SUPREME COURT OF VICTORIA
COURT OF APPEAL
S EAPCI 2019 0133
| ASEA 1 PTY LTD (ACN 632 241 724) | Applicant |
| v | |
| RUDYARD PTY LTD (ACN 605 072 115) | Respondent |
---
| JUDGES: | KAYE and McLEISH JJA |
| WHERE HELD: | MELBOURNE |
| DATE OF HEARING: | 12 May 2020 |
| DATE OF JUDGMENT: | 13 May 2020 |
| MEDIUM NEUTRAL CITATION: | [2020] VSCA 122 |
| JUDGMENT APPEALED FROM: | [2019] VCC 1995 (Judge Woodward) |
---
PRACTICE AND PROCEDURE – Application for a stay of execution of judgment – No material risk that appeal rendered nugatory in absence of a stay – Refusal of a stay would not result in discontinuance of appeal – Respondent entitled to benefit of judgment – Application for a stay refused – Supreme Court (General Civil Procedure) Rules 2015 rr 64.39 and 66.16.
PRACTICE AND PROCEDURE – Costs – Application by respondent for security for costs – Real risk that costs order would not be satisfied – Security for costs would not result in discontinuance – Applicant ordered to provide security for costs in the amount of $35,000 – Supreme Court (General Civil Procedure) Rules 2015 r 64.38(2) – Australian Dream Homes Pty Ltd v Stojanovski [2016] VSCA 38, Timbercorp Finance Pty Ltd (in liq) v Tomes [2015] VSCA 322, Jafari v 23 Developments Pty Ltd [2019] VSCA 16 referred to.
---
| APPEARANCES: | Counsel | Solicitors |
| For the Applicant | Mr H Foxcroft QC with Mr A Blair | Welner Lawyers |
| For the Respondent | Dr M Wolff | Noble Lawyers Pty Ltd |
KAYE JA
McLEISH JA:
The respondent (‘Rudyard’) brought a proceeding by Originating Motion in the County Court against the applicant (‘ASEA’), by which it applied, by summons, for judgment under s 16(2) of the Building and Construction Industry Security of Payment Act 2002 (‘the Security of Payment Act’). The claim by Rudyard arose out of works performed by it pursuant to a contract with ASEA dated 10 April 2019 for a proposed 28 residential apartment development in Plenty Road, Preston. The judge, who heard the claim, gave judgment in favour of Rudyard in the sum of $343,750 (including GST) together with interest at the rate of 20 per cent per annum from 23 July 2019.[1] ASEA has sought leave to appeal against the whole of the decision.
[1]Rudyard Pty Ltd v ASEA 1 Pty Ltd [2019] VCC 1995 (Judge Woodward).
The Court has before it two applications, namely:
(1)An application by ASEA for a stay of the order made by the judge.
(2)An application by Rudyard that ASEA give security for Rudyard’s costs relative to the application for leave to appeal in the amount of $75,000.
Background
The claim by Rudyard was based on three payment claims it had made on ASEA, pursuant to s 14 of the Security of Payment Act, totalling $343,750 (including GST), dated 24 April, 25 May and 29 June 2019 respectively. ASEA opposed judgment on three principal bases. First, it contended, the payment claims had not been properly served on ASEA. Secondly, it was contended that the payment claims each…
Keep reading for free
Create a free CaseChat account to read ASEA 1 Pty Ltd v Rudyard Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2020] VSCA 122
- Decision Date
CaseChat Overview and Summary
The court found that there was no material risk that the appeal would be rendered nugatory if the stay was not granted, and that refusal of a stay would not result in the discontinuance of the appeal. The respondent was entitled to the benefit of the judgment. Therefore, the application for a stay of execution was refused. The court relied on the relevant rules of the Supreme Court (General Civil Procedure) Rules 2015 and considered relevant case law.
Rudyard Pty Ltd applied for security for costs, arguing that there was a real risk that the costs order would not be satisfied if the appeal was unsuccessful. The applicant argued that security for costs would result in the discontinuance of the appeal. The court found that security for costs would not result in the discontinuance of the appeal, and ordered the applicant to provide security for costs in the amount of $35,000. The court referred to relevant case law and the relevant rule of the Supreme Court (General Civil Procedure) Rules 2015.
The court's final orders were that the application for a stay of execution of judgment was refused and that the applicant was ordered to provide security for costs in the amount of $35,000.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established