respondent satisfies the adjudicator concerned that the value of the work (or the goods and services) has changed since the previous determination.
If the adjudicator’s determination contains:
(a) a clerical mistake, or
(b) an error arising from an accidental slip or omission, or
(c) a material miscalculation of figures or a material mistake in the description of any person, thing or matter referred to in the determination, or
(d) a defect of form,
the adjudicator may, on the adjudicator’s own initiative or on the application of the claimant or the respondent, correct the determination.
Omit the sections. Insert instead:
In this section:
(a) the date occurring 5 business days after the date on which the adjudicator’s determination is served on the respondent concerned, or
(b) if the adjudicator determines a later date under section 22 (1) (b)—that later date.
If an adjudicator determines that a respondent is required to pay an adjudicated amount, the respondent must pay that amount to the claimant on or before the relevant date.
If the respondent fails to pay the whole or any part of the adjudicated amount to the claimant in accordance with section 23, the claimant may:
(a) request the authorised nominating authority to whom the adjudication application was made to provide an adjudication certificate under this section, and
(b) serve notice on the respondent of the claimant’s intention to suspend carrying out construction work (or to suspend supplying related goods and services) under the construction contract.
A notice under subsection (1) (b) must state that it is made under this Act.
An adjudication certificate must state that it is made under this Act and specify the following matters:
(a) the name of the claimant,
(b) the name of the respondent who is liable to pay the adjudicated amount,
(c) the adjudicated amount,
(d) the date on which payment of the adjudicated amount was due to be paid to the claimant.
If any amount of interest that is due and payable on the adjudicated amount is not paid by the respondent, the claimant may request the authorised nominating authority to specify the amount of interest payable in the adjudication certificate. If it is specified in the adjudication certificate, any such amount is to be added to (and becomes part of) the adjudicated amount.
If the claimant has paid the respondent’s share of the adjudication fees in relation to the adjudication but has not been reimbursed by the respondent for that amount (the
Omit the section. Insert instead:
An adjudication certificate may be filed as a judgment for a debt in any court of competent jurisdiction and is enforceable accordingly.
An adjudication certificate cannot be filed under this section unless it is accompanied by an affidavit by the claimant stating that the whole or any part of the adjudicated amount has not been paid at the time the certificate is filed.
If the affidavit indicates that part of the adjudicated amount has been paid, the judgment is for the unpaid part of that amount only.
If the respondent commences proceedings to have the judgment set aside, the respondent:
(a) is not, in those proceedings, entitled:
(i) to bring any cross-claim against the claimant, or
(ii) to raise any defence in relation to matters arising under the construction contract, or
(iii) to challenge the adjudicator’s determination, and
(b) is required to pay into the court as security the unpaid portion of the adjudicated amount pending the final determination of those proceedings.
Omit “(3) (b)” from section 26 (3). Insert instead “(3) (c), (d) and (e)”.
Omit “or 25” from section 27 (1). Insert instead “or 24”.
Omit section 27 (2). Insert instead:
The right conferred by subsection (1) exists until the end of the period of 3 business days immediately following the date on which the claimant receives payment for the amount that is payable by the respondent under section 15 (1), 16 (1) or 23 (2).
If the claimant, in exercising the right to suspend the carrying out of construction work or the supply of related goods and services, incurs any loss or expenses as a result of the removal by the respondent from the contract of any part of the work or supply, the respondent is liable to pay the claimant the amount of any such loss or expenses.
Insert after section 28 (1):
The Minister may:
(a) limit the number of persons who may, for the time being, be authorised under this section, and
(b) refuse an application under subsection (1) if authorising the applicant would result in any such number being exceeded.
Insert “(otherwise than on the ground referred to in subsection (1A) (b))” after “refused”.
Insert after section 28 (2):
An authorised nominating authority may charge a fee for any service provided by the authority in connection with an adjudication application made to the authority. The amount that may be charged for any such service must not exceed the amount (if any) determined by the Minister.
The claimant and respondent are:
(a) jointly and severally liable to pay any such fee, and
(b)
each liable to contribute to the payment of any such fee in equal proportions or in such proportions as the adjudicator to whom the adjudication application is referred may determine.
An authorised nominating authority must provide the Minister with such information as may be requested by the Minister in relation to the activities of the authority under this Act (including information as to the fees charged by the authority under this Act).
Omit section 29 (3). Insert instead:
The claimant and respondent are each liable to contribute to the payment of the adjudicator’s fees and expenses in equal proportions or in such proportions as the adjudicator may determine.
Omit the section. Insert instead:
An adjudicator is not personally liable for anything done or omitted to be done in good faith:
(a) in exercising the adjudicator’s functions under this Act, or
(b) in the reasonable belief that the thing was done or omitted to be done in the exercise of the adjudicator’s functions under this Act.
No action lies against an authorised nominating authority or any other person with respect to anything done or omitted to be done by the authorised nominating authority in good faith:
(a) in exercising the nominating authority’s functions under this Act, or
(b) in the reasonable belief that the thing was done or omitted to be done in the exercise of the nominating authority’s functions under this Act.
Insert at the end of section 31 (1) (d):
, or
in such other manner as may be provided under the construction contract concerned.
Omit the section. Insert instead:
The provisions of this Act have effect despite any provision to the contrary in any contract.
A provision of any agreement (whether in writing or not):
(a) under which the operation of this Act is, or is purported to be, excluded, modified or restricted (or that has the effect of excluding, modifying or restricting the operation of this Act), or
(b) that may reasonably be construed as an attempt to deter a person from taking action under this Act,
is void.
Insert after section 38 (3):
A further review of this Act (as amended by the Building and Construction Industry Security of Payment Amendment Act 2002) is to be undertaken by the Minister as soon as possible after the period of 12 months from the commencement of Schedule 1 [29] to that Act.
A report on the outcome of the further review is to be tabled in each House of Parliament within 3 months after the end of that period of 12 months.
Insert at the end of clause 1 (1):
Building and Construction Industry Security of Payment Amendment Act 2002
Insert after Part 2:
An amendment made to this Act by the Building and Construction Industry Security of Payment Amendment Act 2002 does not apply to or in respect of a payment claim served before the commencement of the amendment and any such payment claim is to be dealt with in accordance with this Act as if the amendment had not been made.
(Section 4)
Insert after section 3 (2):
A reference in this Act:
(a) to the carrying out of work includes a reference to construction work (within the meaning of the Building and Construction Industry Security of Payment Act 1999) carried out or undertaken to be carried out under a construction contract within the meaning of that Act, and
(b) to the supply of materials includes a reference to related goods and services (within the meaning of that Act) supplied or undertaken to be supplied under any such contract.
Insert after section 7 (1):
If an adjudication certificate within the meaning of the Building and Construction Industry Security of Payment Act 1999 has been filed as a judgment for a debt in accordance with section 25 of that Act, the court may, by order made on the application by the person who filed the adjudication certificate, issue a debt certificate in respect of the debt under this section.
0
0
0