MAGISTRATES COURTS OF QUEENSLAND
CITATION:
Project Delivery Managers v Keswick Developments P/L [2011] QMC 27
PARTIES:
PROJECT DELIVERY MANAGERS
(applicant)
v
KESWICK DEVELOPMENTS PTY LTD
(respondent)
FILE NO/S:
M1346/10
DIVISION:
Magistrates Courts
PROCEEDING:
Application for summary judgment
ORIGINATING COURT:
Magistrates Court at Townsville
DELIVERED ON:
31 January 2011
DELIVERED AT:
Townsville
HEARING DATE:
1 December 2010
MAGISTRATE:
Verra LP
ORDER:
The application for summary judgment is refused.
CATCHWORDS:
TRADE PRACTICES – BUILDING AND CONSTRUCTION – payment of building contract – Payment Claim
Building and Construction Industry Payment Act 2003, s 7, s 8, s 17, s18, s19
COUNSEL:
Morzone for applicant
Whitten for respondent
SOLICITORS:
Wilson Ryan and Grose Solicitors for applicant
Kelly Legal for respondent
The originating application seeks the following orders –
1. Judgment against the respondent in the sum of $124,664.07 as a liquidated debt pursuant to Section 19(2)(a)(i) of the Building and Construction Industry Payments Act 2004 (Qld) (the Act);
2. The respondent pay the applicant interest pursuant to Section 67P of the Queensland Building Services Authority Act 1991 (Qld) or in the alternative, pursuant to Section 47 of the Supreme Court Act 1995 (Qld);
3. The respondent pay the applicant’s costs of and incidental to this application.
In the applicant’s outline of submissions[1], a brief summary of events leading up to the application is set out under the heading of ’background’. That summary is as follows -
[1] P2
Background
On or about 9 October 2009, the applicant entered into a written Consultancy Agreement for construction work and related goods and services with the respondent to provide the services of construction management and project management for the various phases of construction of infrastructure on Keswick island.
The applicant provided construction work related consultancy services to the respondent pursuant to the Contract.
The applicant submitted regular invoices to the respondent pursuant to the Contract. The practice that was established by the parties was to send invoices by email to the email address as advised by the respondent.
In or around August 2010, the relationship between the parties deteriorated and the respondent failed to attend to the full payment of invoices submitted from or around June 2010. A number of defects have been alleged and the Contract has subsequently been terminated.
The respondent has engaged Kelly Legal as their solicitors and correspondence regarding a potential civil claim for damages greater than the amount owing to the applicant has been threatened and used as a reason for non-payment of the outstanding invoices.
The respondent failed to pay the last invoices. Consequently, in respect of the work subject of those invoices, on 22 October 2010 the applicant served the respondent with a Tax Invoice as a Payment Claim under the Building and Construction Industry Payments Act 2004 (Qld) for an amount of $124,664.07.
The respondent did not serve a Payment Schedule in response to the Payment Claim.
Correspondence following the deterioration of the relationship
Around August 2010 the relationship between the parties deteriorated and an exchange of correspondence followed.…
Continue reading Project Delivery Managers v Keswick Developments P/L
Sign in free to access the full text
- AGLC
- Project Delivery Managers v Keswick Developments P/L [2011] QMC 27
- Case
- [2011] QMC 27
- Decision Date
CaseChat Overview and Summary
The court considered the statutory framework provided by the Building and Construction Industry Security of Payment Act 1999 (NSW), which provides mechanisms for the swift payment of undisputed or partially disputed amounts claimed by suppliers and contractors. The court examined the specific terms of the building contract and the payment claims made by Project Delivery Managers. It assessed whether these claims complied with the requirements of the Act, including the need for the claims to be in writing, provide sufficient particulars, and be made within the prescribed time frames. The court also evaluated whether Keswick Developments had valid reasons to dispute the claims and whether those reasons met the statutory criteria.
The court found that Project Delivery Managers had not strictly complied with the requirements of the Act in making their payment claims. The claims were either not in writing, lacked sufficient particulars, or were not made within the required time frames. Consequently, the court held that the claims were not valid under the Act and Project Delivery Managers were not entitled to the amounts they sought. As a result, the application for summary judgment was refused, and the case was to proceed to a full hearing to determine the merits of the dispute. The court emphasised the importance of adhering to the statutory requirements to ensure that the payment scheme operates effectively and efficiently within the building and construction industry.
Orders
Orders of the court
The application for summary judgment is refused.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.